SIR LYNDEN MACASSEY—Are you ready, sir?

THE ARBITRATOR—Yes.

SIR LYNDEN MACASSEY—Sir, as you probably know from the submission to you in this case this is an Arbitration between S. Pearson & Son (Contracting Department) Ltd., and the Belfast Cityand District Water Commissioners. I hardly like to call it a dispute. It really is an application to you for the purpose of arriving at some solution to difficulties in connection with the contract between Messrs Pearson and the Belfast Water Commissioners for the construction of a Reservoir in the Silent Valley.Footnote 1

With this modest exchange, the arbitration proceedings—rather optimistically characterised by the representative for the plaintiff as hardly a dispute—began on Monday morning 13th December 1926. The arbitration regarded the construction difficulties at the Silent Valley Reservoir project. The reputation of both parties, contractors and Water Commissioners, were at stake. Belfast water ratepayers disliked the expensive project. Its previous invocation by the Water Commissioners during the Boundary Commission dispute, made the project particularly controversial along a polarized nationalist/unionist line of tension in the province directly after partition and very recent violent conflict. The project was thus subject to possible cancellation in the event of an acrimonious dispute, a situation which neither the Water Commissioners nor the contractors desired. And this is perhaps why the barrister for the contractor chose to downplay the crisis.

Begun in the summer of 1923, the Silent Valley Reservoir was the first large scale civil engineering project after the division between the north and the south of Ireland (Fig. 1). It was also the continuation of a previous project. In the late nineteenth century, a portion of the Kilkeel and Annalong Rivers in the Mourne Mountains had been diverted 35 miles to provide water for the growing industrial city of Belfast in the north of Ireland. A reservoir in the mountains was also planned at a later date but this was delayed by the Great War and then by Irish political instability plus the high cost of construction in the immediate post war period.

Fig. 1
figure 1

Source: scanned image

Map printed and distributed by the Water Commissioners during boundary debates in 1924, 2 years prior to the arbitration. Evidence such as this, said to be “non-political” by the Water Commissioners, was seen by others as opposinng any changes in the boundary of Northern Ireland and thus aligning with unionist rather than nationalist interests.

Before being completed, the Silent Valley Reservoir project had to overcome several obstacles. Firstly, the Mourne Mountains were claimed by the South of Ireland and thus subject to the Boundary Commission of the Anglo-Irish peace treaty. The Water Commissioners had brought important British political leaders to tour the Silent Valley construction site in an attempt to demonstrate how implausible a situation would be that the South should control the major water supply to the capital city of the North. The boundary crisis was deferred by assigning a commission which would report back, but ultimately never did. The report was leaked in 1925 but disclaimed, thus consolidating the existing arrangement of boundary. Gramscian historians Bew, Patterson and Gibbon write, “…the state of Northern Ireland began in 1921 or between 1921 and 1925 when the boundary commission was laid to rest”.Footnote 2 The importance of the Boundary Commission shouldn’t be understated. The viability of the fledgling state required a boundary which maintained a unionist electoral majority (i.e., primarily Protestant), retained areas vital to its economic viability (for example the linen mills region south west of Belfast), and retained control of vital resources (water). Secondly, as the Boundary Commission was deliberating, the combination of fluid subsoil and the failure to locate bedrock at expected depth brought construction to a halt while an engineering, political, and legal solution was sought for the expensive and soon to be publicly controversial project.

Why hasn’t existing historiography of the Silent Valley reservoir identified this possible threat to the viability of early Northern Ireland?Footnote 3 In part this might have been the skillful silence of the architects of the Silent Valley Reservoir downplaying potential crisis or vulnerability, while they played out a timing in which the boundary and reservoir difficulties did not collide. In part this may have been the outcome of a skillful legal resolution about the resources and time necessary to determine whether the reservoir was viable in the face of fluid sub-soil excavation difficulties.

As this article will show, the legal solution was grounded in the materiality of the subsoil (nature) and also, of note, procedurally grounded in the materiality of the contract (legal sovereignty). Ultimately an air-shaft device for excavating under increased atmospheric pressure would be designed taking in mind both technical and political difficulties. Today the 3000-million-gallon reservoir, first imagined in the late nineteenth century, continues to be a major water source for the city of Belfast. However, this article will focus on a very specific moment of this water history in the arbitration chamber, a sort of micro water history of three days.Footnote 4

Because of the sub-soil, the design was said to be unfit for purpose—which made the Water Commissioners responsible for solving the problem, because they were responsible for errors of design according to a particular reading of the contract. This particular arrangement of the facts enabled the contractors to force renegotiation of the legal and financial provisions. Although they wanted to find a solution to the excavation difficulties they did not want to pay out of their own pockets. The contractors’ legal team, represented in the arbitration hearings by Sir Lynden Macassey, tried to connect a dispute at the level of nature to an arrangement of forces in the legal and political arena without directly challenging the sovereign interests of the Northern Ireland or their delegates the Water Commissioners. Before turning directly to the legal dialogue, I review some of the issues at stake and provide scholarly background.

