Skip to main content
Log in

Completing projects according to plans: an earned-value improvement index

  • Theoretical Paper
  • Published:
Journal of the Operational Research Society

Abstract

To finish in accordance with its originally planned duration or cost, a project that is not meeting its schedule or budget requires improved performance in the work that remains. This paper shows how to calculate the new productivity in terms of the average earned-value performance over the first part of a project, and it shows how the new productivity rate depends on the fraction of tasks completed. The completed task fraction beyond which recovery is impossible is calculated, and a point beyond which recovery is highly unlikely is suggested. Using an analytic approximation for an S-curve, these calculations are transformed into a temporal domain.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Figure 1
Figure 2

Similar content being viewed by others

References

  • Eden C et al (2000). On the nature of disruption and delay (D&D) in major projects. J Opl Res Soc 51: 291–300.

    Article  Google Scholar 

  • Brooks Jr FP (1995). The Mythical Man-Month, anniversary edition. Addison-Wesley: Boston.

    Google Scholar 

  • Graves SB (1989). Why costs increase when projects accelerate. Res Tech Mngt 32 March–April: 16–18.

    Google Scholar 

  • Cooper KG (1994). The $2000 hour: how managers influence project performance through the rework cycle. Proj Mngt J 25: 11–24.

    Google Scholar 

  • Williams TM et al (1995). The effects of design changes and delays on project costs. J Opl Res Soc 46: 809–818.

    Article  Google Scholar 

  • Fleming QW and Koppelman JM (2000). Earned Value Project Management, 2nd edn. Project Management Institute, Inc.: Newtown Square, Pennsylvania.

    Google Scholar 

  • Project Management Institute Standards Committee (2003). A Guide to the Project Management Body of Knowledge (PMBOK®), 3rd edn. Project Management Institute, Inc.: Newtown Square, Pennsylvania.

  • Anbari F (1980). An operating management control system for large-scale projects. Presentation given to American Institute for Decision Sciences, Ninth Annual Meeting, Northeast Regional Conference, Philadelphia.

  • Kerzner H (2003). Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 8th edn, Chapter 15.5. New York: John Wiley and Sons, Inc., p 580f.

    Google Scholar 

  • Zwikael O et al (2000). Evaluation of models for forecasting the final cost of a project. Proj Mngt J 31: 53.

    Google Scholar 

  • Cioffi DF (2005). Designing project management: a scientific notation and an improved formalism for earned value calculations. Submitted to the Int J Proj Mngt accepted and in revision.

  • Cioffi DF (2005). A tool for managing projects: an analytic parameterization of the S-Curve. Int J Proj Mngt 23: 215–222.

    Article  Google Scholar 

Download references

Acknowledgements

I thank Homayoun Khamooshi for a careful reading and for catching an error in an earlier version, and an anonymous referee with helping place the material in a better context.

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to D F Cioffi.

Appendix A

Appendix A

Equations for the S-Curve solution

The normalized S-curve equation presented here, y(β) (where β is normalized time), asks the user to choose two parameters: 1) the slope of the rise in the middle part of the S-curve (r 0.67) and 2) the time at which approximately half the funds have been expended (β 1/2).12 The following set of expressions defines an S-curve in terms of these two values

where

and

As we desire, y=1 at the end of a project (yy >1 afterwards), and at β1/2, y=y /2≈0.5. In the absence of any other information, choosing r 0.67=1 (two-thirds of the rise takes place in the middle third of the S) and β 1/2=0.5 yields the following explicit equation:

The above equation, used in the calculation in the main text, produces a typical S-curve. Increasing r 0.67 would sharpen the rise and flatten the curve at its two ends, but these changes would not change the nature of the results described above.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Cioffi, D. Completing projects according to plans: an earned-value improvement index. J Oper Res Soc 57, 290–295 (2006). https://doi.org/10.1057/palgrave.jors.2602007

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1057/palgrave.jors.2602007

Keywords

Navigation