A new interval type-2 fuzzy approach for analyzing and monitoring the performance of megaprojects based on earned value analysis (with a case study)

  • Original Article
  • Published:
Neural Computing and Applications Aims and scope Submit manuscript

Abstract

Major factors of project success include using tools of performance measurements and feedbacks. Earned value management (EVM) is a unique issue within megaprojects due to their inevitable external risks and variations. In order to improve the effectiveness and accuracy of future status estimation of megaprojects, in this paper a novel evaluation model is proposed which takes account of interval type-2 fuzzy sets (IT2FSs) to cope with uncertainty. In the proposed approach, in addition to cost and time criteria, a great deal of attention is paid for other important factors affecting project success, including quality, stakeholder satisfaction, safety and risk, which is computed from different perspectives. Moreover, to make informed decisions and to reduce uncertainty in assessment of megaprojects, key performance indicators (KPIs) are provided. Also, a new extension of multi-criteria decision-making method is introduced to weigh KPIs in future performance equations. Finally, the proposed IT2F-EVM approach is applied to control and estimate the future status of a real case study in a petro-refinery company. The results show that the approach can successfully address highly uncertain environments.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 5
Fig. 6
Fig. 7

Similar content being viewed by others

References

  1. Abdi A, Taghipour S, Khamooshi H (2018) A model to control environmental performance of project execution process based on greenhouse gas emissions using earned value management. Int J Proj Manag 36(3):397–413

    Article  Google Scholar 

  2. Acebes F, Pajares J, Galán JM, López-Paredes A (2014) A new approach for project control under uncertainty. Going back to the basics. Int J Proj Manag 32(3):423–434

    Article  Google Scholar 

  3. Anbari FT (2003) Earned value project management method and extensions. Proj Manag J 34(4):12–23

    Article  Google Scholar 

  4. Babar S, Thaheem MJ, Ayub B (2016) Estimated cost at completion: integrating risk into earned value management. J Constr Eng Manag 143(3):04016104

    Article  Google Scholar 

  5. Bagherpour M, Zareei A, Noori S, Heydari M (2010) Designing a control mechanism using earned value analysis: an application to production environment. Int J Adv Manuf Technol 49(5–8):419–429

    Article  Google Scholar 

  6. Batselier J, Vanhoucke M (2017) Improving project forecast accuracy by integrating earned value management with exponential smoothing and reference class forecasting. Int J Proj Manag 35(1):28–43

    Article  Google Scholar 

  7. Bryde D, Unterhitzenberger C, Joby R (2018) Conditions of success for earned value analysis in projects. Int J Proj Manag 36(3):474–484

    Article  Google Scholar 

  8. Castillo O, Amador-Angulo L, Castro JR, Garcia-Valdez M (2016) A comparative study of type-1 fuzzy logic systems, interval type-2 fuzzy logic systems and generalized type-2 fuzzy logic systems in control problems. Inf Sci 354:257–274

    Article  Google Scholar 

  9. Castillo O, Cervantes L, Soria J, Sanchez M, Castro JR (2016) A generalized type-2 fuzzy granular approach with applications to aerospace. Inf Sci 354:165–177

    Article  Google Scholar 

  10. Celik E, Gumus AT (2015) An assessment approach for non-governmental organizations in humanitarian relief logistics and an application in Turkey. Technol Econ Dev Econ. https://doi.org/10.3846/20294913.2015.1056277

    Article  Google Scholar 

  11. Chang CJ, Yu SW (2018) Three-variance approach for updating earned value management. J Constr Eng Manag 144(6):04018045

    Article  Google Scholar 

  12. Chen SM, Lee LW (2010) Fuzzy multiple attributes group decision-making based on the ranking values and the arithmetic operations of interval type-2 fuzzy sets. Expert Syst Appl 37(1):824–833

    Article  Google Scholar 

  13. Chen SM, Lee LW (2010) Fuzzy multiple attributes group decision-making based on the ranking values and the arithmetic operations of interval type-2 fuzzy sets. Expert Syst Appl 37(1):824–833

    Article  Google Scholar 

  14. Choi YI, Ahn J (2018) Earned value management considering technical readiness level and its application to new space launcher program. Int J Aeronaut Space Sci 19(1):227–237

    Article  Google Scholar 

  15. Coban R (2010) Computational intelligence-based trajectory scheduling for control of nuclear research reactors. Prog Nucl Energy 52(4):415–424

    Article  Google Scholar 

  16. Coban R (2011) A fuzzy controller design for nuclear research reactors using the particle swarm optimization algorithm. Nucl Eng Des 241(5):1899–1908

    Article  Google Scholar 

  17. Coban R, Aksu IO (2018) Neuro-controller design by using the multifeedback layer neural network and the particle swarm optimization. Tehnički vjesnik 25(2):437–444

    Google Scholar 

  18. Coban R, Can B (2009) An expert trajectory design for control of nuclear research reactors. Expert Syst Appl 36(9):11502–11508

    Article  Google Scholar 

  19. Collin J (2002) Measuring the success of building projects–improved project delivery initiatives. Int J 11(2):203–221