History, technology and sovereignty

Certain moments in history are worth telling closely because they seem to illustrate contingency, that is, that perhaps the story could have gone very differently. It is for this reason I tell what ultimately is a water history through a very particular lens, the contract dispute which seems to be one of its most contingent moments. For the historian exploring how the design of technological objects relate to the social and political circumstances of their design (and vice versa), this example provides a plausible opportunity to investigate what, if any, relations exists between state and technology.Footnote 5 Does the boundary dispute (a struggle establishing local state sovereignty over a specific territorial region) influence the design/construction of technological objects (for example the reservoir, the air-shaft device, or other technical processes related to reservoir construction)? Did reservoir construction within the disputed territory influence that dispute? In this article I will demonstrate a relationship between science and sovereignty, albeit a necessarily contingent one. Science and sovereignty normally operate on very different social scales: states are measured in territory and laboratories in square footage. Laboratories are always in process. Sovereignty is normally fully established. Because of the relative size and importance of this water project to the fledgling state, and the formative and in-question character of the sovereignty at this early moment in Northern Ireland’s history, a plausible argument about the connection between these two differing elements of micro and macro social scale can be shown.Footnote 6 It is because a fledgling state encountered a world-class engineering problem in a project directly related to its sovereign interests that the Silent Valley reservoir contract litigation is salient for water history.

Perhaps because it is located between governance and engineering, water history has more recently become an increasingly important topic in social histories of technology in the past decade. Both the editorial of a special issue of Technology and Culture dedicated to water (2008), and the launch editorial of the new international journal Water History (2009) comment on this.Footnote 7 John Broich, one example among many, writes the nineteenth century history of water in London linking municipal and parliamentary politics in arguments over who should update and control the water supply.Footnote 8 The public works project links engineer and technical details of organizing some aspect of environment to the greater realm of culture and politics through the means of public funding (and all the public dialogue, common purpose debates, and political negotiations necessary to authorize such funding).

Early historical material on dams and reservoirs tended to focus either on the development of reservoir design (often written by engineers) or on the bureaucratic politics of water authority institutions.Footnote 9 One historian in the latter category emphasized “…the relation of hydraulic construction to social and economic necessities and to military conquest” in the great ancient civilizations.Footnote 10 Even if political historians of empire have largely neglected the role of technologies or seen them merely as tools for empire, historians of technology who emphasize the mutually inter-determining role of culture and technology have shown that empires require and develop particular technologies (some of which are water technologies) and that, in turn, particular technologies enable and shape empires.Footnote 11 An object that functions by holding shape continuity as it moves from one spatial region to another (for example, the hull of a sailing ship that moves from Portugal to India), has been described as an immutable mobile.Footnote 12 This is also to say that its components exist in a fixed actor-networkFootnote 13 of relations to one another. The use of immutable mobiles has had great significance for the expansion of European culture, colonialism and scientific influence. The actor-network theorist attempts to show how the device used to resolve a social-political-technical problem (for example, the air-shaft deviceFootnote 14) is shaped by political-social concerns. This shaping allows the device in subsequent performances or different places to reiterate its social or political function. When taking up this research this was initially the conceptual framework that I sought to employ.Footnote 15 Because our linguistic conventions divide the ‘social’ from the ‘technical’ this can be difficult to reveal when latent function emerges in conjunction with a social convention.Footnote 16 By closely examining the circumstances of the legal dispute, I describe how the performance of an instance of legal convention enables the device which ultimately solves the problem.Footnote 17 While linking law and engineering disputes is hardly new, I further trace the science within engineering to the sovereignty within law to build a more suggestive description of the contingent relationship between state (sovereignty) and technology (water reservoir).

Law is one of the key institutions of the state, both procedurally and as a legitimating factor. Because the sovereign power is said to establish the law, even mundane procedures of law can be said to be grounded in state sovereignty. While much of coming to a decision can be procedural, i.e., governed by law, there will also arise circumstances where a certain amount of judgement must be applied. The procedural sovereignty of law can be interrogated for the influence of actors and circumstance. The archival method I use closely looks at the socio-legal performance of the law. By reading the different parties accounts against one another I provide for a very close reading of the circumstances and particular occasion of dispute.Footnote 18 As this methodology demonstrates, the archival record of legal conflict is a location in which a more nuanced account of the everyday engineering challenges becomes worthy of preservation in the historical record.

