Introduction

Vulnerability is enormous in drilling operations and activities, particularly in Exploratory Wells or the wells with limited subsurface data. Drilling and Well Operations comprise numerous unpredictable operations and steps, which include both controllable and non-controllable elements/factors. Every one of these variables add to the complexity of the well and likewise sufficient possibilities should be worked in time and cost assessments of the drilling activities (Nzeda and Schamp 2014). In any case, the most ideal approach to correlate various wells is by ranking them while considering maximum possible parameters. Well Complexity Calculator developed here considers multiple factors to produce a single digit which is true representative of Well Complexity. Several studies have proposed methodologies and concepts that help quantify the costs and complexity of the well due to different parameters such as constraints posed by well drilling and planning factors, broadly classified by Well Complexity Index. It was proposed that many researches have been carried out to determine the well complexity and its costs; however, reservations exist when evaluating and predicting the factors which influence the performance of the well operations (Kaiser 2007). A number of conventional techniques have also been proposed in this aspect, where offset records are used to analyze the actual performance of the well in an oil field; however, these standards and records are subjective in nature and tends to be viable for short range and technical performance standards (Pessier and Fear 2013).

According to Nzeda, and Schamp (2014), the complexity of well operations, including drilling, completion, testing and stimulation of the well, is a risk-prone process that requires accurate amalgamation of scientific and technical concepts of petroleum engineering. However, these mathematical and computational concepts for precise calculations are integrated with the consideration of far more subjective and qualitative well operations which includes the physical hazards such as environmental catastrophe. This poses a continuous hazard throughout the well operations.

To safeguard the economics and safety of the well operations, a number of studies show the incorporation of various factors which need to be considered during the contingency planning of the complex wells which are difficult to be drilled and require a competitive budget strategy (Ezenwanne and Giadom 2018; Curry et al. 2013; Oag and Williams 2013; Dupriest 2013). Mason and Judzis (2013) proposed that the method to calculate the future performance of future higher step-out wells are very challenging. They considered that departure-to-TVD ratio, often attributed as ERD, explains the difficulty of drilling offshore wells. They demonstrated that the offset well data reveals the “Risks and Limits” of the drilling such difficult wells. The Saudi Arabian Oil Company also mentioned a similar issue by which they classified their ERW as per the measured depth (MD) and derived a new method for designing deep wells that reached a total depth of 17,600 ft (Muñoz et al. 2016).

According to Nzeda, and Schamp (2014), the complexity of well operations, including drilling, completion, testing and stimulation of the well, is a risk-prone process that requires accurate amalgamation of scientific and technical concepts of petroleum engineering. They developed Drilling Complexity Index (DCI) and Planning Complexity Index (PCI) and accordingly declared their combination as Well Complexity Index (WCI). They declared it as is a very useful tool which categorizes the complexity of the well. It is used as contingency indicator for the level of complexity to be faced in the well operations. DCI can be used at any interval of well delivery process. DCI is often used in planning of new wells. It is suggested by researchers that DCI is used in predicting the non-productive time (NPT) of the drilling operations, time and cost of the drilling plans, and portfolio management and found Drilling Complexity Index has found to be of major importance in predicting the hazards and risks in the overall well operations (Nzeda and Schamp 2014; Nzeda et al. 2014). Drilling Complexity Index (DCI), together with Planning Complexity Index (PCI), is classified as Well Complexity Index (WCI). DCI involves the challenges of subsurface operations, such as drilling rigs and equipment. Planning complexity index covers surface challenges, considering geopolitics of the well location, the climate and well logistics. These two factors are very important in project evaluation of well planning and operations (Nzeda et al. 2014).

Drilling a well is a very expensive venture, and several factors influence its drilling cost; the common characteristics are considered to be the rent of the drilling rig, transport and weather conditions, etc. Irrespective of the high-tech equipment, the weather downtime always incorporates considerable variation in the time required to drill a well (Jenkins and Crockford 2013). Loberg et al. (2013) considers the economic feasibility an important aspect in well planning, alongside technical considerations. Probabilistic well cost estimate was suggested that would strengthen and systemize the corresponding workflows of the drilling of the well.

