Introduction

Medical devices are special products that are directly related to patient’s health and lives (Lin et al. 2014). Bringing a new medical product successfully from the bench to beside is highly complex and depends heavily on the implementation of rigorous processes. These processes need to allow developers to optimally phase development, testing, and other activities, and to successfully execute on the manifold requirements of third parties, including regulators and payers. These additional requirements set medical product/device development apart from the development of other products (Pietzsch et al. 2009).

According to I.S. EN ISO 14971 (2012), medical device means any instrument, apparatus, implement, machine, appliance, in vitro reagent or calibrator, software, implant, reagent, material or other similar or related article, intended by the manufacturer to be used, alone or in combination, for human beings for one or more of the specific purposes:

  • diagnosis, prevention, monitoring, treatment or alleviation of disease,

  • diagnosis, monitoring, treatment, alleviation of or compensation for an injury or disability,

  • investigation, replacement, modification or support of the anatomy or of a physiological process or state,

  • supporting or sustaining life,

  • control or support of conception,

  • disinfection or sterilization of any of the above-mentioned devices,

  • providing information for medical purposes by means of in vitro examination of specimens derived from the human body, and which does not achieve its principal intended action by pharmacological, immunological or metabolic means in or on the human body; but which may be assisted in its function by such means.

Medical device classification

North American Industry Classification System (NAICS) has classified the medical devices industry that is covered by the Office of Health and Consumer Goods (OHCG) as illustrated in Fig. 1.

Fig. 1
figure 1

Medical device classification (NAICS classification represented in graphical form)

USFDA did analysis based on the data available with them and interviews conducted with the thought leaders. It reported that medical device companies lack expertise in developing risk assessment and mitigation plans during the product development phases. This significantly impairs their ability to monitor and control quality through the manufacturing and the post-production phases. Risk assessment tools like design and process failure mode and effects analysis (FMEAs) are often not developed, applied appropriately (Understanding Barriers to Medical Device Quality, FDA report, Oct. 31, 2011).

Failure mode and effect analysis (FMEA) is the commonly used technique in RM of medical products/devices. It has got several drawbacks; this paper uses fuzzy FMEA to compare results with traditional FMEA for RM in MPD process. However, FMEA and ISO 14971 approaches are rarely carried out in an integrated manner, either in theory or in practice. Risk analysis and failure analysis in industry lack guidance as well as showcase (Chan et al. 2012). In particular, FMEA is often implemented to improve device reliability and quality, as well as to correct potential problems (with an intention to satisfy the ISO9000 and QS9000 requirements), while ISO 14971 is a mandatory requirement for the medical devices manufacturer (Chan et al. 2012). This paper discusses case study of MPD process. The objectives of study are:

  • to get an insight into MPD process,

  • to map the existing MPD process of the case under consideration into customized phase gate process,

  • to identify risks during five phases of MPD and categorize them based on source of occurrence,

  • to prioritize the risks using traditional FMEA and fuzzy FMEA,

  • to compare results of traditional FMEA and fuzzy FMEA,

  • to categorize risks based on criticality and propose a risk mitigation plan.

This paper is further organized as follows: section two reviews the literature. Section three details the research methodology adopted. Phase-wise risk identification, ranking and analysis using traditional FMEA and fuzzy FMEA are discussed in section four. Section five presents risk treatments and risk mitigation model. Results, discussion, conclusion and future scope are discussed in section six.

Literature review

This paper discusses a case of MPD process risk identification, analysis and management in detail. Different authors have carried research work related to risks in other PD and MPD which are discussed here.

Product development process risks

As compared to MPD risks, risks in other PD have been studied more.