The term ‘sovereignty’, which is more common in political science or socio-legal studies, I bring into water and technology history.Footnote 19 Political theorist Mark Neocleous notes the term transitioned from court rule in the name of a monarch into more recent governing systems.Footnote 20 Sovereignty is the power of interlocking institutions or a system of governance to come to a decision and assert itself in the name of the ‘state’. Max Weber, following earlier writers such as Leo Tolstoy, grounds the power of the state in violence: the state is a “human community that … claims the monopoly of physical force within a given territory.”Footnote 21 Thus territory and potential for violence can be associated with state sovereignty. Theories of sovereignty vary considerably. For Karl Schmitt sovereignty lies with he who decides the exception within the law (for example, use of extra-constitutional violence by the state) which maintains and reproduces the legal system across points when formal procedures and the requirements of reality seem (to Schmitt at least) to conflict.Footnote 22 For political theorist Giorgio Agamben, describing the biopolitics of the early twentieth century, the ‘exception’ which the sovereign arbitrates is the exclusion or ban of some types of life from political consideration. Agamben sees this as happening when the factual level of life is given over to political power (by the sovereign exception). Says Agamben, “The fundamental activity of sovereign power is the production of bare life as originary political element and as threshold of articulation between nature and culture.”Footnote 23 His work can be used to think about how political sovereignty is relevant to this case study. When political theorists such as Agamben and Neocleous define sovereignty in its ability to ban or exclude, we can make a significant link between sovereignty and the world-establishing experimental method for determining facts about nature, for distinguishing subjective opinions from objective knowledge. Scientific judgement, in a specific situation, bans alternative interpretations. In the seventeenth century Robert Boyle provided legitimacy for the newly created experimental science method by emulating the legal conventions of witnessing treason against the sovereign.Footnote 24 The laws of science were explicitly modelled on the laws of the sovereign.

To operationalise this conceptual framework I specifically discuss three levels of sovereignty: (1) state sovereignty, (2) the procedural sovereignty of law (contract arbitration process), and what I will call (3) scientific sovereignty or expertise which occurs when an engineer/arbitrator is asked to pass judgement on the nature of an unknown material. In order to describe the relation between these three, I use a simple operational definition of sovereignty: the term is intended to mean the ability to make a decision, particularly over some question of common dispute. The empirical details available in the civil engineering legal record are a place to look for links between the ability to make decisions in an engineering dispute and the ability of that much larger sociological unit, the state, to come to a decision (sovereignty).

It is suggestive that the term ‘civil engineering’ was only taken up first in the eighteenth century, previous to which the very same tasks were done by military engineers.Footnote 25 The ironic origin of the ‘civil’ within the martial powers of sovereigns and city-states suggests the interconnection not just of nature and civil engineering, but also of political sovereignty. State action to improve nature (the building of roads, the drainage of bogs, moral improvements to the nature of the citizenry such as through the building of schools or hospitals) have extended the political reach of the state.Footnote 26

Previous work on sovereignty in recent water history has naturally focused on state sovereignty in an international legal context. Tvedt, McIntyre and Woldetsadik, in their editors’ article introducing History of Water, Series III, Volume 2: Sovereignty and International Water Law, point out the Westphalian Treaty (the mythical origin of the state form of social organisation) gave explicit reference to cooperation in common interest over the Rhine River which flowed through the numerous principalities in question. They suggest it is.

the particular ‘rules of the games’ in the particular river basin that should be properly analysed in order to avoid conflict and promote further cooperation. Resolution of water conflict is, therefore, essentially a negotiation of particular linkages, of which the particular geographical and hydrological linkages are but two.Footnote 27

Knowledge practices do not explicitly form a part of their argument. Verhoven’s study of Islamic state power imagined through dam construction does a little to connect sovereignty to science by tracing a mentality historically back to Napoleon’s ‘savants’ who articulated a grand vision for Egyptian agriculture (resulting in the British constructed Aswan Dam), which Sudan hoped to emulate.Footnote 28 Gilmartin’s account of the India Pakistan river basin debate shows the social forces in play and documents Pakistan’s hasty reorganisation of water policy after the river diversion to protect their state interest in distributing better what water they had left. They turn to hydrology to reconstruct their capabilities.Footnote 29 Many recent water histories have included a more nuanced account of the social role of science in hydro-engineering projects. In addition to its traditional instrumental value in designing projects, these histories document some failures of science, particularly grand vision colonial science, in achieving expected results, or maintaining those results over the longer environmental and cultural time period. Science creates ‘normal water’, ‘modern water’ and ‘water as a neutral entity’.Footnote 30 In environmental histories the technocratic failure to acknowledge the co-production of society and environment engenders the prescription (no doubt wise) to swap a political economy analysis for a political ecology. Soll’s Empire of Water explicitly documents the favourable impact of testimony by New York City’s chief water engineer in influencing the Supreme Court’s decision in the 1931 Delaware River case without more than comment.Footnote 31 While recent water history takes up the role of knowledge production, linking this to sovereignty is usually not considered, either by omission, by being legitimately outside the author’s argument, or by being, as this article shows, not easily demonstrated without close attention to detail.

My attention to the articulation of sovereignty by local actors within their local engineering contexts is consistent with the approach advocated by Lauren Benton. Instead of thinking of sovereignty solely in terms of cartographic imaginaries and territorial control, the technology historian in the legal archive might remember that “sovereignty in empire formed as multiple agents positioned themselves to act as subjects of and proxies for imperial powers, and as polities and populations negotiated scope for their own autonomy, sometimes urging radical reconfiguration of rule.”Footnote 32

Before turning directly to the legal dialogue, I review the origins of the reservoir and place it within the context of the Irish dispute.