It is suggested that Well Complexity Index is a very useful technique that allows the comprehensive planning and operating the drilling projects, addressing a broad range of aspects, from the well planning phase to the drilling phase. WCI significantly helps to evaluate the resources needed for the project and anticipated non-productive time (Nzeda et al. 2014). In any case, the most ideal approach to correlate various wells is by ranking them while considering maximum possible parameters. In this research paper, Well Complexity Calculator (WCC) has been developed where 51 oil and gas drilling well complexity parameters have been utilized to develop Well Complexity Calculator. The parameters selected here are more in quantity compared to work already done in this regard (Nzeda et al. 2014).

The parameters which are used to develop in previously published work are very few. Using a few parameters to define oil and gas well drilling complexities sometimes results in erroneous outcomes. In previous work, the detail of the procedure for application of the Well Complexity Index was also not available. In contrast, in this research paper, parameters are categorized into three main complexities types named Design Well Complexity, Geological Well Complexity and Project Well Complexity. Design and Geological Well Complexities combine to form Drilling Well Complexity, and then Drilling Well Complexity and Project Well Complexity combine to form Well Complexity. This categorization is different from the work already done in this regard (Nzeda et al. 2014) and allows to see the impact of design-related parameters, geological parameters and project-related parameters separately as well as in combination (Fig. 1).

Fig. 1
figure 1

Flowchart of the problem description

Earlier work also doesn’t explain the process of preparation of the calculator itself. Here, step-by-step procedure is presented following which any Company involved in Drilling & Well Operations can develop their own Well Complexity Calculator and accordingly integrate it into its Well Engineering Management System/Well Delivery System.

The later part of this paper consists of different sections. Firstly, materials and methods are presented in Sect. 2, which represent the main parameters selection and calculator development methodology. Section 3 is results and discussion and the last section, which is Sect. 4, is Summary and Conclusions.

Development of well complexity calculator: materials and method

The main major material required in this research study is to have the data of different oil and gas drilling wells, related with complexities of drilling at different levels.

Formulation of well complexity parameters and sub parameters

Based on the literature review and consultation with different industry experts, multiple parameters were formulated under each category; considering the application of Well Complexity Calculator on the single lateral Wells being drilled only in the onshore environment. Table 1 presents the parameters for each category used for the development of Well Complexity Calculator. These parameters are more in quantity compared to work already done in this regard (Nzeda et al. 2014).

Table 1 Well complexity parameters

Formulation of sub-parameters

All the parameters mentioned in Table 1 were further divided into the sub-parameters. Sub-parameters against each parameter are listed in detail in Appendix B.

Categorization of well complexity

Work already performed on Well Complexity Indices involves either single major category or fewer categories (Nzeda et al. 2014). Here Well Complexity was categorized into following three main categories:

  1. 1.

    Design well complexity

  2. 2.

    Geological well complexity

  3. 3.

    Project well complexity

    However, based on the combined effects of three main categories mentioned above, following two categories are produced:

  4. 4.

    Drilling well complexity (combined effect of Sr # 1 and 2)

  5. 5.

    Well complexity (combined effect of Sr # 1, 2 and 3)

Development of survey forms and conducting the survey

After formulating Well Complexity Parameters and Sub-Parameters, different options were considered for getting the weightage factor against each parameter and rating against each sub-parameter. Workshop was one of the options, but it was not possible to gather all the relevant industry experts and professionals in one workshop for this purpose. Therefore, option of online survey was selected being easier and convenient to get the input from all the industry experts and professionals. Google Survey Forms were utilized for this purpose. Extract from the Google Survey being used here is presented in Appendix A.

Aim of the survey was to rate different parameters against each other. Linear numeric rating scale from 1 to 10 was provided for recording the responses. Numeric 10 means that this parameter has the strongest impact on complexity, whereas 01 means that this particular parameter has the weakest impact on the complexity. Then sub-parameters were to be rated within each parameter separately. Most complicated/difficult sub-parameter was awarded 10, whereas most easy sub-parameter was awarded 00. Other sub-parameters within the parameter were awarded from 10 to 00 depending upon their complication/complexity/difficulty level.

Data quality check

After receiving raw data from survey, a rigorous exercise has been done for the data quality check. Aim of the data quality check was to filter the survey results which were ambiguous or were not in line with the question being asked. On certain instances, it was observed that survey participants could not understand the complexity parameters and hence entered the same rating against each of the sub-parameter. Such types of answers were removed from the survey in order to make the quality of the results better and more reliable.