Chalupnik et al. (2009) focused on the approaches which aimed to mitigate the likely impact of process risks on product performance without removing the sources of risks. Browning et al. (2002) specified that the goal of PD process is to produce a recipe that satisfies requirements. They developed a risk value method to integrate approaches as technical performance measure tracking charts and risk reduction profiles. Unger and Eppinger (2011) discussed PD processes and proposed PD process design method. The risk categories and steps for risk management also have been discussed. Zhang and Chu (2011) applied fuzzy Risk priority number (RPN)-based method to ensure the robustness against uncertainty of a new horizontal directional drilling machine. They mentioned that risk analysis is very important in reducing the failures. Tang et al. (2011) developed a risk management framework and applied it to assess customer perception risk in NPD process. Choi and Ahn (2010) proposed a risk analysis model to determine the risk degrees of the risk factors occurring in PD process. They used both fuzzy theory and Markov processes on concurrent engineering basis. Kayis et al. (2006) developed a user interactive, dynamic risk management software package which was commercialized and deployed successfully by a major international manufacturer. Thunnissen (2003) classified the risks and uncertainties in detail. Kayis et al. (2007) identified and quantified the most prominent risks in the product life cycle. They also developed five algorithms for finding the feasible solution for mitigation of the risks. Cooper (2003) presented a practitioner view of the desired characteristics of tools to support NPD and suggested a need to construct a robust risk management framework. The details of the literature reviewed are as shown in Table 1.

Table 1 Details of the literature referred

Medical product development risks

A small fault or mistake made in our daily life might not be so severe but in the health care domain, the smallest mistake in development can make the difference between life and death (Lindholm and Host 2009). ISO 14971 is dedicated for RM of medical devices, while United States Food and drug administration (USFDA) strongly implies the link in their quality system regulation. It is a complete guide for RM consisting of several steps. There is sparseness of literature on the development process RM of medical products.

Details of the research related to risks in medical products are given in Table 2.

Table 2 Details of research related to medical product risks

It is recommended that, RM should be done through PD process (ISO 14971:2012; Schmland 2005).

Materials and methods

This paper has employed a descriptive method, i.e., a case study for research as explained by Yin (1984). The objective of this study is to identify risks during different stages of development of a dental product, i.e., dental cement. The case study method has been selected because for this type of research, direct access to the operational and technical decision makers of the company is required. This facilitates the collection of data through the product developers of the company. The flow of the research work is depicted in Fig. 2.

Fig. 2
figure 2

Methodology used for research

History

The case under study has been conducted with a dental manufacturing company who is into existence for more than 10 years. It manufactures total sixteen dental products. The company falls under the category of small and medium sized manufacturing enterprises (SMEs) which are under tremendous pressure due to free market economy, rapid technological development and continuous change in customer demands (Islam and Tedford 2012). In addition to these, medical product manufacturing companies have to fulfill the regulatory requirements.

The product

The dental cement falls under the category of dental equipment and supplies as per NAICS classification (refer Fig. 1). It is used as a temporary filling to aid recovery of an inflamed pulp. It acts as a protective base beneath the amalgamation restoration. For temporary application, it is used as luting agent for crowns of different materials.

Data collection

Two methods are used for data collection:

  1. 1.

    Interviews with the development team.

  2. 2.

    Referring the documents such as—technical reports, minutes of meeting, etc.

Analysis

The detailed analysis of the product under study was carried out. Following points were noted during discussion and the document references:

  1. 1.

    This product was under development since the past 8 months.

  2. 2.

    There were complaints by the end users regarding the performance, hence modifications were undertaken.

It was been regarded as a good candidate to consider as a case to identify important risks during MPD process.

The development team consisted of:

  • The managing director of the company.

  • Two dentists.

  • Two manufacturing engineers.

The existing product development process was studied and is depicted in Fig. 3.

Fig. 3
figure 3

Existing process of MPD

The company was not using any specific model for the development of the product. Probably the same thing what many small and medium medical product manufacturing companies do?

Process mapping

The next part of the work was to prepare the development team for identification of risks during different phases of MPD. With detailed understanding of the current development process (refer Fig. 3), it was mapped with a five phase process.

Medical product development phases and risk management

Five phases of MPD are considered (Pietzsch et al. 2009). Lindholm and Host (2009) identified risks using controlled experiments for procurement of medical product. Cagliano et al. (2011) used risk breakdown structure to identify risk sources. This paper identifies the risks involved in MPD process through the expertise of development team members. The activities at each stage and the associated risks are identified as shown in Table 3 along with the risks identified during each stage.

