Failure case histories
Mt. Beni rockslide
On 28 December 2002, a landslide occurred on the Eastern flank of Mt. Beni (Central Italy), on a slope which had been previously exploited by quarrying activity until the 1980s (Fig. 1a). The failure mechanism, involving jointed massive basalts overlying ophiolitic breccias, was characterized by a volume of about 500,000 m3 and has been classified as a rockslide/rock topple (Gigli et al. 2011). Several distometric bases were put in place along the perimetral crack (Fig. 1b) and recorded cumulative displacements since April 2002. Increasing rates, ranging from few millimetres up to few centimetres per day, were detected by most of the devices starting from September 2002 until the collapse of 28 December. According to eyewitnesses, the event began at about 4:30 a.m. local time. Gigli et al. (2011) made particular reference to distometric base 1-2, since this recorded the longest and most consistent progressive acceleration in the time series of displacements; they ultimately calculated a failure forecast according to the linear extrapolation of the trend in the inverse velocity plot, which could be distinguished since 2 August already (Fig. 2a). Although it provides a good estimate that failure is going to occur, fitting of these data gives a T
f
which anticipates the actual failure (T
af
) by 4 days and a half (ΔT
f
= T
af
-T
f
= 4.5), as is also shown by the related life expectancy plot in Fig. 3a. Life expectancy plots are very useful tools to examine the course with time of the T
f
predictions, updated on an on-going basis each time a new measurement is available (Mufundirwa et al. 2010; Dick et al. 2014).
Inverse velocity plots for data filtered by means of SMA, LMA and ESF are given in Fig. 2. In this case, short-term moving average smoothing eliminates the small steps in the raw data curve, yielding a significantly improved T
f
(ΔT
f
= 1.1); on the other hand, long-term moving average, despite determining a slightly better fitting, generates a considerably negative ΔT
f
(−4.3) and most importantly delays the identification of the OOA point by 1 month. The latter aspect is verified even more for the exponentially smoothed velocities. Their poor linearity would have also made their use in the emergency scenario quite troublesome, even if, in retrospect, it is found that the last T
f
value is highly accurate. Respective life expectancy plots (Fig. 3) display additional, valuable information: All datasets, beside velocities filtered by means of ESF, converge parallel to the actual time to failure line. However, raw data consistently give anticipated forecasts of the time of failure, whereas SMA allows forecasts to get decisively closer to the actual failure line since November 21. In Fig. 3c, predictions approach the actual values already on late October but finally diverge towards significantly negative ΔT
f
, which is something to avoid in risk management of geological hazards (concept of “safe” and “unsafe” predictions, Mufundirwa et al. 2010). Exponential smoothing produces a reliable T
f
in correspondence of the last measurement, but the predicted time to failure line does not have a regular pattern, if compared to the others.
A slightly different, but really interesting example from the Mt. Beni rockslide, which is not reported in Gigli et al. (2011), is given by displacement rates measured at the distometric base 15-13. Especially in its last phase, the final acceleration (Fig. 4a) is quite irregular (i.e. progressive-regressive wall movement; Newcomen and Dick 2015). Moreover, it seems to have a slightly concave shape with respect to base 1-2, possibly suggesting α lower than 2. We may thus refer these features to one or more of the natural noise factors. The reliability of the linear fitting of the inverse velocity graph results to be strongly affected and produces a time of failure forecast which precedes the last actual measurement acquired on December 20, hence well ahead of T
af
(approximately 8 days, Figs. 4a and 5a). Here, SMA does not exhibit a noticeable improvement in terms of smoothing, and the consequent T
f
is equivalent to T
f
from raw data. Again, exponential smoothing introduces irregularity on the plot and delays the OOA point. In this case, filtering by means of the long-term moving average produces better results under every aspect: OOA is found at the same time than in the raw data, steps in the inverse velocity line are eliminated (thus improving also the degree of fitting) and accuracy of T
f
is much higher (ΔT
f
= 2); the related life expectancies converge close to the actual time to failure line already from late November, 1 month before the event. On the contrary, predicted lines from Fig. 5a, b are horizontal in their first section and ultimately do not get near the actual expectancy line.