Analysis of survey results

After quality check of the raw survey data, different types of analysis were performed on the data. Analysis was done mainly on following three methodologies. It is pertinent to mention that mean/average of the data produced very misleading results and hence was not adopted for the analysis.

  1. 1.

    Median. It is a value or quantity lying at the midpoint of a frequency distribution of observed values or quantities, such that there is an equal probability of falling above or below it.

  2. 2.

    Mode. It is the number which appears most often in set of numbers.

  3. 3.

    Monte Carlo Simulation. There are many ways in which Monte Carlo Simulation can be defined. However, it is a broad class of computational algorithms that rely on repeated random sampling, standard deviation, mean and probability to obtain numerical results. Accuracy of Monte Carlo Simulation depends on the number of iterations which are selected, however increase of iterations can increase the time required for each calculation. Here in this analysis, 5000 iterations were selected with 55% probability, which has showed reasonable consistency in the results.

Normalization and compilation of analysis results

After performing the quality check and three analysis mentioned above, obtained results were normalized. Aim of the normalization was to make the highest rated sub-parameter within each parameter equal to 10 and the lowest rated equal to 0 and accordingly rest of the sub-parameters spreading as per the ratio of actual survey results obtained. This was done to make the results in line with the original aim of the survey, which was not obtained as such due to the inputs from the survey participants. Following equation was used to normalize the survey results.

$${\text{Normalized Sub}} - {\text{Parameter Results }} = { }\frac{{\left( {{\text{Rating }} - {\text{ Lowest Rating}}} \right){ } \times { }\left( {{\text{Highest Rating }} - {\text{ Zero}}} \right){ }}}{{\left( {{\text{Highest Rating }} - {\text{ Lowest Rating}}} \right)}}$$
(1)

Thereafter, resultant ratings of each sub-parameters were multiplied with the weightage factor of each well complexity parameter to produce the end results of each well complexity sub-parameter. After applying weightage factor of parameters on the rating of each sub-parameter, resultant values made all the sub-parameters quantitatively comparable with each other although many of them are purely qualitative in nature. This normalization and compilation of survey results was performed for all the three analysis methodologies (Median, Mode and Monte Carlo Simulation).

Results and discussion

Figures 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18, 19, 20, 21, 22, 23, 24, 25, 26, 27, 28, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 44, 45, 46, 47, 48, 49, 50, 51 and 52 present all the three methodologies results of Well Complexity Sub-Parameters for each parameter. Out of the three methodologies, Median showed the best suited results for all the parameters without any abnormality in the trend lines/graphs, whereas Mode and Monte Carlo Simulation results show some abnormality in the trend lines on some instances which was primarily due to the type of survey input and not because of the methods itself. Anomaly in Monte Carlo result is obtained in Fig. 2, whereas anomaly in Mode result is obtained in Fig. 31. Median has not showed anomaly for any result. Accordingly, Median results were selected for onward analysis and utilization for the preparation of Well Complexity Calculator. Figures 23, 25, 29 and 33 show those parameters in which multiple sub-parameters can be selected, whereas for the rest of the parameters single sub-parameter can be selected. Resultant ratings based on Median are listed in Appendix B.