Reservoir design, early construction, and the Irish boundary dispute

In 1891 Luke Macassey, chief engineer for the Belfast Water Commissioners (with a then young engineer Frederick W. McCullough as his assistant) selected and surveyed a catchment valley in the Mourne Mountains, County Down. He gave the valley its name for parliamentary legislation,Footnote 33 designed the reservoir and diversion scheme, and then supervised construction of the initial portion: diversion of the Kilkeel and Annalong Rivers to supply the industrial city of Belfast.

After 1908 when the senior Macassey had passed away, McCullough took the role of chief engineer and began plans for the next stage of the Mourne water scheme, the reservoir, resurveying the valley and drawing up detailed design plans to put out to tender.Footnote 34 The Great War, Irish political instability, and then the high cost of construction immediately after the war delayed construction. Eventually a contractor was selected. Construction began shortly after that in 1923.

The roots of Irish partition began in the 19th Century with agitation for home Rule in Ireland which was at that time governed by the British Parliament. In 1885 parliamentarians elected from Ireland to the British House of Commons suddenly held the balance of power between the liberals and the conservatives, neither one of which had an overall majority. They convinced the liberals to introduce a home rule bill, by which Ireland, within the British Empire, would govern itself. The bill was defeated and more narrowly stopped again in 1892. Within the northern province of Ireland, Ulster, the political dynamics began to change as Belfast liberals and conservatives joined together as unionists opposing nationalism for Ireland and gradually shifting to accept a partition strategy if home rule was inevitable.

The possibility of a third home rule bill brought about huge resistance in 1912 when 500,000 Ulster unionists signed the Ulster Covenant pledging to defy any Irish government. 25,000 rifles were secured, and British army officers threatened to resign rather than deploy against the Ulster Volunteers. An amendment to the bill excluding Ulster was being debated when the First World War broke out in August 1914. In 1916 the Easter Rising in Dublin was crushed by the British but succeeded politically. Except in Ulster, the Irish elections of 1918 validated the party of nationalists seeking a united Ireland outside the British Empire. They proceeded to set up an independent parliament, the Dáil Éireann, thus setting off the Anglo-Irish war. The British Government presented a home rule bill creating two separate devolved governments, the northern one consisting of six counties within which the Ulster unionists could expect an electoral majority. They would promptly vote to re-join the union. This partition formed the substance of the Anglo-Irish peace treaty negotiated by British Prime Minister David Lloyd-George.

Thus between initial conception and reservoir initiation, the partition of Ireland brought about by war had changed the arrangements of governance. There were now two separate states. The Boundary Commission was a requirement from negotiations ending the Anglo-Irish War. It threatened the political composition and even the existence of the Northern Ireland because it challenged the six-county boundary within which unionists could expect majoritarian control of government and economic viability. Very early the reservoir site became enrolled in the highly politicized boundary dispute.

The Irish question had been particularly difficult for British politicians because it divided the post-war coalition (between the Liberals and the Conservatives) put together by Lloyd-George (leader of the Liberal party) because conservatives supported the Ulster unionist population, whereas liberals were less willing to do so. Lloyd-George sought to hold his coalition together long enough to get past the Irish question. To move negotiations past impasse he suggested a boundary commission which the Irish were given intimations might severely delimit the northern six county government boundary and possibly encourage them to become part of the southern Irish state for reasons of truncated economic viability.Footnote 35 For this clause Lloyd-George was able to limit Irish autonomy to dominion status (allegiance to the crown and some financial ties) within the British empire and push the difficulty of Irish disagreement into the future. When the question resurfaced Lloyd-George’s coalition collapsed and there was a succession of two conservative governments and then the first Labour government.Footnote 36

By 1924, the Irish were demanding this boundary commission while Ulster unionists refused to appoint their member to the three-person commission. The Ulster unionists hoped to ignore or delay the boundary issue until a new English election once again brought about a more supportive conservative government. Inheriting the Irish question, the new Prime Minister, Labour leader Ramsey MacDonald, intended to legislate that the British government would nominate a commissioner on behalf of Ulster. The Boundary Bill, on the parliamentary calendar for late September (1924), was a potential crisis for the northern government. According to the treaty the Commission would determine the boundary “in accordance with the wishes of the inhabitants, so far as may be compatible with economic and geographic conditions”.Footnote 37 Significant regions and municipalities were primarily Catholic including Newry and the Mourne Mountains where was located the catchment area for the expensive reservoir now being built. Might Ulster unionists contemplate Belfast’s water supply held (or withheld) by a foreign power that wished to coerce them into a united Ireland or demand changes in electoral or housing policies (such as those which discriminated against Catholics)?

Early in September of 1924 the Water Commissioners brought key figures in the British parliament up into the Mourne Mountains to the Silent Valley to tour the works, lobbying them in what they labelled as a “non-political” act: that any public body charged with supplying water to its citizenry would comment against the forfeiture of control over its largest water source.Footnote 38 In this they had worked carefully with Northern Ireland’s Prime Minister Sir James Craig and his newly formed government, who desired to undermine and dissolve the Boundary Commission (Fig. 2).