    Google Scholar 

  20. Dorfeshan Y, Mousavi SM (2019) A new interval type-2 fuzzy decision method with an extended relative preference relation and entropy to project critical path selection. Int J Fuzzy Syst Appl 8(1):19–47

    Article  Google Scholar 

  21. Dorfeshan Y, Mousavi SM, Vahdani B (2018) A multi-criteria analysis model under an interval type-2 fuzzy environment with an application to production project decision problems. J Qual Eng Prod Optim 3(1):43–66

    Google Scholar 

  22. Dorfeshan Y, Mousavi SM, Mohagheghi V, Vahdani B (2018) Selecting project-critical path by a new interval type-2 fuzzy decision methodology based on MULTIMOORA, MOOSRA and TPOP methods. Comput Ind Eng 120:160–178

    Article  Google Scholar 

  23. Ghorabaee MK, Amiri M, Sadaghiani JS, Zavadskas EK (2015) Multi-criteria project selection using an extended VIKOR method with interval type-2 fuzzy sets. Int J Inf Technol Decis Mak 14(5):993–1016

    Article  Google Scholar 

  24. Gomes LFAM, Lima MMPP (1992) From modeling individual preferences to multicriteria ranking of discrete alternatives: a look at prospect theory and the additive difference model. Found Comput Decis Sci 17(3):171–184

    MATH  Google Scholar 

  25. Hashemi ST, Kaur H (2017) A hybrid conceptual cost estimating model using ANN and GA for power plant projects. Neural Comput Appl 28(11):1–12

    Google Scholar 

  26. Henderson K (2004) Further developments in earned schedule. Meas News 1(1):15–22

    Google Scholar 

  27. Hu J, Zhang Y, Chen X, Liu Y (2013) Multi-criteria decision making method based on possibility degree of interval type-2 fuzzy number. Knowl Based Syst 43:21–29

    Article  Google Scholar 

  28. Jacob DS, Kane M (2004) Forecasting schedule completion using earned value metrics revisited. Meas News 1(11):7

    Google Scholar 

  29. Kerzner H (2011) Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. Wiley, New York

    Book  Google Scholar 

  30. Kerzner H (2017) Project management: a systems approach to planning, scheduling, and controlling. Wiley, New York

    Google Scholar 

  31. Kim E, Wells WG Jr, Duffey MR (2003) A model for effective implementation of earned value management methodology. Int J Proj Manag 21(5):375–382

    Article  Google Scholar 

  32. Lester A (2017) Project management, planning and control: managing engineering, construction and manufacturing projects to PMI, APM and BSI standards. Elsevier, Amsterdam

    Google Scholar 

  33. Lipke W (2003) Schedule is different. Meas News 31(4):31–34

    Google Scholar 

  34. Liu HT, Cheng HS (2016) An improved grey quality function deployment approach using the grey TRIZ technique. Comput Ind Eng 92:57–71

    Article  Google Scholar 

  35. Liu S, Lin Y (2006) Grey information: theory and practical applications. Springer, Berlin

    Google Scholar 

  36. Mavrotas G, Caloghirou Y, Koune J (2005) A model on cash flow forecasting and early warning for multi-project programmes: application to the Operational Programme for the Information Society in Greece. Int J Proj Manag 23(2):121–133

    Article  Google Scholar 

  37. Mendel JM (2003) “Type-2 fuzzy sets: some questions and answers”, IEEE connections, newsletter of the IEEE. Neural Netw Soc 1:10–13

    Google Scholar 

  38. Mendel JM, John RI, Liu F (2006) Interval type-2 fuzzy logic systems made simple. IEEE Trans Fuzzy Syst 14(6):808–821

    Article  Google Scholar 

  39. Mohagheghi V, Mousavi SM, Vahdani B (2017) Analyzing project cash flow by a new interval type-2 fuzzy model with an application to construction industry. Neural Comput Appl 28(11):3393–3411

    Article  Google Scholar 

  40. Mohagheghi V, Mousavi SM, Vahdani B, Shahriari MR (2017) R&D project evaluation and project portfolio selection by a new interval type-2 fuzzy optimization approach. Neural Comput Appl 28(12):3869–3888

    Article  Google Scholar 

  41. Mohagheghi V, Mousavi SM, Vahdani B, Siadat A (2017) A mathematical modeling approach for high and new technology-project portfolio selection under uncertain environments. J Intell Fuzzy Syst 32(6):4069–4079

    Article  MATH  Google Scholar 

  42. Moradi N, Mousavi SM, Vahdani B (2017) An earned value model with risk analysis for project management under uncertain conditions. J Intell Fuzzy Syst 32(1):97–113

    Article  MATH  Google Scholar 

  43. Mortaji STH, Bagherpour M, Noori S (2013) Fuzzy earned value management using LR fuzzy numbers. J Intell Fuzzy Syst 24(2):323–332

    Google Scholar 

  44. Muhwezi L, Acai J, Otim G (2014) An assessment of the factors causing delays on building construction projects in Uganda. Int J Constr Eng Manag 3(1):13–23