Table 3 Activities and risks during the phases of medical product development process

The risk identification is the most important phase of this work. A total of twenty most prevalent risks during five phases of MPD are identified. These risks are classified into three categories: technical, strategy and market risks. This categorization is done based on the expert’s opinion, source of risks and the literature referred (refer Table 4). These categories contribute individually and interactively to the product performance (Mu et al. 2009).

Table 4 Technical and market risks addressed by researchers

The three categories are described as:

  1. 1.

    Technical risks: the risk of not meeting technical and functional performance requirements, it occurs because of technical uncertainty.

  2. 2.

    Strategy risks: the risks due to operating strategy of the company and are mostly associated with culture and structure of the company.

  3. 3.

    Market risks: even in the absence of risks due to technology when the device fails to satisfy customer needs, it is regarded to as market risk.

Table 5 shows the classification of the risks into three categories and the coding.

Table 5 Risks coding and categorization based on source of occurrence

It can be seen from Table 5 that the technical risks contribute most to the MPD process, followed by strategy risks and market risks, respectively. This research uses two approaches for risks analysis and prioritization: traditional FMEA and fuzzy FMEA, which are discussed in detail in the next subsections.

Failure mode and effect analysis (FMEA)

FMEA is a risk assessment tool to evaluate and mitigate the potential failures in systems, processes, designs or services (Lin et al. 2014). It is an effective quality improvement and risk assessment tool (Tay and Lim 2008) widely used in practice (Islam and Tedford 2012). FMEA and ISO 14971 risk analysis receive most attention from manufacturing companies (Chan et al. 2012); therefore, FMEA is used as a prevention and improvement tool to analyze the risks in MPD process. The risk during each stage and the associated consequences related to its occurrence were discussed with the development team. Calculation of RPNs for identified risks as prescribed by ISO 14971 (2012) guidelines for risk analysis is one noticeable step in FMEA to prioritize the failure modes (Li and Zeng 2014). RPNs are determined by evaluation of three factors: occurrence (O), severity (S) and detection (D) (Zhang and Chu 2011) as discussed here:

  • Occurrence (O)

The number of times the risk occurs is called as probability of occurrence.

  • Severity (S)

The effect of each risk on the process is expressed in terms of severity or the level of risk.

  • Detection (D)

This ranks the ability of planned tests and inspections to remove defects or detect failure modes in time. The assigned detection number measures the risk that the failure will escape detection. A high detection number indicates that the chances are high that the failure will escape detection or, in other words, that the chances of detection are low.

The three risk factors are evaluated using 10-point scale as described in Table 6. Risks with higher RPN values are assumed to be more important and are given higher priorities over others (Mariajayaprakash et al. 2013). Each potential risk associated with the MPD process is scored in relation to O, S and D (refer Table 7).

Table 6 Criteria for the probability of occurrence, severity and detection
Table 7 O, S, D and RPNs for the risks identified by traditional FMEA

The methodology of FMEA is shown in Fig. 2.

Then, RPN is calculated by multiplying O, S and D. The higher the RPN for a particular factor, the greater is the risk of failure of the process due to that factor.

Based on RPNs, the risks are ranked as shown in Table 7. In spite of extensive use of FMEA for risk analysis, it has been criticized for number of reasons as discussed here:

  1. 1.

    RPN is calculated by multiplication of O, S and D. Different combinations of O, S and D have different risk impacts but may produce same value of RPN. This may lead to wastage on the part of resources or time.

  2. 2.

    O, S and D have different relative importance which is not considered in FMEA. The three factors are assumed to be equally important (Vencheh et al. 2013). This may not be always the case in practical situation.

  3. 3.

    Precise evaluation of O, S and D is difficult (Liu et al. 2013).

  4. 4.

    The occurrence (O) score is required to be rated and updated manually from time to time by users based on their knowledge, experience and with reference to the latest data. It makes FMEA tedious and time consuming (Tay and Lim 2008).

  5. 5.

    RPNs are not continuous with many holes (Liu et al.2013).

  6. 6.

    Effectiveness of risk mitigation measures taken cannot be evaluated using RPN.