Fig. 2
figure 2

Well type

Fig. 3
figure 3

Rig type

Fig. 4
figure 4

Rig capability

Fig. 5
figure 5

Total measured depth

Fig. 6
figure 6

True vertical depth

Fig. 7
figure 7

Well shape

Fig. 8
figure 8

Max inclination

Fig. 9
figure 9

Max dogleg

Fig. 10
figure 10

No. of casings

Fig. 11
figure 11

No. of contingent hole sections

Fig. 12
figure 12

Smallest hole size

Fig. 13
figure 13

Target tolerance

Fig. 14
figure 14

Off-set wells availability

Fig. 15
figure 15

Type of mud

Fig. 16
figure 16

Max mud weight

Fig. 17
figure 17

Drilling margin

Fig. 18
figure 18

No. of well targets

Fig. 19
figure 19

UBD/MPD application

Fig. 20
figure 20

Liner hanger application

Fig. 21
figure 21

CwD/RwC application

Fig. 22
figure 22

Under-reaming/bi-center bit

Fig. 23
figure 23

Cementing operations

Fig. 24
figure 24

New technology application

Fig. 25
figure 25

Formations issues

Fig. 26
figure 26

Uncertainty in formation tops

Fig. 27
figure 27

Pore Grad. evaluation method

Fig. 28
figure 28

Frac. Grad. evaluation method

Fig. 29
figure 29

Hazardous gas presence

Fig. 30
figure 30

Max bottom hole temperature

Fig. 31
figure 31

Max. wellhead pressure

Fig. 32
figure 32

Regional difficulty factor

Fig. 33
figure 33

Geographic factor

Fig. 34
figure 34

Average drillability

Fig. 35
figure 35

Coring operations

Fig. 36
figure 36

Wireline logging

Fig. 37
figure 37

MDT logging

Fig. 38
figure 38

VSP/VSI

Fig. 39
figure 39

LWD

Fig. 40
figure 40

Contracts already signed

Fig. 41
figure 41

Material available/delivered

Fig. 42
figure 42

Price volatility

Fig. 43
figure 43

Weather NPT expectation

Fig. 44
figure 44

Natural events/disasters

Fig. 45
figure 45

Site security condition

Fig. 46
figure 46

Local/political instability

Fig. 47
figure 47

Site access

Fig. 48
figure 48

Ownership type

Fig. 49
figure 49

Permitting

Fig. 50
figure 50

Project resources

Fig. 51
figure 51

Planning time

Fig. 52
figure 52

Logistics/mobilization time

Creation of well complexity calculator in excel spreadsheet

Based on the results listed in Appendix-B, Well Complexity Calculator was created in Excel Spreadsheet with the simple user interface. User is required to input the well information and select sub-parameter against each parameter for the well under investigation. Screenshot of the Well Complexity Calculator is presented in Appendix C.

All the parameters are created with the drop-down option to select one of the available sub-parameters, whereas Parameters # 22, 24, 28 and 32 are with multiple selections of sub-parameters. However, each of the available sub-parameter cannot be selected in this case as well, for example in Parameter # 24, out of “Single Loss Zone” and “Multiple Loss Zone” one sub-parameter can be selected and likewise out of “Single Gain/Influx Zone” and “Multiple Gain/Influx Zones” one sub-parameter can be selected to avoid erroneous results. Hence, calculator is macro-enabled, and VB codes are included in it in order to apply these logics which restrict user to select one of these two sub-parameters while allowing the selection of other sub-parameters.

Based on the sub-parameters selected by user, scores are picked which are accumulated and accordingly Well Complexities were calculated on the Scale of 10 through Eqs. 26.

$${\text{Design}}\;{\text{ Well }}\;{\text{Complexity}} = \frac{{10 \; \times \;{\text{Sum }}\;{\text{of }}\;{\text{Scores }}\;{\text{for }}\;{\text{Selected }}\;{\text{Sub }}\;{\text{Parameters }}\;{\text{for }}\;{\text{Parameters }}\;1{ }\;{\text{to }}\;23{ }}}{{{\text{Sum }}\;{\text{of}}\;{\text{ Maximum}}\;{\text{ Scores }}\;{\text{for }}\;{\text{Parameters }}\;1{ }\;{\text{to }}\;23}}$$
(2)
$${\text{Geological Well Complexity}} = \frac{{10{ } \times {\text{Sum of Scores for Selected Sub Parameters for Parameters }}\;24{ }\;{\text{to }}\;38{ }}}{{{\text{Sum of Maximum Scores for Parameters }}\;24{ }\;{\text{to }}\;38}}$$
(3)
$${\text{Project Well Complexity}} = \frac{{10{ } \times {\text{ Sum of Scores for Selected Sub Parameters for Parameters }}\;39\;{\text{ to}}\;{ }51{ }}}{{{\text{Sum of Maximum Scores for Parameters}}\;{ }39\;{\text{ to}}\;{ }51}}$$
(4)
$${\text{Drilling Well Complexity}} = \frac{{10{ } \times {\text{ Sum of Scores for Selected Sub Parameters for Parameters}}\;{ }1\;{\text{ to }}\;38{ }}}{{{\text{Sum of Maximum Scores for Parameters}}\;{ }1{ }\;{\text{to }}\;38}}$$
(5)
$${\text{Well Complexity}} = { }\frac{{10{ } \times {\text{Sum of Scores for Selected Sub Parameters for Parameters}}\;{ }1\;{\text{ to }}\;51{ }}}{{{\text{Sum of Maximum Scores for Parameters }}\;1{ }\;{\text{to}}\;{ }51}}$$
(6)