Summarizing, the Mt. Beni case study, as analysed here, showed that linear fitting of unfiltered inverse velocity data, although surely constituting an indicator of the on-going acceleration of the slope movements, produced T
f
which anticipate by several days the actual time of collapse. Smoothing data with simple moving average algorithms allowed to benefit from improved qualities of fitting and of T
f
predictions. In particular, long-term moving average gave optimal results for the noisier, less linear (α < 2) time series from distometric base 15-13, while short-term moving average performed better when applied to the more regular measurements registered by distometric base 1-2. Exponential smoothing did not produce satisfying improvements to these data.
Vajont landslide
The 1963 Vajont disaster in Northeast Italy has been one of the most catastrophic landslides in history, and many authors have studied the event under different perspectives. Without entering into the complex details of the failure mechanism, as these have already been largely described and discussed (and still are), the collapse occurred at about 10:39 p.m. local time on 9 October 1963, when a 270 million m3, mostly calcareous rock mass detached from the slope of Mt. Toc and slid at 30 m/s into the newly created Vajont reservoir (Fig. 6). The consequent tsunami wave overtopped the dam and killed 2500 people in the villages downstream. The pre-failure movements of the unstable material were strongly controlled by the water level in the valley floor and creeping motions began to be observed immediately since the creation of the reservoir (Havaej et al. 2015). The final chain of events started with the April 1963 reservoir filling cycle; the final rupture followed 70 days of downslope accelerating movements (Helmstetter et al. 2004). According to measurements from four benchmarks installed at different positions on the mountain slope, pre-failure velocities were extremely high: Among these, benchmarks 5 and 63 in particular were the ones which showed a clear state of accelerating creep, with displacement rates ranging from ≈5 mm/day up to over 20 cm/day (Fig. 7a , b) and a total cumulative deformation of a few meters (Muller 1964). In Fig. 7, measurements from Mt. Beni are also plotted in order to show the different orders of magnitude in the displacement between the two landslides (Fig. 7a) and the different shape of the curves (Fig. 7b). Distometric base 1-2 of Mt. Beni indeed shows significantly lower rates relatively to both Vajont benchmarks. Data from base 15-13 are instead in the same order of magnitude, but the acceleration is “stepped” rather than exponential. This further indicates the need to perform high-degree smoothing on this time series (Fig. 4).
In Fig. 7c, the inverse velocity plot for the unfiltered measurements of benchmark 63 is shown. Even though a slight step-like pattern can be noticed, the graph is remarkably linear as a whole and, most importantly, the linear trend line fits particularly well the last points leading up to failure. Therefore, if recorded velocities are regularly high since the initial stages of acceleration, i.e. A ≈ 0.04 (as in Vajont data; Voight 1988) or lower, and if the assumption of α = 2 is consistently satisfied, it is suggested not to apply any strong data filtering, in order to avoid loss of sensitivity with regard to actual downward trends. At most, linear fitting of short-term averaged velocities may also be conducted in parallel to the fitting procedure of the original data. For benchmark 63, SMA yields a slightly better fitting and a slightly more accurate T
f
(ΔT
f
= 0.3) with respect to results from the original data (ΔT
f
= 1.1, Fig. 7d). Conversely, inverse velocity plot from benchmark 5 (Fig. 8a) seems to have a pattern quite similar to that of distometric base 15-13 at Mt. Beni (Fig. 4a): After the fourth point of the dataset, the trend appears to assume a certain concavity (α < 2) and consequently, as opposed to benchmark 63, the last velocity points before failure are not well fitted by the linear regression line. This causes again a premature T
f
prediction, which anticipates also the time of the last measurement on 8 October (ΔT
f
= 2.7, Fig. 8a). Excellent linearization is produced by LMA and ESF (Fig. 8), with the first one also determining an extremely accurate T
f
(ΔT
f
= 0.1). From the relative life expectancy plot, it can be seen that a correct prediction about the time of failure could have been given about 10 days earlier than the actual event; in further support of their reliability, the forecasts of the time of failure remained consistent after each of the last six displacement measurements. On the other hand, life expectancies from the raw data are always some days off the actual time-to-failure line.