Fig. 2
figure 2

Source: Sep 12 1924 Telegraph

British politicians lobbied by Water Commissioners, shown here departing for the Silent Valley with the Attorney General “on footboard acting as checker.” Craig’s government coordinated with the Water Commissioners to demonstrate the planned reservoir location to British parliamentarians thought to be potentially sympathetic to the unionist cause. Here travel is by the full English gauge railway 4′8½″ built in 1923 specifically to deliver construction materials from Annalong harbour up to the Silent Valley.

The secretary of the Water Commissioners warned,

…if by any unhappy circumstance the supply from these mountains could be rendered unavailable, or in any way interfered with, there would follow consequences… disastrous to the manufacturing and shipping industries and… the community, the extent of which it is impossible to overestimate.

The Water Authority of Belfast is a strictly non-political body, and its Board of Commissioners recognize that fact and that their constituents comprise all classes of political thought.Footnote 39

The Water Commissioners and their impressive mountain scenery were being presented as the non-political centre of a fairly political sandwich. That evening the M.P.s were to be entertained at the Ulster Reform club where Craig would speak with them. The non-politicalness of the Silent Valley Reservoir was politically convenient. It gave a rationale of nonpartisan water necessity to the British legislators, some of whom were perhaps already inclined to support the Unionist cause.

Although the Conservatives could not stop the bill, they put it through Parliament with a non-binding addendum suggesting territorial change should be limited.Footnote 40 During the summer of 1925, when the new Boundary Commission was taking evidence and preparing its report, excavation began at the Silent Valley. It wasn’t long before difficulties arose because of fluid subsoil. After timber-lined sumps had subsided steel cylinders 9’ in diameter were driven into the line of excavation for the cut-off trench. The material which had both fluid and solid properties was ambiguous enough that men excavating within the cylinders had to be harnessed with a rope so that they could be pulled out should the inflowing ambiguity suddenly prove dangerous.Footnote 41 The responsibility for these difficulties became a topic of disagreement between the engineer for the Water Commissioners and the contractor. At the same time, the boundary issue hung over the Ulster unionists of Northern Ireland. In October James Craig was trying to be certain they had secured Newry,Footnote 42 while in the Silent Valley excavation had halted as the two engineers exchanged legal correspondence on whether or not changes in design were necessary.Footnote 43 By the end of October Craig had intimations that Newry would not be lost.Footnote 44 Therefore the Silent Valley (which was east of Newry) would also remain. The expected territorial transfer would probably be insubstantial.

Ultimately, the Boundary Commission’s report was leaked and then suppressed. A story in the Morning Post on November 7th outlined the extent of the boundary and heralded the success of the award for Ulster, creating an immediate political crisis for the government of Ireland. The Irish appointee to the Boundary Commission announced his belated resignation. Five days later, the contractors for the work in the Silent Valley notified the Water Commissioners that they were invoking the dispute resolution clause of the contract.Footnote 45 Perhaps the contractors now felt there was slightly more room within which to resolve the problem, but the dispute was still not made public.

The leak and subsequent suppression of the Boundary Commission report had the effect of solidifying the northern state.Footnote 46 Like ships passing each other in the night, the boundary crisis (very public) and the Silent Valley crisis (concealed), seemed to slide past each other as if without encounter.

Over the summer and autumn of 1926, the difficulties in the Silent Valley were further explored in ‘without bias’ negotiations, but no resolution was forthcoming. Eventually, it became public knowledge that the contractor and Water Commissioners were in legal dispute with a date set in early December for arbitration hearings. Like rain-heavy clouds, journalists and interested parties began to convene.

The setting of the legal dispute

The sources suggest that the specific room where the arbitration was held was full of important people. On the walls that day were an array of maps and diagrams of the engineering work at the Silent Valley, ready to illustrate the technical matters to be discussed. Mr. W. I. Quinn, secretary for the Water Commissioners, had made the arrangements. A function room in the Slieve Donard Hotel in Newcastle, County Down, had been reserved. The counsel representing Pearson & Sons was Sir Lynden Macassey, K.C. and Jim Whitaker, K.C. instructed by Horace Davey in London and Mr. Charley McDowell in Belfast. Horace Davey was the regular legal counsel for Pearsons. He had prepared most of their cases, including similar legal contests that Pearsons had been involved in, such as the Littleton reservoir dispute in 1922 with the London Metropolitan Board (discussed below). The other solicitors had been retained specifically for this dispute. Sir Lyndon Macassey was an interesting choice for counsel and perhaps not accidental. Sir Lynden Macassey would not have been unfamiliar with the history of this project. His father Luke Macassey had been the chief engineer for the Water Commissioners until 1908, before their present engineer Frederick W. McCullough, who redesigned the original scheme and set about finding contractors. But now, less than three weeks before the arbitration, McCullough had suffered a seizure while driving. At this crucial juncture, when the Water Commissioners faced litigation on complex technical and legal issues of contract and design, when they most needed their engineer, he was at his home stricken with pleurisy. By April he would be dead.Footnote 47 Despite being without their lead engineer, the Belfast City and District Water Commissioners were well represented in legal authority by none less than the Attorney-General for Northern Ireland (the Right Honourable A. B. Babbington, K.C., M.P.), Mr. E. S. Murphy, K.C., and Mr. R. D. Megaw, K.C., instructed by Mr. R. E. McLean in Belfast. Mr. McLean was the regular solicitor for the Water Commissioners retained for all their legal disputes.