In addition to these, authors experienced few other issues with traditional FMEA. The experience of experts is not considered while calculating RPNs, which is very important in MPD process where the data regarding O, S and D are based on the FMEA team members’ experience. Also asking the experts to assign scores ranging from 1 to 10 for different risks considered may produce false and unrealistic impression (Kumru and Kumru 2013). To overcome the drawbacks associated with traditional RPNs, this paper uses fuzzy approach discussed in the next subsection.

Fuzzy FMEA

Fuzzy linguistic theory has been widely used to solve fuzzy phenomenon problems existing in the real world, such as uncertain, imprecise, unspecific and fuzzy situations. It is a powerful tool for incorporating imprecise data and fuzzy expressions into decision framework (Liu et al. 2014).

In FMEA, O, S and D are three major risk factors considered. Under many practical situations, it is difficult to obtain exact assessment values of the risk factors due to inherent vagueness and uncertainty in human judgments (Liu et al. 2014). Hence, fuzzy approach for FMEA has wide applicability (Liu et al. 2013).

The majority of the fuzzy FMEA approaches use fuzzy if–then rules to prioritize failure modes, which demand a rule base of a very large size based on experts’ judgments. Asking an expert to make so many judgments is practically unrealistic. The case considered here is subjective and undefined; the use of fuzzy linguistic is more appropriate. As such, in this research, the linguistic scale with triangular fuzzy numbers (TFNs) is used for the evaluation of O, S and D (Fig. 4). The description of linguistic and corresponding fuzzy numbers is shown in Table 8.

Fig. 4
figure 4

Fuzzy linguistic scale for O, S and D for MPD process risks (Lin et al. 2013)

Table 8 Fuzzy linguistics for O, S, D and corresponding fuzzy numbers

The fuzzy O, S and D are based on experience and expertise of team members. The weights of experts are calculated using Eq. (1) as different experts have different influence on the results (Lin et al. 2014).

$$ w_{{{\text{tm}}k}} = \frac{{E_{{{\text{tm}}k}} }}{{\mathop \sum \nolimits_{k = 1}^{n} E_{{{\text{tm}}k}} }} , \quad k = 1,2,3 \ldots ,n $$
(1)

where tmk and E are kth team member and its expertise, respectively. The weights of five expert team members are shown in Table 9.

Table 9 Weights of experts

The result of the evaluation of O, S and D of the 20 risks identified during MPD process using fuzzy linguistic terms by five FMEA team members (TM) is shown in Table 10.

Table 10 Evaluation of O, S and D by expert team members using fuzzy linguistic terms

Weight of the importance of each risk has been assigned by experts using fuzzy linguistic terms: unimportant (U), less important (L), medium important (M), important (I) and very important (VI) with corresponding fuzzy numbers (0, 0, 0.15), (0.1, 0.25, 0.4), (0.35, 0.5, 0.65), (0.6, 0.75, 0.9), (0.85, 1, 1), respectively (Fig. 5) (Lin et al. 2013).

Fig. 5
figure 5

Fuzzy linguistic scale for weight of importance of each risk (Lin et al. 2013)

Based on experts’ opinions, weight of importance of each risk is shown in Table 11.

Table 11 Weight of importance of each risk assigned by team members

Let \( {\text{O}}_{ij}^{n} \), \( {\text{S}}_{ij}^{n} \) and \( {\text{D}}_{ij}^{n} \) be the occurrence, severity and detection, respectively, which are evaluated by n experts for interface i and risk j, \( {\text{O}}_{ij}^{n} \), \( {\text{S}}_{ij}^{n} \) and \( {\text{D}}_{ij}^{n} \in T \) be the membership function for triangular fuzzy number, \( {\text{W}}_{ij}^{n} \) be the importance weight evaluated by n respondents for interface i and risk j, \( {\text{W}}_{ij}^{n} \in {\text{S}} \) be the membership function for it

