Development and Validation of a Delay Assessment Matrix for Road and Highway Projects

  • Original Contribution
  • Published:
Journal of The Institution of Engineers (India): Series A Aims and scope Submit manuscript

Abstract

The study aims to gather information and assess the extent of delays and their impact on road and highway projects in India. The objective is to develop a delay assessment matrix for easy quantification of delay-causing factors on project duration. A mixed-method approach was used for data collection wherein information was gathered through literature review, questionnaire survey, interviews, and responses under the RTI act. The collected information was screened, verified, and analyzed using statistical tools. Factor analysis was employed to arrive at a final list of 20 factors grouped in a 3 × 3 matrix, having the probability of occurrence vs. impact on project duration as the axes. The model was tested on a recently completed highway project using the Monte Carlo simulation technique. The case simulation revealed the project duration to be 1237 days (50% probability) which was found to be in agreement with the actual project duration of 1236 days. The analytical contribution of the study is the development of the matrix by fixing up the range of probability of occurrence and the impact that these factors would have on project duration. The delay assessment matrix along with the methodology can be used as a practical tool by practitioners in their projects during the planning stages. The methodology can be adopted for ongoing and upcoming projects for successful delay prediction and quantification of delay impacts in the projects.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1

Similar content being viewed by others

References

  1. IBEF Indian road industry report (2021), https://www.ibef.org/industry/roads-presentation

  2. Department of economic affairs, economic survey 2020–21: Volume I. Ministry of finance, government of India (2021), https://www.indiabudget.gov.in/economicsurvey/

  3. Infrastructure and project monitoring division, 425th flash report on central sector projects. Ministry of statistics and programme implementation, government of India (2021), http://www.cspm.gov.in/english/flr/FR_Apr_2021.pdf

  4. G. Elawi, M. Algahtany, D. Kashiwagi, Owners’ perspective of factors contributing to project delay: Case studies of road and bridge projects in Saudi Arabia. Proced. Eng. 145, 1402–1409 (2016). https://doi.org/10.1016/j.proeng.2016.04.176

    Article  Google Scholar 

  5. Y.C. Kog, Major construction delay factors in Portugal, the UK, and the US. Pract. Period. Struct. Des. Constr. 23(4), 04018024 (2018). https://doi.org/10.1061/(ASCE)SC.1943-5576.0000389

    Article  Google Scholar 

  6. R. Asiedu, H. Alfen, Understanding the underlying reasons behind time overruns of government building projects in Ghana. KSCE J. Civ. Eng. 20(6), 2103–2111 (2015). https://doi.org/10.1007/s12205-015-0544-4

    Article  Google Scholar 

  7. A. Kavuma, J. Ock, H. Jang, Factors influencing time and cost overruns on freeform construction projects. KSCE J. Civ. Eng. 23(4), 1442–1450 (2019). https://doi.org/10.1007/s12205-019-0447-x

    Article  Google Scholar 

  8. J. Larsen, G. Shen, S. Lindhard, T. Brunoe, Factors affecting schedule delay, cost overrun, and quality level in public construction projects. J. Manag. Eng. 32(1), 04015032 (2016). https://doi.org/10.1061/(ASCE)me.1943-5479.0000391

    Article  Google Scholar 

  9. Y.C. Kog, Project management and delay factors of public housing construction. Pract. Period. Struct. Des. Constr. 23(1), 04017028 (2018). https://doi.org/10.1061/(ASCE)sc.1943-5576.0000350

    Article  Google Scholar 

  10. C. Tengan, C. Aigbavboa, Level of stakeholder engagement and in monitoring and evaluation of construction projects in Ghana. Proced. Eng. 196, 630–637 (2017). https://doi.org/10.1016/j.proeng.2017.08.051

    Article  Google Scholar 

  11. S. Kim, K. Tuan, V. Luu, Delay factor analysis for hospital projects in Vietnam. KSCE J. Civ. Eng. 20(2), 519–529 (2015). https://doi.org/10.1007/s12205-015-0316-1

    Article  Google Scholar 

  12. Ö. Ökmen, Risk assessment for determining best design alternative in a state-owned irrigation project in Turkey. KSCE J. Civ. Eng. 20, 109–120 (2016). https://doi.org/10.1007/s12205-015-0397-x

    Article  Google Scholar 

  13. Y. Mittal, V. Paul, A. Rostami, M. Riley, A. Sawhney, Delay factors in construction of healthcare infrastructure projects: A comparison amongst developing countries. Asian J. Civ. Eng. 21(4), 649–661 (2020). https://doi.org/10.1007/s42107-020-00227-1

