Abstract
The study aims to gather information and assess the extent of delays and their impact on road and highway projects in India. The objective is to develop a delay assessment matrix for easy quantification of delay-causing factors on project duration. A mixed-method approach was used for data collection wherein information was gathered through literature review, questionnaire survey, interviews, and responses under the RTI act. The collected information was screened, verified, and analyzed using statistical tools. Factor analysis was employed to arrive at a final list of 20 factors grouped in a 3 × 3 matrix, having the probability of occurrence vs. impact on project duration as the axes. The model was tested on a recently completed highway project using the Monte Carlo simulation technique. The case simulation revealed the project duration to be 1237 days (50% probability) which was found to be in agreement with the actual project duration of 1236 days. The analytical contribution of the study is the development of the matrix by fixing up the range of probability of occurrence and the impact that these factors would have on project duration. The delay assessment matrix along with the methodology can be used as a practical tool by practitioners in their projects during the planning stages. The methodology can be adopted for ongoing and upcoming projects for successful delay prediction and quantification of delay impacts in the projects.
Similar content being viewed by others
References
IBEF Indian road industry report (2021), https://www.ibef.org/industry/roads-presentation
Department of economic affairs, economic survey 2020–21: Volume I. Ministry of finance, government of India (2021), https://www.indiabudget.gov.in/economicsurvey/
Infrastructure and project monitoring division, 425th flash report on central sector projects. Ministry of statistics and programme implementation, government of India (2021), http://www.cspm.gov.in/english/flr/FR_Apr_2021.pdf
G. Elawi, M. Algahtany, D. Kashiwagi, Owners’ perspective of factors contributing to project delay: Case studies of road and bridge projects in Saudi Arabia. Proced. Eng. 145, 1402–1409 (2016). https://doi.org/10.1016/j.proeng.2016.04.176
Y.C. Kog, Major construction delay factors in Portugal, the UK, and the US. Pract. Period. Struct. Des. Constr. 23(4), 04018024 (2018). https://doi.org/10.1061/(ASCE)SC.1943-5576.0000389
R. Asiedu, H. Alfen, Understanding the underlying reasons behind time overruns of government building projects in Ghana. KSCE J. Civ. Eng. 20(6), 2103–2111 (2015). https://doi.org/10.1007/s12205-015-0544-4
A. Kavuma, J. Ock, H. Jang, Factors influencing time and cost overruns on freeform construction projects. KSCE J. Civ. Eng. 23(4), 1442–1450 (2019). https://doi.org/10.1007/s12205-019-0447-x
J. Larsen, G. Shen, S. Lindhard, T. Brunoe, Factors affecting schedule delay, cost overrun, and quality level in public construction projects. J. Manag. Eng. 32(1), 04015032 (2016). https://doi.org/10.1061/(ASCE)me.1943-5479.0000391
Y.C. Kog, Project management and delay factors of public housing construction. Pract. Period. Struct. Des. Constr. 23(1), 04017028 (2018). https://doi.org/10.1061/(ASCE)sc.1943-5576.0000350
C. Tengan, C. Aigbavboa, Level of stakeholder engagement and in monitoring and evaluation of construction projects in Ghana. Proced. Eng. 196, 630–637 (2017). https://doi.org/10.1016/j.proeng.2017.08.051
S. Kim, K. Tuan, V. Luu, Delay factor analysis for hospital projects in Vietnam. KSCE J. Civ. Eng. 20(2), 519–529 (2015). https://doi.org/10.1007/s12205-015-0316-1
Ö. Ökmen, Risk assessment for determining best design alternative in a state-owned irrigation project in Turkey. KSCE J. Civ. Eng. 20, 109–120 (2016). https://doi.org/10.1007/s12205-015-0397-x