$$ {\text{O}}_{ij}^{n} = \left( {{\text{OL}}_{ij}^{n} ,{\text{OM}}_{ij}^{n} , {\text{OU}}_{ij}^{n} } \right),\quad {\text{O}}_{ij}^{n} \in T,\quad {\text{where}}\quad 0 \le {\text{OL}}_{ij}^{n} \le {\text{OM}}_{ij}^{n} \le {\text{OU}}_{ij}^{n} \le 10 $$
(2)
$$ {\text{S}}_{ij}^{n} = \left( {{\text{SL}}_{ij}^{n} ,{\text{SM}}_{ij}^{n} , {\text{SU}}_{ij}^{n} } \right),\quad {\text{S}}_{ij}^{n} \in T,\quad {\text{where}}\quad 0 \le {\text{SL}}_{ij}^{n} \le {\text{SM}}_{ij}^{n} \le {\text{SU}}_{ij}^{n} \le 10 $$
(3)
$$ {\text{D}}_{ij}^{n} = \left( {{\text{DL}}_{ij}^{n} ,{\text{DM}}_{ij}^{n} ,{\text{DU}}_{ij}^{n} } \right),\quad {\text{D}}_{ij}^{n} \in T,\quad {\text{where}}\quad 0 \le {\text{DL}}_{ij}^{n} \le {\text{DM}}_{ij}^{n} \le {\text{DU}}_{ij}^{n} \le 10 $$
(4)
$$ {\text{W}}_{ij}^{n} = \left( {{\text{WL}}_{ij}^{n} ,{\text{WM}}_{ij}^{n} ,{\text{WU}}_{ij}^{n} } \right),\quad {\text{W}}_{ij}^{n} \in {\text{S}},\quad {\text{where}}\quad 0 \le {\text{WL}}_{ij}^{n} \le {\text{WM}}_{ij}^{n} \le {\text{WU}}_{ij }^{n} \le 1 $$
(5)
$$ {\text{O}}_{ij} = {\text{O}}_{ij}^{1} \times W_{{{\text{tm}}1}} + {\text{O}}_{ij}^{2} \times {\text{W}}_{{{\text{tm}}2}} + \cdots + {\text{O}}_{ij}^{n} \times {\text{W}}_{{{\text{tm}}n}} $$
(6)
$$ {\text{S}}_{ij} = {\text{S}}_{ij}^{1} \times {\text{W}}_{{{\text{tm}}1}} + {\text{S}}_{ij}^{2} \times {\text{W}}_{{{\text{tm}}2}} + \cdots + {\text{S}}_{ij}^{n} \times {\text{W}}_{{{\text{tm}}n}} $$
(7)
$$ {\text{D}}_{ij} = {\text{D}}_{ij}^{1} \times {\text{W}}_{{{\text{tm}}1}} + {\text{D}}_{ij}^{2} \times {\text{W}}_{{{\text{tm}}2}} + \cdots + {\text{D}}_{ij}^{n} \times {\text{W}}_{{{\text{tm}}n}} $$
(8)
$$ {\text{W}}_{ij} = {\text{W}}_{ij}^{1} \times {\text{W}}_{{{\text{tm}}1}} + {\text{W}}_{ij}^{2} \times {\text{W}}_{{{\text{tm}}2}} + \cdots + {\text{W}}_{ij}^{n} \times {\text{W}}_{{{\text{tm}}n}} $$
(9)

where \( {\text{O}}_{ij} ,\;{\text{S}}_{ij} ,\; {\text{D}}_{ij} \) are occurrence, severity and detection values of experts’ team members opinion for interface i and risk j, \( {\text{W}}_{ij} \) is importance for each risk evaluated by experts’ team members for interface j and risk ji, \( {\text{W}}_{{{\text{tm}}k}} \) is the weight of kth team member and n is the number of experts’ team members, respectively.

The fuzzy numbers for probability of occurrence (O), severity (S), detection (D) and fuzzy weights for each risk by each team member (W) are aggregated based on expert team members’ subjective opinion using Eqs. (6)–(9) (Lin et al. 2013). The aggregated fuzzy information for twenty risks is shown in Table 12.