Again, as in the Mt. Beni case study, it is not argued that velocities from benchmarks at Mt. Toc were not indicating a clear accelerating trend towards slope collapse. Nevertheless, it is found out that the accuracy of T
f
predictions could be improved by appropriately smoothing out data and thus linearize the respective inverse velocity plots. Equivalently to distometric base 15-13 at Mt. Beni, results showed that, for fast-moving slopes, if α < 2, it is suggested to filter data with a long-term moving average; instead, if α ≈ 2, it seems more convenient to proceed with the regular inverse velocity analysis performed on an on-going basis or, at most, to filter data with a short-term moving average.
Stromboli debris talus roto-translational slide
On 7 August 2014, a debris talus located below the Northeastern crater (NEC) of Stromboli Volcano was affected by a roto-translation slide, evolving into a rock avalanche on a 30°–45° steep slope called “Sciara del Fuoco”, and followed by the opening of an eruptive vent localized at ≈650 m a.s.l. (≈100 m below the NEC, Di Traglia et al. 2015; Rizzo et al. 2015; Zakšek et al. 2015). Debris cone material likely reached the sea, but tsunami waves were not recorded. Growth stages of this debris talus at Stromboli are a common phenomenon related to the explosive activity, which produces accumulation of volcaniclastic debris around the active craters (Calvari et al. 2014). Contrariwise, the roto-translational slides occurred at the onset of the 2002–2003, 2007 and 2014 flank eruptions, characterized by magma propagation from the central conduit towards the NEC (Di Traglia et al. 2014, 2015). The debris talus is composed by loose volcaniclastic material, prevalently breccias alternating with tuff, lapillistones and thin (<2–3 m) lava flows (Apuani et al. 2005). The NEC area has been continuously monitored by a Ground-Based Interferometric Synthetic Aperture Radar (GBInSAR) system (Di Traglia et al. 2014, Fig. 9). The latter recorded an increase in the line-of-sight displacement rate of the debris talus starting from 30 May 2014. The curve of deformation rate for this period presents a high degree of noise (Fig. 10a). This is mostly due to the dynamics of the magma within the volcanic edifice: At Stromboli, successive cycles of filling and emptying of the plumbing system can cause phases of inflation and deflation of the entire crater area, thus adding natural noise to the displacements of the debris talus. For this reason, strong negative velocities are displayed at times in Fig. 10a and a definite raise in rates can be observed only from late July. This final acceleration was made up of relatively low-medium rates, from few millimetres per day up to a peak velocity of 40.4 mm/day on 6 August 2014. Since 04:01 GMT on 7 August 2014, the GBInSAR recorded complete loss in coherence in the debris cone sector, consistently with a fast movement of the summit area (i.e. T
af
).
In Fig. 10a, the OOA is found about only 1 week before the slope collapse. Hence, it was not possible to produce with confidence a failure prediction, as only few measurements could be collected between OOA and T
af
(Fig. 10b). Data filtering, eliminating short-term fluctuations and highlighting longer-term cycles, is here of invaluable help, as it may allow an earlier detection of the OOA point. With LMA (Fig. 11), the latter is found on 27 July, but the inverse velocity line appears to be excessively smoothed out, causing a late T
f
prediction (ΔT
f
= −1.7); ESF generates the OOA on 24 July and provides a slightly better failure forecast (ΔT
f
= −1.3), despite a worse fitting (R
2 = 0.77). SMA undoubtedly produces, in this case, the best results overall (Fig. 11a, b): A trend towards the x-axis begins already on 23 July, the level of fitting is high (R
2 = 0.88) and T
f
is extremely reliable (ΔT
f
= −0.4). In fact, from the life expectancy plot in Fig. 11b, it can be seen that a roughly correct time of failure forecast could have been made consistently since 3 August, approximately 4 days before the actual collapse of the debris talus. Similarly to the time series of distometric base 1-2 at Mt. Beni, it is found that, when accelerations towards failure are characterized by moderate velocity values, it is more reliable to filter data by means of SMA. This is even more important for the Stromboli case study, where failure is usually anticipated by a very brief final acceleration phase and therefore an early identification of the OOA is highly needed. A short-term moving average has higher sensitivity towards trend changes in the data and thus appears to be the most helpful mean of analysis, with regard to this specific issue.
