Ground subsidence characteristics caused by construction of shallow-buried tunnel in a sandy soil composite formation

  • Original Paper
  • Published:
Arabian Journal of Geosciences Aims and scope Submit manuscript

Abstract

In dry fine sand and medium-coarse sand strata, large surface subsidence and even collapse are common issues related to tunnel excavation. In the Liu-Huo Section of Line 1 of Shijiazhuang Subway, transverse and vertical surface subsidence were examined by analyzing the measured subsidence data. The width coefficient of the settling tank and the loss rate of the sand mixed stratum were determined using the Peck formula. The settlement of the vertical and transverse surface and vault was further analyzed by establishing a three-dimensional numerical model of the tunnel. Results show that the deformation and surface subsidence vary rapidly for the dry sand mixed stratum, and the subsidence trough is “narrow and steep,” which is different from the general clay stratum. In the Peck formula, the ground settlement tank width coefficient is i = 6.55, and the formation loss rate is Vi = 4.81%. Ground settlement increased nonlinearly with the excavation of the pilot tunnels using the double-sided drift method. The settlement caused by the left No. 1 pilot tunnel was the largest, next was the right No. 3 pilot tunnel, the left No. 2 pilot tunnel, and the right No. 4 pilot tunnel. The settlement caused by the middle No. 5 and No. 6 pilot tunnels was smaller. The vertical settlement is divided into three stages: the small settlement stage, rapid stage, and stable stage. The settlement caused by the excavation of the No. 1, No. 2, and No. 3 pilot tunnels was the largest. After excavation of the No. 3 pilot tunnel, the settlement occupied about 78.3% of the final settlement. Monitoring of the No. 1, No. 2, and No. 3 pilot tunnels should be strengthened during the excavation, and the settlement should be strictly controlled.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 5
Fig. 6
Fig. 7
Fig. 8
Fig. 9
Fig. 10

Similar content being viewed by others

References

Download references

Acknowledgments

A special thanks to our colleagues at Qingdao Metro Group Co., LTD and China Construction Second Engineering Bureau LTD for providing surveying data and field monitoring assistance. We would like to thank our friends and colleagues for their invaluable advice, assistance, and supports during field monitoring and data acquisition.

Funding

This study was financially supported by the National Natural Science Foundation of China (Grant No. 41402275), Natural Science Foundation of Shandong province (Grant No. ZR2019QEE008), Special Funding for Science and Technology Development of Qingdao (Grant No. JK2014-14), Academic project of China Construction Second Engineering Bureau LTD (91110000100024296D170006), and the University Funding of the Qingdao University of Technology (Grant No. C2-2013-006).

Author information

Authors and Affiliations

Authors

Corresponding authors

Correspondence to Peng Zhang or Xiaoming Guan.

Additional information

Responsible Editor: Zeynal Abiddin Erguler

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Zhang, P., Pan, Y., Yu, Z. et al. Ground subsidence characteristics caused by construction of shallow-buried tunnel in a sandy soil composite formation. Arab J Geosci 13, 901 (2020). https://doi.org/10.1007/s12517-020-05880-z

Download citation

  • Received:

  • Accepted:

  • Published:

  • DOI: https://doi.org/10.1007/s12517-020-05880-z

Keywords

Navigation