    Article  Google Scholar 

  14. O. Abbasi, E. Noorzai, J.K. Gharouni, M. Golabchi, Exploring the causes of delays in construction industry using a cause-and-effect diagram: Case Study for Iran. J. Archit. Eng. 26(3), 05020008 (2020). https://doi.org/10.1061/(asce)ae.1943-5568.0000431

    Article  Google Scholar 

  15. M. Ruqaishi, H. Bashir, Causes of delay in construction projects in the oil and gas industry in the Gulf cooperation council countries: A case study. J. Manag. Eng. 31(3), 05014017 (2015). https://doi.org/10.1061/(asce)me.1943-5479.0000248

    Article  Google Scholar 

  16. M. Gunduz, Y. Nielsen, M. Ozdemir, Fuzzy assessment model to estimate the probability of delay in Turkish construction projects. J. Manag. Eng. 31(4), 04014055 (2015). https://doi.org/10.1061/(asce)me.1943-5479.0000261

    Article  Google Scholar 

  17. O. Bagaya, J. Song, Empirical study of factors influencing schedule delays of public construction projects in Burkina Faso. J. Manag. Eng. 32(5), 05016014 (2016). https://doi.org/10.1061/(asce)me.1943-5479.0000443

    Article  Google Scholar 

  18. Y.C. Kog, Construction delays in Indonesia, Malaysia, Thailand, and Vietnam. Pract. Period. Struct. Des. Constr. 24(3), 04019013 (2019). https://doi.org/10.1061/(asce)sc.1943-5576.0000434

    Article  Google Scholar 

  19. G. Niazi, N. Painting, Significant factors causing cost overruns in the construction industry in Afghanistan. Proced. Eng. 182, 510–517 (2017). https://doi.org/10.1016/j.proeng.2017.03.145

    Article  Google Scholar 

  20. Z.M. Yaseen, Z.-H. Ali, S.Q. Salih, N. Al-Ansari, Prediction of risk delay in construction projects using a hybrid artificial intelligence model. Sustainability 12(4), 1514 (2020). https://doi.org/10.3390/su12041514

    Article  Google Scholar 

  21. M. Sanni-Anibire, R. Mohamad Zin, S. Olatunji, Causes of delay in the global construction industry: A meta analytical review. Int. J. Constr. Manag. (2020). https://doi.org/10.1080/15623599.2020.1716132

    Article  Google Scholar 

  22. S. Alsharif, A. Karatas, A framework for identifying causal factors of delay in nuclear power plant projects. Proced. Eng. 145, 1486–1492 (2016). https://doi.org/10.1016/j.proeng.2016.04.187

    Article  Google Scholar 

  23. A.A. Alsulaiti, L. Kerbache, Analysis of critical delay factors in construction projects with a focus on Qatar. Int. J. Busin. Econ. Res. 9(3), 130–139 (2020). https://doi.org/10.11648/j.ijber.20200903.16

    Article  Google Scholar 

  24. M. Alzara, J. Kashiwagi, D. Kashiwagi, A. Al-Tassan, Using PIPS to minimize causes of delay in Saudi Arabian construction projects: University case study. Proc. Eng. 145, 932–939 (2016). https://doi.org/10.1016/j.proeng.2016.04.121

    Article  Google Scholar 

  25. Dixit S, Sharma K Factors influencing construction time delay on high rise projects in India, Proceedings of the Creative Construction Conference, Article 047, (2019), https://doi.org/10.3311/CCC2019-047

  26. T. Gebrehiwet, H. Luo, Analysis of delay impact on construction project based on RII and correlation coefficient: Empirical study. Proced. Eng. 196, 366–374 (2017). https://doi.org/10.1016/j.proeng.2017.07.212

    Article  Google Scholar 

  27. M. Islam, B. Suhariadi, Construction delays in privately funded large building projects in Bangladesh. Asian J. Civ. Eng. 19(4), 415–429 (2018). https://doi.org/10.1007/s42107-018-0034-3

    Article  Google Scholar 

  28. M. Jahangoshai Rezaee, S. Yousefi, R.K. Chakrabortty, Analyzing causal relationships between delay factors in construction projects: A case study of Iran. Int. J. Manag. Proj. Bus. 14(2), 412–444 (2021). https://doi.org/10.1108/IJMPB-01-2019-0020

    Article  Google Scholar 

  29. M. Kadry, H. Osman, M. Georgy, Causes of construction delays in countries with high geopolitical risks. J. Constr. Eng. Manag. 143(2), 04016095 (2017). https://doi.org/10.1061/(asce)co.1943-7862.0001222