Y. Mittal, V. Paul, A. Rostami, M. Riley, A. Sawhney, Delay factors in construction of healthcare infrastructure projects: A comparison amongst developing countries. Asian J. Civ. Eng. 21(4), 649–661 (2020). https://doi.org/10.1007/s42107-020-00227-1
O. Abbasi, E. Noorzai, J.K. Gharouni, M. Golabchi, Exploring the causes of delays in construction industry using a cause-and-effect diagram: Case Study for Iran. J. Archit. Eng. 26(3), 05020008 (2020). https://doi.org/10.1061/(asce)ae.1943-5568.0000431
M. Ruqaishi, H. Bashir, Causes of delay in construction projects in the oil and gas industry in the Gulf cooperation council countries: A case study. J. Manag. Eng. 31(3), 05014017 (2015). https://doi.org/10.1061/(asce)me.1943-5479.0000248
M. Gunduz, Y. Nielsen, M. Ozdemir, Fuzzy assessment model to estimate the probability of delay in Turkish construction projects. J. Manag. Eng. 31(4), 04014055 (2015). https://doi.org/10.1061/(asce)me.1943-5479.0000261
O. Bagaya, J. Song, Empirical study of factors influencing schedule delays of public construction projects in Burkina Faso. J. Manag. Eng. 32(5), 05016014 (2016). https://doi.org/10.1061/(asce)me.1943-5479.0000443
Y.C. Kog, Construction delays in Indonesia, Malaysia, Thailand, and Vietnam. Pract. Period. Struct. Des. Constr. 24(3), 04019013 (2019). https://doi.org/10.1061/(asce)sc.1943-5576.0000434
G. Niazi, N. Painting, Significant factors causing cost overruns in the construction industry in Afghanistan. Proced. Eng. 182, 510–517 (2017). https://doi.org/10.1016/j.proeng.2017.03.145
Z.M. Yaseen, Z.-H. Ali, S.Q. Salih, N. Al-Ansari, Prediction of risk delay in construction projects using a hybrid artificial intelligence model. Sustainability 12(4), 1514 (2020). https://doi.org/10.3390/su12041514
M. Sanni-Anibire, R. Mohamad Zin, S. Olatunji, Causes of delay in the global construction industry: A meta analytical review. Int. J. Constr. Manag. (2020). https://doi.org/10.1080/15623599.2020.1716132
S. Alsharif, A. Karatas, A framework for identifying causal factors of delay in nuclear power plant projects. Proced. Eng. 145, 1486–1492 (2016). https://doi.org/10.1016/j.proeng.2016.04.187
A.A. Alsulaiti, L. Kerbache, Analysis of critical delay factors in construction projects with a focus on Qatar. Int. J. Busin. Econ. Res. 9(3), 130–139 (2020). https://doi.org/10.11648/j.ijber.20200903.16
M. Alzara, J. Kashiwagi, D. Kashiwagi, A. Al-Tassan, Using PIPS to minimize causes of delay in Saudi Arabian construction projects: University case study. Proc. Eng. 145, 932–939 (2016). https://doi.org/10.1016/j.proeng.2016.04.121
Dixit S, Sharma K Factors influencing construction time delay on high rise projects in India, Proceedings of the Creative Construction Conference, Article 047, (2019), https://doi.org/10.3311/CCC2019-047
T. Gebrehiwet, H. Luo, Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study. Proced. Eng. 196, 366–374 (2017). https://doi.org/10.1016/j.proeng.2017.07.212
M. Islam, B. Suhariadi, Construction delays in privately funded large building projects in Bangladesh. Asian J. Civ. Eng. 19(4), 415–429 (2018). https://doi.org/10.1007/s42107-018-0034-3
M. Jahangoshai Rezaee, S. Yousefi, R.K. Chakrabortty, Analyzing causal relationships between delay factors in construction projects: A case study of Iran. Int. J. Manag. Proj. Bus. 14(2), 412–444 (2021). https://doi.org/10.1108/IJMPB-01-2019-0020
M. Kadry, H. Osman, M. Georgy, Causes of construction delays in countries with high geopolitical risks. J. Constr. Eng. Manag. 143(2), 04016095 (2017). https://doi.org/10.1061/(asce)co.1943-7862.0001222