Collapse of the medieval city walls in Volterra
Volterra is one of the most well-known cultural heritage sites in Central Italy. The town, originated as an Etruscan settlement, later became an important medieval centre. During this period, the perimeter walls, which still surround the town, were built. Some of these have their foundation over cemented sand deposits, which sit on top of the stratigraphic column and overlap a formation made up of marine clays. On 31 January 2014, a 35-m long and 9.5-m high portion of the historic walls suddenly collapsed. After this event, a GBInSAR system was installed to monitor the deformation of the entire SW side of the city walls (Pratesi et al. 2015; Fig. 12). Since late February, generally high displacement rates of another portion of the walls were captured; after an initial phase of roughly linear movements (≈2 mm/day), finally velocities increased decisively on 1 March (Fig. 13a) and, shortly thereafter, the area completely collapsed in the early afternoon of 3 March 2014. Pratesi et al. (2015) attributed the source of the instabilities to the accumulation of water above the impermeable clays and to the resulting overpressure exerted on the upper incoherent sands. This was confirmed by the fact that high movement rates were registered only at the bottom of the wall, in agreement with a slightly roto-translational motion caused by loss in base support.
The Volterra case study is of particular interest, as it does not strictly imply a failure on a natural slope, but rather on a man-made structure built on unstable terrain. This does not necessarily constitute a limit for INV, as Voight (1989) affirms that the model is thought to be applicable to a variety of fields where mechanical failure is involved, including earth sciences, materials science and engineering. However, the apparent lack of a linear trend toward zero in the inverse velocity plot of the unstable part of the walls discouraged its use during the terminal phase of the emergency (Fig. 13b). Following the recurrence of above-average rate values (from ≈2–3 to 19.4 mm/day), authorities were informed about the high probability of an imminent collapse, but a T
f
estimation process was not carried out.
It can be argued that accelerations affected by strong deviation from the ideal inverse velocity linearity are those in more need of high-degree smoothing. In fact, SMA and ESF (Fig. 13c, d) do not generate useful improvements from raw data in terms of readability of the inverse velocity plot and again a T
f
prediction would not be advised. Contrariwise, LMA filter provides a clear OOA and an obvious linear trend line to the x-axis (R
2 = 0.98, Fig. 13e). Results show that final T
f
is just few hours earlier than T
af
(ΔT
f
= 0.5 days). The relative life expectancy plot indicate that roughly accurate forecasts of the time of wall collapse could have been made as soon as 27 February, as all the subsequent points forming the predicted time-to-failure line lie in close proximity to the actual time-to-failure line.
Therefore, if rate values seem to diverge from the expected behaviour of the INV model, it is suggested to try performing time of failure analyses only following the application of strong filters to the data. The usefulness of this process is even greater if relatively low movement rates are involved in the acceleration phase and, consequently, little variations in velocity values can give rise to confusing spikes in the inverse velocity plot.
Effect of noise on the reliability of T
f
predictions
From the analysis of failure case histories, it resulted that data smoothing can provide several types of advantages, depending on the properties of the velocity curves: When a general trend toward failure is already evident in the raw data (e.g. Mt. Beni, Vajont), it is still possible to obtain more reliable T
f
predictions; when measurements have a high level of noise and the final phase of acceleration is short-lived (e.g. Stromboli debris talus), an earlier OOA can be identified; when data seem to imply that linear INV is not applicable (e.g. Volterra), it might be possible to deduce the obscured trend toward failure, if present. Particularly in the last two instances, applying filters could be decisive in allowing, in practice, the use of INV. Among the considered examples, it was noticed that measurements at Stromboli and Volterra were affected by high noise intensity and strongly needed to be filtered in order to apply the method, while at Mt. Beni and Vajont, the level of disturbance was smaller and affected just the reliability of T
f
predictions.