Table 12 Aggregated fuzzy information for twenty risks

The values shown in Table 12 for twenty risks in MPD process are fuzzy sets. Defuzzification of the fuzzy sets is necessary to convert the fuzzy sets into numerical values. There are different algorithms for defuzzification, such as centre of gravity, centre of gravity for singletons, centre of area, left most maximum, right most maximum (Kumru and Kumru 2013) and mean of maximum. As compared to Mean of maximum (MoM), Centre of Area (CoA) yields better results (Lin et al. 2014). Fuzzy occurrence, severity, detection and fuzzy weight of importance of each risk in MPD process have been calculated using Eqs. (10)–(13) (Lin et al. 2013), respectively.

$$ {\text{DO}}_{k} = \frac{{[\left( {{\text{OU}}_{k} - {\text{OL}}_{k} } \right) + \left( {{\text{OM}}_{k} - {\text{OL}}_{k} } \right)]}}{3} + {\text{OL}}_{k} \quad \forall k $$
(10)
$$ {\text{DS}}_{k} = \frac{{[\left( {{\text{SU}}_{k} - {\text{SL}}_{k} } \right) + \left( {{\text{SM}}_{k} - {\text{SL}}_{k} } \right)]}}{3} + {\text{SL}}_{k} \quad \forall k $$
(11)
$$ {\text{DD}}_{k} = \frac{{[\left( {{\text{DU}}_{k} - {\text{DL}}_{k} } \right) + \left( {{\text{DM}}_{k} - {\text{DL}}_{k} } \right)]}}{3} + {\text{DL}}_{k} \quad \forall k $$
(12)
$$ {\text{DW}}_{k} = \frac{{[\left( {{\text{WU}}_{k} - {\text{WL}}_{k} } \right) + \left( {{\text{WM}}_{k} - {\text{WL}}_{k} } \right)]}}{3} + {\text{WL}}_{k} \quad \forall k $$
(13)

RPND is calculated using \( {\text{DO}}_{k} \), \( {\text{DS}}_{k} \), \( {\text{DD}}_{k} \) and \( {\text{DW}}_{k} \).

$$ {\text{RPN}}_{\text{D}} = {\text{DO}}_{k} \times {\text{DS}}_{k} \times {\text{DD}}_{k} \times {\text{DW}}_{k} $$
(14)

Table 13 shows the RPND values for all twenty risks identified during MPD process using Eq. (14) (Lin et al. 2013).

Table 13 RPND values for all risks

A comparison of RPN by traditional FMEA and RPND obtained by fuzzy FMEA is shown in Table 13. After doing the comparative analysis of the risks identified during MPD process using Traditional FMEA and Fuzzy FMEA, it is found that later has some advantages as compared to traditional FMEA (Liu et al. 2013):

  • Complex and ambiguous data can be handled in a consistent manner for risk assessment.

  • Risk evaluation function can be customized based on the nature of process.

  • Combination of three factors, O, S and D, of risks in more flexible and realistic way is possible.

At the same time, it has some drawbacks as discussed here (Liu et al. 2013):

  • To define appropriate membership function, risk factor is a crucial task.

  • Any modification in the number of linguistic scale and terms requires redefinition of membership functions.

  • User has to deal with complex calculations to draw the inferences.

  • Even when their membership functions overlap, they provide arbitrary priority ranks of failure modes (Mandal and Maiti 2014).

After calculating RPNs using traditional FMEA and fuzzy FMEA, the risks during MPD process are categorized as: critical risks (CR), moderate risks (MR), low level risks (LR) and negligible risks (NR) based on the RPNs calculated and their criticality.

The detailed categorization and comparison of risks are shown in Fig. 6. The limits of RPNs for categorization are set based on experts’ opinions.

Fig. 6
figure 6

Risks categorization and comparison based on RPNs using traditional FMEA and fuzzy FMEA

Mapping risks to the MPD phases

After carrying the detailed analysis of the risks identified, the risks are mapped back to the five phases of MPD process. A phase-wise comparison between the results of traditional FMEA and fuzzy FMEA based on their category and severity is shown in Fig. 7.

Fig. 7
figure 7

Phase-wise scatter of risks based on category and severity

Risk mitigation

The next step in the risk management is to suggest risk mitigation strategy for the identified risks. As a result of brainstorming and discussion with the MPD experts, the risk treatment for each risk and the mitigation strategy for each category of criticality are recommended as shown in Table 14.