    Google Scholar 

  45. Naeni LM, Salehipour A (2011) Evaluating fuzzy earned value indices and estimates by applying alpha cuts. Expert Syst Appl 38(7):8193–8198

    Article  Google Scholar 

  46. Naeni LM, Shadrokh S, Salehipour A (2014) A fuzzy approach for the earned value management. Int J Proj Manag 32(4):709–716

    Article  Google Scholar 

  47. Najafi A, Azimi F (2016) An extension of the earned value management to improve the accuracy of schedule analysis results. Iran J Manag Stud 9(1):63–85

    Google Scholar 

  48. Ong HY, Wang C, Zainon N (2016) Integrated earned value Gantt chart (EV-Gantt) tool for project portfolio planning and monitoring optimization. Eng Manag J 28(1):39–53

    Article  Google Scholar 

  49. Ontiveros-Robles E, Melin P, Castillo O (2018) Comparative analysis of noise robustness of type 2 fuzzy logic controllers. Kybernetika 54(1):175–201

    MathSciNet  MATH  Google Scholar 

  50. Oztaysi B (2015) A group decision making approach using interval type-2 fuzzy AHP for enterprise information systems project selection. J Mult Valued Logic Soft Comput 24(5):1–15

    MathSciNet  Google Scholar 

  51. Picornell M, Pellicer E, Torres-Machí C, Sutrisna M (2016) Implementation of earned value management in unit-price payment contracts. J Manag Eng 33(3):06016001

    Article  Google Scholar 

  52. Ponz-Tienda JL, Pellicer E, Yepes V (2012) Complete fuzzy scheduling and fuzzy earned value management in construction projects. J Zhejiang Univ Sci A 13(1):56–68

    Article  Google Scholar 

  53. Project Management Institute (2013) A guide to the project management body of knowledge (PMBOK Guide), 5h edn. Project Management Institute, Newtown Square

    Google Scholar 

  54. Project Management Institute (2011) Practice standard for earned value management. Project Management Institute, Incorporated

  55. Qin J, Liu X, Pedrycz W (2015) An extended VIKOR method based on prospect theory for multiple attribute decision making under interval type-2 fuzzy environment. Knowl Based Syst 86:116–130

    Article  Google Scholar 

  56. Qin J, Liu X, Pedrycz W (2017) An extended TODIM multi-criteria group decision making method for green supplier selection in interval type-2 fuzzy environment. Eur J Oper Res 258(2):626–638

    Article  MathSciNet  MATH  Google Scholar 

  57. Radujković M, Sjekavica M (2017) Project management success factors. Proc Eng 196:607–615

    Article  Google Scholar 

  58. Sari IU, Kahraman C (2015) Interval type-2 fuzzy capital budgeting. Int J Fuzzy Syst 17(4):635–646

    Article  MathSciNet  Google Scholar 

  59. Sogandi F, Mousavi SM, Amiri A (2018) Self-starting control chart and post signal diagnostics for monitoring project earned value management indices. J Ind Syst Eng 11(2):85–100

    Google Scholar 

  60. Sutrisna M, Pellicer E, Torres-Machi C, Picornell M (2018) Exploring earned value management in the Spanish construction industry as a pathway to competitive advantage. Int J Constr Manag 18(6):1–12

    Google Scholar 

  61. Turner R (2016) Gower handbook of project management. Routledge, New York

    Book  Google Scholar 

  62. Vandevoorde S, Vanhoucke M (2006) A comparison of different project duration forecasting methods using earned value metrics. Int J Proj Manag 24(4):289–302

    Article  Google Scholar 

  63. Vanhoucke M (2009) Measuring time: improving project performance using earned value management, vol 136. Springer, Berlin

    MATH  Google Scholar 

  64. Vanhoucke M (2010) Using activity sensitivity and network topology information to monitor project time performance. Omega 38(5):359–370

    Article  Google Scholar 

  65. Vanhoucke M (2016) Integrated project management sourcebook. Springer, Berlin

    Book  Google Scholar 

  66. Zadeh LA (1974) Fuzzy logic and its application to approximate reasoning. In IFIP congress, vol 591

  67. Zareei S (2018) Project scheduling for constructing biogas plant using critical path method. Renew Sustain Energy Rev 81(1):756–759

    Article  Google Scholar 

  68. Zolfaghari S, Mousavi SM (2018) Construction-project risk assessment by a new decision model based on De-Novo multi-approaches analysis and hesitant fuzzy sets under uncertainty. J Intell Fuzzy Syst 35:639–649

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Amin Eshghi.

Ethics declarations

Conflict of interest

The authors declare that they have no conflict of interest.

Additional information

Publisher's Note

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Eshghi, A., Mousavi, S.M. & Mohagheghi, V. A new interval type-2 fuzzy approach for analyzing and monitoring the performance of megaprojects based on earned value analysis (with a case study). Neural Comput & Applic 31, 5109–5133 (2019). https://doi.org/10.1007/s00521-018-04002-x

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s00521-018-04002-x

Keywords

Navigation