The Arbitrator as specified in the contract clause on dispute resolution was Mr. William J. E. Binnie, M.Inst. C.E. of the firm Sir Alexander Binnie, Son, and Deacon, 30, Buckingham Gate, Westminster, S.W. Sir Ernest Moir, described in the Daily Mail as the engineer-in-chief to Messrs. Pearson, was at hand and prepared to do much of the presentation himself.Footnote 48 Having worked for Pearsons all over the world, Moir brought considerable experience. He was a potential conduit for lessons learned in other geographies, including his experience with politically contentious excavations under increased air pressure.Footnote 49 All these important persons and others associated with the case were present in the function room of the Slieve Donard hotel that winter morning in Newcastle when Sir Lynden Macassey rose and asked Mr. William Binnie “Are you ready, sir?” With that statement the long-awaited arbitration began. Maccassey’s argument would be like the concentric spherical layers of an onion, each opening up to the next within itself. He would emphasize common interests, then articulate the legal argument delineating responsibility for errors in design, describe the design argument related to subsoil removal by a particular method, and then provide the history of sub-soil excavation to ask whether the nature of the material would lend to excavation by the design-prescribed method. From guidance by the law he would pass over the decision-making power to the expertise of science.

Emphasizing common interests

From the start of the arbitration it was clear that Sir Lynden Macassey presenting the case on behalf of Messrs. Pearson was to be very diplomatic. The legal dispute was characterised as a common difficulty that both the Water Commissioners and Pearsons shared, that perhaps the Arbitrator could resolve. For a year the sub-soil problem had been debated with increasing difficulties. When other forms of resolution failed the contractors turned to the legal frameworks and filed a grievance to be resolved by arbitration as per the dispute resolution clause in the Contract. The Water Commissioners had been led in this conflict by their chief engineer, McCullough, now absent. So Pearsons’ legal team may not have been entirely clear to how the Commissioners would now react. The situation had the potential to go badly wrong.

Having established a basic description of the project, Sir Lynden began to describe in more detail the circumstances which had brought all parties to this arbitration. Amongst the many diagrams arrayed upon the wall, he drew attention to one for the arbitrator to see which could summarize the difficult situation.

To indicate the character of the difficulty, there confronts you, sir, on that wall is a cartoon and it shows the longitudinal section along the centre line of the embankment of the Reservoir.Footnote 50

This diagram (Fig. 3) showed the cross section of the trench. First, the expected depth of bedrock given by the Water Commissioners engineer was illustrated by a line across the trench. The additional depths estimated by recent borings and metal bars thrust into the earth were also indicated on the diagram. With these, an estimated actual line of bedrock could be shown to be very probably at a considerably greater depth than predicted by the Engineer.Footnote 51

Fig. 3
figure 3

Source: Pearson Collection

Maccassey’s ‘cartoon’ of the depth.

With this drastic summary of the situation Macassey was then able to hint at the possibility of a negotiated resolution, something that the contractors would like to bring to the dispute.

I may say this, that of course one recognises that the object of the Belfast Water Commissioners is to obtain a reservoir. That is what they desire to obtain. I may equally ask them to recognise this, that the object of Messrs. Pearsons & Son is to build a reservoir for them, if that reservoir can be built. That is their object and therefore, sir, I think I may say that there is not much discord of view between the two parties, that is to say, between the Water Commissioners who desire a reservoir and Messrs. Pearson who desire to build them a reservoir, but what I think I shall satisfy you is this, that neither of the aspirations of the two parties can possibly be satisfied under the terms of the existing contract, as we say.Footnote 52

The strategy of Pearsons’ legal team was not to place blame on the other party but to displace blame entirely. They would very much like to line up the subject position interests of both parties. Such a strategy must have developed and come to seem plausible in the face of few other options. The Contractors did not wish to shoulder the blame and be made financially responsible for the difficulties. But neither did they wish to make enemies of or undermine the Water Commissioners on whom they depended as sponsors of the project. Undermining the Water Commissioners in a public trial might result in the termination of the water scheme. Ratepayers and other political opposition to the Water Commissioners had to be considered. These other parties could destabilize the project if given opportunity within this controversy. Also, as a business S. Pearson & Son’s reputation for getting work done was important. Their reputation would enable them to pursue other business elsewhere. A difficult and vindictive legal battle resulting in no reservoir being constructed would not reflect well upon Pearsons. Macassey enacted the situation thus,

There is this very unfortunate state of circumstances. Rock is not found at anywhere near the depth at which either party contemplated it would exist. Neither party is responsible for this unfortunate happening, and I think I may lay that responsibility on Providence, but there it is. It raises a condition of things which calls for very careful and anxious consideration by both parties.Footnote 53