With the aim of performing additional analyses, we now simulate the introduction of random sets of noise on two ideal time series which, initially, are created in accordance to Voight’s model for rates approaching failure. These series are calculated based on the equations that better approximate the actual trends of displacements registered at Mt. Beni (distometric base 1-2) and Vajont, meaning that the parameters A and α must be estimated accordingly. As reckoned by Voight (1988), this can be accomplished by plotting log-velocity against log-(t
f
–t). Such plot for data from distometric base 1-2 at Mt. Beni is shown in Fig. 14a. Solving for the equation of the best-fit line, one obtains A = 0.102 and α = 1.994, remarkably close to the condition of perfect linearity; approximating for α = 2 yields A = 0.099. Since the general Voight’s equation for rate at any given time prior to failure is equivalent to the general Saito expression for creep rate \( \overset{.}{\varepsilon } \) (Voight 1988; Saito 1969)
$$ \overset{.}{\varepsilon }=\mathrm{E}{\left({t}_f-t\right)}^{-n} $$
(5)
where E = [A(α − 1)]1/(1 − α) and n = 1/(α − 1), data are well described by v = 10(t
f
− t)− 1 as proved in Fig. 14b. For displacements at Mt. Toc (Vajont), Voight (1988) found that rates can be suitably expressed by v = 27(t
f
− t)− 1 with A = 0.037 and α = 2. By substituting in the two equations values of time-to-failure from 60 to 1, we simulate rates of two slopes with similar behaviour to Mt. Beni and Mt. Toc and in agreement with a condition of perfect linearity in the inverse velocity plot.
As previously mentioned, we then add to these series of velocities several sets of random noise, meaning both IN and NN. We consider IN as additive noise, while NN as multiplicative noise. The first is in fact related to the precision of the monitoring device, which is typically not dependent on the amount of movement occurred (we hypothesize an instrumental accuracy of ±1 mm). Conversely, natural noise, which is determined by the factors disrupting the ideal linearity of slope accelerations (i.e. variations of A and α), is proportional to the stage of failure. This can be easily seen in (5): Equivalent changes of A and α will cause bigger differences between actual and theoretical velocities as the time-to-failure decreases. Also, in INV, velocity at failure is considered infinite, an assumption which obviously is not verified in nature. Values of “disturbed” velocities are thus computed as
$$ \overline{v}=v+{R}_r+\left(v\cdot {R}_f\right)\cdot {R}_r $$
(6)
where R
r
is a randomly generated number between [−1, +1] and R
f
is a fixed constant which indicate the applied intensity of natural noise. Certainly, (6) is a simplification of an otherwise very complex and unpredictable phenomenon; nonetheless, it can stand as a quick and generally effective approximation for the purposes of this analysis.
According to this approach, examples of a strong NN component (R
f
= 0.2) added to the series of ideal rates for Mt. Beni and Mt. Toc (Vajont) are described, and the effects of data smoothing in improving the reliability and usability of the inverse velocity method are thus further evaluated. Mt. Beni (1-2) and Vajont both represent excellent cases of slope acceleration prior to failure. Mt. Beni was characterized by noticeably lower velocities (i.e. higher value of A) with respect to Mt. Toc. It follows that, when an equal noise intensity is introduced to the respective rate curves, the effects on the analysis of inverse velocity plots will be different. This can be easily observed in Figs. 15 and 16. Graphs have been divided in two sections, before and after an identified OOA/TU point. As previously said, this marks either the point after which a trend toward the x-axis can be clearly defined or a change in the trend slope and usually occurs together with a reduction in data noise (Dick et al. 2014).
Simulation for Mt. Beni (Fig. 15a) shows that, over 60 observations, an OOA can be probably identified at t = 29 and that a reliable T
f
prediction could be performed by using measurements thereafter. Scatter in the first half of the plot would not allow, in a real-time monitoring scenario, to safely determine a trend. This is also confirmed by the low value of R
2. SMA and ESF both yield no great improvement in terms of scatter in the first part of the dataset and the OOA is found basically at the same time than in the original series. Conversely, LMA generates better smoothing across the entire series and a clear OOA is found already at t = 14, with a final ΔT
f
= 0.5. LMA thus produces, in this case, notable benefit to the INV analysis.
The Vajont simulation gives different points of interest: The presence of an overall trend toward zero remains generally clear and T
f
predictions could be initiated quite early in the series (Fig. 16a). Probably, a TU or OOA would be safely found at t = 17 or thereabout. Similarly to what suggested in the real case history of benchmark 63, LMA smooths out excessively the inverse velocity line and, consequently, a sensibly negative ΔT
f
is found (−2.5). Both LMA and ESF have TU/OOA at t = 14. Instead, SMA produces a reliable T
f
(ΔT
f
= 0.6) and the earliest OOA at t = 11.
Several other simulations, with different sets of randomly generated values of noise, were performed. Although the random nature of the process can sometimes yield slightly different results with respect to the ones presented here, the same general behaviour was observed.