Table 14 Risk treatments and mitigation strategies recommended

Risk mitigation model

A risk mitigation model is developed (Fig. 8) based on the risks identified and the mitigation strategy suggested. The model has a logical flow. MPD process risks are shown on right-hand side of the model. Critical, moderate, low level and negligible risks are represented in convergent manner as per the severity of occurrence. The area covered by each risk is proportional to the severity. Common risk mitigation strategies for risks of different category based on criticality are shown on left-hand side of the model. Residual risks are shown in the model, which still remain after applying the mitigation strategy. The acceptable level of each residual risk should be calculated and decision may be taken based on the severity of the residual risk.

Fig. 8
figure 8

MPD process risks mitigation model

Though the model discussed here is specific for the case considered, it will be useful for any other industry for the purpose of risk mitigation.

Results and discussion

The risk management methodologies refer to a standard process presenting the well-known steps: risk identification, risk evaluation and quantification, risk mitigation for treatment and/or impact minimization and risk monitoring (Marmier et al. 2013). Most of the research on RM has focused on risk identification and analysis.

A case study of undefined and subjective MPD, i.e., dental cement, is presented here. The existing MPD process is mapped with the standard phase gate process with necessary customization. A total of twenty risks are explored during five phases of the MPD. These risks are categorized as: technical, strategy and market risks based on the source of occurrence. RPN for each risk is calculated using traditional FMEA and fuzzy FMEA; their results are compared. The risks are further categorized as critical, moderate, low level and negligible risks based on their RPN and the criticality. The risks are mapped back to the five phases of development process to know the sources and criticality of different risks along each phase.

Traditional FMEA gives 40 % CRs, 20 %MRs, 10 %LRs and 25 %NRs out of total risks (Fig. 9). During concept phase, 10 % of risks are MRs and 15 % are NRs. Architecture Phase has 5 % of MR, LR each and 10 % NRs. Development phase has 10 % CRs, 5 % MR and LR each. During testing, 15 % are CRs and 5 % MR. Last phase has 15 % CRs and 5 % MR (Fig. 10).

Fig. 9
figure 9

Comparison between results of traditional FMEA and fuzzy FMEA based on criticality of risks

Fig. 10
figure 10

Distribution of CRs, MRs, LRs and NRs along phases

Fuzzy FMEA resulted in 25 % CRs, 20 % MRs, 10 % LRs and 45 % NRs out of total risks. Concept phase has 5 % MR and 15 % NRs. Architecture Phase has 20 % NRs; development phase has 5 % CR, MR and NR each. Testing has 10 % CRs, 5 % MR and LR each. Validation and launch have 10 % CRs, 5 % MR, LR and NR each (Fig. 10). The concept and development phases have more MRs and NRs as compared to other phases. Results of prioritizing MPD process risks using fuzzy FMEA are found to be more logical as compared to traditional FMEA. It filtered the critical risks from 40 to 25 %, which helps to deal with CRs, efficiently and effectively.

The study provides a detailed methodology for the developers, managers and researchers to explore MPD process risks and perform risk management using traditional FMEA and fuzzy FMEA approach. The risks identified though specific in nature provide a guideline for development processes of other medical products and devices. Also the use of FMEA is discussed in detail. The mitigation model will serve as a generic model for risk mitigation.

Conclusion and future scope

This paper presented a case of managing risks during MPD process. It can be concluded from this case study that MPD process has number of risks, whose management and mitigation are extremely necessary to reduce failure events due to process. During initial phases of MPD, the risks are less severe; but as the process progresses the severity of risks goes on increasing. The MPD process should be critically designed and simulated to minimize the number of risk events and their severity. Considering opinions of the experts on results, fuzzy FMEA approach gives more precise, appropriate and logical results as compared to the traditional FMEA.

The case study research has many advantages and limitations as well. The risks identified are specific for the case under consideration. The RPNs calculated, risk prioritization and categorization are also specific, but can be customized and effectively applied for other cases. The conclusions drawn are limited for the particular case; hence more number of such studies needs to be carried in future. Other techniques for risk analysis should be used and compared with the results reported here. A detailed survey of the medical product development companies will be useful in drawing statistics-based conclusions.