Actual wells data and adjustment of well complexity equations

One of the most critical step was to verify the results of the Well Complexity Calculator. In this regard, 66 actual wells’ camouflaged data were utilized having different specifications and being drilled in different areas of Pakistan. Data used in Well Complexity Calculator are of public nature without any confidentiality. For each well, respective sub-parameters were chosen to obtain the outcomes of all the five Well Complexities.

After calculating Well Complexities of all the wells, it was observed that Eqs. 26 need adjustment with some factor since denominator in these equations was leading to comparatively lower values for all the five Well Complexities. Hence, sensitivity was run and it was concluded that factor of 0.75 in denominator gave the resultant Well Complexities similar to prima-facie complexities of these Wells. This factor doesn’t change the complexity metric scale and is introduced to align the calculated Well Complexities with the perceived complexities of the well (Nzeda et al. 2014). This factor would vary depending on the type of wells in hand. Accordingly, based on the actual wells data presented here, Well Complexity Calculator equations were adjusted and are presented from Eqs. 711.

$${\text{Design Well Complexity}} = \frac{{10{ } \times {\text{Sum of Scores for Selected Sub Parameters for Parameters }}\;1{ }\;{\text{to }}\;23{ }}}{{0.75{ } \times {\text{ Sum of Maximum Scores for Parameters}}\;{ }1{ }\;{\text{to}}\;{ }23}}$$
(7)
$${\text{Geological Well Complexity}} = \frac{{10{ } \times {\text{Sum of Scores for Selected Sub Parameters for Parameters }}\;24\;{\text{ to }}\;38{ }}}{{0.75{ } \times \;{\text{Sum of Maximum Scores for Parameters}}\;{ }24\;{\text{ to}}\;{ }38}}$$
(8)
$${\text{Project Well Complexity}} = \frac{{10{ } \times {\text{ Sum of Scores for Selected Sub Parameters for Parameters }}\;39{ }\;{\text{to }}\;51{ }}}{{0.75\; \times {\text{ Sum of Maximum Scores for Parameters }}\;39\;{\text{ to }}\;51}}$$
(9)
$${\text{Drilling Well Complexity}} = \frac{{10{ } \times {\text{ Sum of Scores for Selected Sub Parameters for Parameters }}\;1{ }\;{\text{to }}\;38{ }}}{{0.75{ } \times {\text{ Sum of Maximum Scores for Parameters }}\;1\;{\text{ to}}\;{ }38}}$$
(10)
$${\text{Well Complexity}} = \frac{{10{ } \times {\text{ Sum of Scores for Selected Sub Parameters for Parameters }}\;1{ }\;{\text{to }}\;51{ }}}{{0.75{ } \times {\text{ Sum of Maximum Scores for Parameters }}\;1\;{\text{ to }}\;51}}$$
(11)

Divisions of well complexities

Based on the Well Complexities calculated for actual Wells, following three division are concluded. However, these divisions can be adjusted as per the Company’s own assessment/requirement.

  1. 1.

    Low complexity wells for complexity values 0.00–3.49

  2. 2.

    Medium complexity wells for complexity values 3.50–6.49

  3. 3.

    High complexity well for complexity values 6.50–10.0

Results of Well Complexities are summarized in Table 2 and are presented in Figs. 53, 54, 55, 56 and 57 which show that wells selected for the analysis and verification of Well Complexity Calculator are having different complexities.

Table 2 Well complexities for actual wells
Fig. 53
figure 53

Design well complexity for actual wells

Fig. 54
figure 54

Geological well complexity for actual wells

Fig. 55
figure 55

Project well complexity for actual wells

Fig. 56
figure 56

Drilling well complexity for actual wells

Fig. 57
figure 57

Well complexity for actual wells

Integration of well complexity calculator in standard well engineering management system/well delivery system

Review of standard well engineering management system/well delivery system.