H. Kang, Y. Kim, Analysis of the probabilistic cost variation ranges according to the effect of core quantitative risk factors for an overseas plant project: Focused on a Middle East gas plant project. KSCE J. Civ. Eng. 20(2), 509–518 (2015). https://doi.org/10.1007/s12205-015-0497-7
M. Magdy, M. Georgy, H. Osman, M. Elsaid, Delay analysis methodologies used by engineering and construction firms in Egypt. J. Leg. Aff. Disput. Resolut. Eng. Constr. 11(3), 04519006 (2019). https://doi.org/10.1061/(asce)la.1943-4170.0000293
N. Perera, M. Sutrisna, T. Yiu, Decision-Making model for selecting the optimum method of delay analysis in construction projects. J. Manag. Eng. 32(5), 04016009 (2016). https://doi.org/10.1061/(asce)me.1943-5479.0000441
H. Pham, T. Luu, S. Kim, D. Vien, Assessing the impact of cost overrun causes in transmission lines construction projects. KSCE J. Civ. Eng. 24(4), 1029–1036 (2020). https://doi.org/10.1007/s12205-020-1391-5
A. Senouci, A. Ismail, N. Eldin, Time delay and cost overrun in Qatari public construction projects. Proced. Eng. 164, 368–375 (2016). https://doi.org/10.1016/j.proeng.2016.11.632
N Tesfahun Adugna 2015 A study of causes of delay and cost overrun in office construction projects in the eThekwini municipal area (Durban University of Technology, Durban, South Africa, Thesis, 2015)
Department of Economic Affairs, PPP Project Info. Ministry of Finance, Government of India (2021), Retrieved from https://www.pppinindia.gov.in/infrastructureindia/web/guest/view- project?p_p_id=viewproject_WAR_Projectportlet&p_p_lifecycle=0&p_p_state=pop_up&p_p_mode=view&p_p_col_id=column- 1&p_p_col_count=1&_viewproject_WAR_Projectportlet_jspPage=%2Fhtml%2Fviewproject%2Fppp_all_info.jsp&_viewproject_WAR_Projectportlet_sessionId=25706
J.M. Conway, A.I. Huffcutt, A review and evaluation of exploratory factor analysis practices in organizational research. Org. Res. Meth. 6(2), 147–168 (2003)
D.J. Mundfrom, D.G. Shaw, T.L. Ke, Minimum sample size recommendations for conducting factor analyses. Int. J. Test. 5(2), 159–168 (2005). https://doi.org/10.1207/s1532757fijt0502-4
M.C. Howard, A review of exploratory factor analysis decisions and overview of current practices: What we are doing and how can we improve? Int. J. Hum. Comp. Inter. 32(1), 51–62 (2016). https://doi.org/10.1080/10447318.2015.1087664
M.W. Watkins, Exploratory factor analysis: A guide to best practice. J. Black Psych. 44(3), 1–28 (2018). https://doi.org/10.1177/0095798418771807
Kandaswamy S, The basics of Monte Carlo simulation: A tutorial. Paper presented at Project Management Institute Annual Seminars & Symposium, Nashville, TN. Newtown Square, PA: Project Management Institute, (2001)
India Infoline News Service, Sadbhav Infrastructure Project's subsidiary receives Provisional Completion Certificate (2020), https://www.indiainfoline.com/article/news-sector-cap-goods-eng-infra/sadbhav-infrastructure-project%E2%80%99-subsidiary-receives-provisional-completion-certificate-120072400739_1.html
Funding
No funding was availed for the research work.
Author information
Authors and Affiliations
Corresponding author
Ethics declarations
Conflict of interest
On behalf of all authors, the corresponding author states that there is no conflict of interest.
Additional information
Publisher's Note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Rights and permissions
About this article
Cite this article
Reddy, H.L., Nagakumar, M.S. Development and Validation of a Delay Assessment Matrix for Road and Highway Projects. J. Inst. Eng. India Ser. A 103, 1053–1061 (2022). https://doi.org/10.1007/s40030-022-00651-3
Received:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s40030-022-00651-3