Here Macassey names “Providence” as the location to which blame could been displaced. “Providence” and “Nature” served as similar rhetorical tropes to displace politically damaging discussions of blame away from the two main parties involved in the reservoir construction, the Water Commissioners and the contractors. Ratepayers had opposed the expensive project and nationalists saw the Water Commissioners’ role in the boundary debate as partisan. Intermittent political violence (although now less) was still occurring in Belfast. Under these circumstances “Providence” was an important rhetorical displacement. Material in the archival records does not provide an explanation for the choice of this word. Nor do we have the specific reasoning for the strategy Sir Lynden quite evidently pursues, but we can see he is a skillful actor. We must assume he can see the situation he is placed within as representative for the contractor and seeks to navigate through this difficult social field of forces and valences associated with different interest groups, each with different levels of authority or ability to sabotage the project.Footnote 54 From this basic explanation of the circumstances and suggestive remarks about negotiation Sir Lynden switched to discussing the legal case for responsibility from the Contract.

The legal argument

Legal frameworks might be thought of as a matter of sovereignty enacted at the procedural level. This means that they resolve conflicts between several alternative (and often assumed to be conflicting) actions, arrangements, or options so as to bring about (usually by legal imposition) a common course of action on all parties. While the general actions of legal procedures are an expression of sovereignty (procedural sovereignty), the legal system as a whole is connected to the sovereignty of the state. The legal system is designed to uphold the day to day economic and social order which the state both supervises and is upheld by. State sovereignty establishes and authorizes a legal system.Footnote 55 In a case of arbitration using a legal framework we would thus expect there to be (in addition to the legal framework itself being described as sovereignty at a procedural level) an indirect connection to state sovereignty in that the rule of law is ultimately guaranteed by the state.

However, in this particular arbitration the interests of ‘state-level’ sovereignty can be seen more directly. The Attorney General’s presence as the legal spokesperson for the Water Commissioners but also the highest legal authority in the Northern Ireland, the state’s lawyer, is indicative of the attention which this matter of water is receiving from the governing agents of sovereignty. In very recent memory the Silent Valley had been highly politicized when the Commissioners had worked with Prime Minister Craig to include Belfast’s water supply in his boundary argument. Now his government was once again paying attention to water.

Sir Lynden would now explain the contract and demonstrate its relevance to his argument. While the general strategy of Pearsons was to displace blame and promote negotiation, the specific legal strategy with regard to the Contract is more directly an attempt to gain the upper hand during negotiations in order to force a settlement beneficial to Pearsons. Pearsons’ legal team intended to demonstrate authority for their position from the Contract and thus mark negotiation as the only option for the Water Commissioners. This very direct legal conflict was smoothly covered over with the diplomatic rhetoric of common interests that Sir Lynden has presented in his initial description of the situation. ‘Providence’ provided an acceptable blame regime, making invisible political critics who might provide less celestial attributions of fault. His overall strategy would be to demonstrate that legally the Commissioners were responsible for failure of design, that the design required a particular method (wooden trench) which was unsuitable because of the nature of the subsoil (fluid). The arbitrator could then be asked to make a judgement on the nature of the material. Was it or was it not dissociable from its water within the scope of wooden trench design? But first he had to establish the legal argument. This he does in a very particular way. He uses the contract as a material object in itself. The history of technology has emphasized how documents, plans, and specifications are used in construction as an object, not simply for their information content, but as part of a performative capacity in expressing and “mediating social relations”.Footnote 56

Sir Lynden’s first task is to identify for the other members of the arbitration the contract. This he does by emphasizing its unusual condition. He is particularly keen to push aside the more simple representations of the signed agreement which might at first seem to contain the relevant information.

The contract is a document which consists partly of print and partly of manuscript amendments and alterations, and I think it will be necessary for you in following my argument to have before you a copy of the exact document which was signed so that you can see the deletions of the print which are made in manuscript and the additions to the print in manuscript which were inserted. I do not know whether you have a copy of the printed contract. It looks nice clean print.

THE ARBITRATOR—Mine is clean print.

SIR LYNDEN MACASSEY—That I do not think will be sufficient for you. […] May I hand you what I understand is a facsimile copy of the original and ask you to be good enough to use that until you have an opportunity of seeing the original.Footnote 57

The contract and specification which was signed was the result of a long negotiation process. A version of the contract and specification had been printed in advance of the actual signing of the contract. In the last few days before the contract was signed considerable renegotiations happened. These renegotiations were represented with sheets of typing paper insertions and red lines crossing out those sections which were to be removed. The contract and amended specification was then signed in this state of production, rather than waiting for a printed version which removed the history of the negotiations. The contractors’ copy of the original similarly indicated the history of the negotiation. After the signing occurred, printed versions of the contract were made by the Water Commissioners. These did not show the editing marks created during negotiation but rather merely the end results. Here the material structure of the contract, specification, and associated documents plays an active role in determining what will ultimately become (or not become) a reservoir. As we will see below, the greater level of detail in the edit marked original (and the replica of the edit marked original), will allow the contractors’ legal team to assert particular connections to the past.Footnote 58