Well Engineering Management System/Well Delivery System of any company is a structured and a step-by-step approach for planning, execution and close-out of any drilling project (Nzeda and Schamp 2014). An actively maintained Well Engineering Management System/Well Delivery System provides the means to capture lessons learned and to retain knowledge for future reference (De Wardt 2010) (Fig. 58).

Fig. 58
figure 58

Standard well engineering management system/well delivery system

Without proper Well Engineering Management System/Well Delivery System, well planning, execution and close-out would always go through different approach each time the well is planned, executed and closed out. Different companies use Well Engineering Management System/Well Delivery System adjusted as per their business methodologies. However, basic concept and structure remains the same which aim toward following the same pattern each time the work is done and to include more steps as the approach becomes maturey.

Basic stages/phases in any Well Engineering Management System/Well Delivery System are as under:

  1. 1.

    Identify & Assess

  2. 2.

    Concept & Select

  3. 3.

    Define & Design

  4. 4.

    Execute & Deliver

  5. 5.

    Evaluate & Close-Out

Moreover, Well Engineering Management System/Well Delivery System also normally has the gate system or stage gate system in which associated gate keepers approve the things and gate is considered approved upon achievement of certain deliverables and documentations (Al-Salem et al. 2018).

Gate system verifies that no steps/stages/phases in Well Engineering Management System/Well Delivery System are skipped before moving ahead and all required documentation is secured and archived. Normally gates are simply named numerically as under:

  1. 1.

    Gate—I

  2. 2.

    Gate—II

  3. 3.

    Gate—III

  4. 4.

    Gate—IV

Standard Well Engineering Management System/Well Delivery System is presented in Error! Reference source not found., in which different steps from project initiation to project close-out are covered. It is also shown that how these steps are distributed among different stages/phases and being controlled by different gates.

Work already done in this regard considered Well Complexity Index mainly a planning tool (Blaise et al. 2014). However, its usage during the Evaluate & Close-Out phase is also very important. As presented in Fig. 59, Well Complexity Calculator can be integrated into a Standard Well Engineering Management System/Well Delivery System at following phases/stages:

  1. 1.

    Identify & Assess

  2. 2.

    Concept & Select

  3. 3.

    Define & Design

  4. 4.

    Evaluate & Close-Out

Fig. 59
figure 59

Well complexity calculator integrated into standard well engineering management system/well delivery system

Integration of well complexity calculator in identify & assess phase/stage

Well Complexity Calculator can be integrated at Identify & Assess phase/stage to get its benefit at the early stage of the project. In this phase/stage, upon carrying out preliminary well design based on available data and off-set wells review, well budget & project economics are prepared. Here, Well Complexity Calculator can be a useful tool to estimate the Time & Cost of a well by comparing its calculated Well Complexity value with company’s historical Well Complexity data. Historical data of Well Complexity vs Dry Hole Drilling Days can be used to estimate the time/refine the time estimates, whereas historical data of Well Complexity vs Dry Hole Drilling Cost can be used to estimate the cost/refine the cost estimates at this level.

Integration of well complexity calculator in concept & select phase/stage

Concept & Select phase starts with the receiving of well design requirements and criteria from G & G team, based on which well designing is done, whereas normally project specific organogram is prepared based on overall workload distribution, instead of criticality or complexity of the project itself.

In Concept & Select phase, Well Complexity Calculator can be used as the basis of resources/manpower allocation for the project according to its complexity level. Based on the Well Complexity value, project team of relevant experience and expertise can be formulated for a well in hand. Furthermore, during preparation and evaluation of different well design options, Well Complexity value for each well design can be calculated and be one of the key factors in making the selection of well design. Therefore, during the peer review meeting, Well Complexity value for each well design option can be presented along with pros and cons of different well design options in order to have a quantitative perspective of each well design along with conventional approach of qualitative selection.

Integration of well complexity calculator in define & design phase/stage

In Define & Design phase/stage, detailed well designing is performed, followed by more refined Time & Cost estimation which is then used in preparation and approval of Well AFE.