    Article  Google Scholar 

  30. H. Kang, Y. Kim, Analysis of the probabilistic cost variation ranges according to the effect of core quantitative risk factors for an overseas plant project: Focused on a Middle East gas plant project. KSCE J. Civ. Eng. 20(2), 509–518 (2015). https://doi.org/10.1007/s12205-015-0497-7

    Article  Google Scholar 

  31. M. Magdy, M. Georgy, H. Osman, M. Elsaid, Delay analysis methodologies used by engineering and construction firms in Egypt. J. Leg. Aff. Disput. Resolut. Eng. Constr. 11(3), 04519006 (2019). https://doi.org/10.1061/(asce)la.1943-4170.0000293

    Article  Google Scholar 

  32. N. Perera, M. Sutrisna, T. Yiu, Decision-Making model for selecting the optimum method of delay analysis in construction projects. J. Manag. Eng. 32(5), 04016009 (2016). https://doi.org/10.1061/(asce)me.1943-5479.0000441

    Article  Google Scholar 

  33. H. Pham, T. Luu, S. Kim, D. Vien, Assessing the impact of cost overrun causes in transmission lines construction projects. KSCE J. Civ. Eng. 24(4), 1029–1036 (2020). https://doi.org/10.1007/s12205-020-1391-5

    Article  Google Scholar 

  34. A. Senouci, A. Ismail, N. Eldin, Time delay and cost overrun in Qatari public construction projects. Proced. Eng. 164, 368–375 (2016). https://doi.org/10.1016/j.proeng.2016.11.632

    Article  Google Scholar 

  35. N Tesfahun Adugna 2015 A study of causes of delay and cost overrun in office construction projects in the eThekwini municipal area (Durban University of Technology, Durban, South Africa, Thesis, 2015)

  36. Department of Economic Affairs, PPP Project Info. Ministry of Finance, Government of India (2021), Retrieved from https://www.pppinindia.gov.in/infrastructureindia/web/guest/view- project?p_p_id=viewproject_WAR_Projectportlet&p_p_lifecycle=0&p_p_state=pop_up&p_p_mode=view&p_p_col_id=column- 1&p_p_col_count=1&_viewproject_WAR_Projectportlet_jspPage=%2Fhtml%2Fviewproject%2Fppp_all_info.jsp&_viewproject_WAR_Projectportlet_sessionId=25706

  37. J.M. Conway, A.I. Huffcutt, A review and evaluation of exploratory factor analysis practices in organizational research. Org. Res. Meth. 6(2), 147–168 (2003)

    Article  Google Scholar 

  38. D.J. Mundfrom, D.G. Shaw, T.L. Ke, Minimum sample size recommendations for conducting factor analyses. Int. J. Test. 5(2), 159–168 (2005). https://doi.org/10.1207/s1532757fijt0502-4

    Article  Google Scholar 

  39. M.C. Howard, A review of exploratory factor analysis decisions and overview of current practices: What we are doing and how can we improve? Int. J. Hum. Comp. Inter. 32(1), 51–62 (2016). https://doi.org/10.1080/10447318.2015.1087664

    Article  Google Scholar 

  40. M.W. Watkins, Exploratory factor analysis: A guide to best practice. J. Black Psych. 44(3), 1–28 (2018). https://doi.org/10.1177/0095798418771807

    Article  Google Scholar 

  41. Kandaswamy S, The basics of Monte Carlo simulation: A tutorial. Paper presented at Project Management Institute Annual Seminars & Symposium, Nashville, TN. Newtown Square, PA: Project Management Institute, (2001)

  42. India Infoline News Service, Sadbhav Infrastructure Project's subsidiary receives Provisional Completion Certificate (2020), https://www.indiainfoline.com/article/news-sector-cap-goods-eng-infra/sadbhav-infrastructure-project%E2%80%99-subsidiary-receives-provisional-completion-certificate-120072400739_1.html

Download references

Funding

No funding was availed for the research work.

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Harish L. Reddy.

Ethics declarations

Conflict of interest

On behalf of all authors, the corresponding author states that there is no conflict of interest.

Additional information

Publisher's Note

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Reddy, H.L., Nagakumar, M.S. Development and Validation of a Delay Assessment Matrix for Road and Highway Projects. J. Inst. Eng. India Ser. A 103, 1053–1061 (2022). https://doi.org/10.1007/s40030-022-00651-3

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s40030-022-00651-3

Keywords

Navigation