Well Complexity Calculator can be used for more refined time calculation. Normally, time estimation of any well depends on the available information from off-set wells for similar activities in which time for additional planned activities is added on same basis/assumptions. Using Well Complexity Calculator, a more structured approach can be adopted for calculation of time contingency and expected non-productive time by comparing Well Complexity value of a well in hand to the historical data of wells having similar complexity values. Thereafter, expected drilling time estimated using Well Complexity can be directly used to calculate the Well AFE. Moreover, comparison of AFE can be made with the historical data of Well Complexity vs Dry Hole Drilling Cost for further refinement.

In Define & Design phase/stage, the next important utilization of Well Complexity Calculator is to set Key Performance Indicator (KPI) Targets of the well in hand. If there is no Well Complexity Calculator in use, usually this step is skipped in a Standard Well Engineering Management System/Well Delivery System and Panned Dry Hole Drilling Days and Dry Hole Drilling Cost is considered to be the only KPI Target of the Well.

Integration of well complexity calculator in evaluate & close-out phase/stage

In Evaluate & Close-Out phase/stage, comparison is done between planned and actual KPIs. In addition to this, lesson learnt and best practices are tracked and documented for future reference along with reconciliation of actual Cost and Time.

Proper use of Well Complexity Calculator during Evaluate & Close-Out phase is important not only to compare the broader range of planned KPIs set for the well during Define & Design phase with the actual KPIs results but also to compare the actual KPIs results with historical data of Well Complexity values vs different well KPIs. In addition to this, Final Well Complexity values must be made part of historical database of Well Complexity in order to use it for future reference.

Summary and conclusion

Without the application of a system like Well Complexity Calculator, wells during planning phase are categorized as low, medium or high complexity based on either two to three major parameters or based on qualitative assessment of team involved in the project.

Furthermore, wells during the close-out phase are categorized as low, medium or high complexity based on the actual downtime/problems encountered during execution instead of actual Well complexity. Through the application of Well Complexity Calculator, Well Complexity can be computed considering multiple parameters. The main conclusive outcomes of this study are:

  • Well Complexity Calculator (WCC) developed here considers 51 different parameters.

  • Parameters are categorized into three main complexities types named Design Well Complexity, Geological Well Complexity and Project Well Complexity. Design and Geological Well Complexities combine to form Drilling Well Complexity, and then Drilling Well Complexity and Project Well Complexity combine to form Well Complexity.

  • This categorization allows to see the impact of design-related parameters, geological parameters and project-related parameters separately as well as in combination.

  • All the qualitative/quantitative parameters are converted into five different types of Well Complexities, where each complexity is a single digit on the scale of 10.

  • Well Complexity Calculator developed in this study is validated through the actual wells’ camouflaged data. Well Complexity Calculator can be used at any stage from initial planning to close out stage of a Well.

  • Well Complexity Calculator will give the practical benefit when it is integrated into Well Engineering Management System/Well Delivery System of an organization and made part of the approval processes. It is recommended to integrate Well Complexity Calculator into Well Engineering Management System/Well Delivery System or; in case of its absence; into a normal well planning process of any organization and accordingly evaluate its results against different Well KPIs.

  • If results are reasonable with respect to that organization, it can be made permanent part of the system.

  • In case of unsatisfactory results, Well Complexity Calculator can be further analyzed on the similar methods and methodologies carried out here for its refinement and adjustment with respect to that organization’s data and experience.

  • This research paper presents step-by-step procedure following which any Company involved in Drilling & Well Operations can develop their own Well Complexity Calculator and accordingly integrate it into its Well Engineering Management System/Well Delivery System.

The research outcomes from this study also show some limitations, which are:

  • The limitation of this study is kind of input that it received from the experts carrying out the initial assessment of the parameters and sub-parameters.

  • This limitation can be eradicated by careful quality check of the input data which has been done here in this research paper.

  • After rigorous exercise of data quality check, subsequent steps were carried out in order to prepare the Well Complexity Calculator.

  • Another limitation is the kind of well which was available for the verification of the calculator are single lateral wells being drilled in onshore environment. The calculator developed here is applicable for single lateral wells being drilled in the onshore environment.

  • However, steps explained in this research papers will remain same for preparation of Well Complexity Calculator with the inclusion of number of laterals and drilling environment as two more parameters; and accordingly this limitation can be eliminated as well.