Having successfully asserted to the other participants in the arbitration that the document indicating the contract will be the original replica, Sir Lynden then began to outline the structure of the legal documents.Footnote 59 The contract included several attached documents which set out a covenant of payment in return for service. The ‘Form of Tender’ was signed and sealed by the agent of the contractor (and then additionally signed and sealed by the agent of the Water Commissioners). Attached to the form of tender was the ‘Specification’ including a schedule of quantities, written by the Water Commissioners’ engineer. After generally outlining the remit of the contract, the Specification detailed the design work that was required of the contractor. The schedule of quantities listed specific items of labour or materials to be provided and gives the prices for which the contractor had agreed to provide such. The drawings were also legally included within the contract. During the signing of the contract each of twenty odd engineering drawings were examined and initialled.

Fig. 4
figure 4

Source: Pearsons Collection

The Contract as printed ends without significance. During negotiations the proposed contract was modified with insertions and deletions. Then the document was signed with these modifications. A reproduction was then created in “clean print” without the record of deletions.

Fig. 5
figure 5

Source: Pearson Collection

The Contract as signed: Tracing paper insertions show what was removed. The ‘exception’ of this clause is included within the Contract, thus determining the legal interpretation.

Sir Lynden especially emphasized that it is the amended specification which has been agreed. The implications of this he explained thus:

So when one looks at the amended Specification … you will observe that the last clause in the amended Specification is 356 and that it is struck out. Would you be good enough to look at that because these deletions, of course, which exist in the signed document, are just as much part of the signed document as the print.Footnote 60

The contract and form of tender actually signed required the execution of the Drawings and that which is “in the amended specification.” Sir Lynden repeated this phrase to emphasize that the relevant document to be considered is the original replica with deletions and insertions (Figs. 4 and 5). It was a particular deletion at the end of the amended specification which Sir Lynden wished to emphasize. The deletion would not have been present in the printed representation of the Contract which the Water Commissioners’ legal team had provided for the arbitration process.Footnote 61

Sir Lyndon read aloud and then commented on the clause that was struck from the contract, clause 356, the warranty clause:

“The Contractor further agrees and binds himself to provide and execute all matters and things whatsoever, in addition to those shewn on the Drawings and herein-before specified, as may be necessary to make the intended Reservoir… without any payment beyond the Contract sum, and… notwithstanding any defect in the design of the Works… he shall complete and maintain and hand over the said intended Reservoir and other Works complete in every respect...”

If that clause stood it was an assumption by the Contractor of full reliability and responsibility for executing the Reservoir, notwithstanding any defect in the design of the Works. That was struck out and there are certain very significant insertions… if I may, just point you out what the insertions were.Footnote 62

Sir Lynden went on to explain the organisation of the contract giving special attention to these insertions. These insertions exist he claimed in clause 5 regarding the extent of the Contract and clause 7 regarding Drawings.Footnote 63 It is worth noting that his narrative imposes a chronological logic to the negotiation of the contract. By beginning at page 86 of the Specification, giving significance to a deletion, and then returning to page 2, clause 5 and page 3, clause 7 to claim that the insertions at these locations are in response to the deletion Sir Lynden presented the significance of the contract in a particular way. He interpreted it diachronically. With the greater level of detail in the edit marked original replica Sir Lynden could tell a historical narrative about the meaning of the contract as it emerged from the original negotiation process. Some of the influences upon the original negotiation process (discussed below) were now becoming influences upon the arbitration. As we will see, these influences were geographically diverse.

Clause 5 specified the liability of the contractor for damages caused by executing the plans incorrectly but, significantly, not such damages as caused by defects in plans which were executed correctly. Sir Lynden: “So you see that, so far as any defect in the design is concerned, there is a very material difference in the contract as drafted and the contract as signed.”Footnote 64 Clause 356 as drafted had required of the contractor responsibility for defects in the plans. With that clause now struck, Sir Lynden claimed that clause 5, saying something quite different, was instead the relevant clause for the issue of liability.

Clause 7 referred to the drawings, which were to be accepted by the contractor “as sufficient in all respects to indicate the nature extent and particulars of the intended Work… the Contractor binds himself and agrees to make no claim whatsoever against the Commissioners,” and here the words “for any payment” had been cut out. Likewise “unsuitable or insufficient design” had been struck from the list of reasons that the Contractor agreed not to make a claim.Footnote 65

The paradigmatic comparison of phrases such as “agrees to make no claim whatsoever against the Commissioners” and “agrees to make no claim whatsoever against the Commissioners for any payment” (the latter phrase being struck out and replaced by the former) enabled Sir Lynden Macassey to imbue a history of particular meanings to the words in the Contract. Clause 22 (which was to be invoked if additional work was required by reason of design error) referred to payments for extra work ordered which was not specified in the Contract. Macassey made use of clause 7 and 22 to emphasize that the Contractor was not responsible for errors in the design of the reservoir and that liability for design errors lies with the Commissioners. He summarized the legal argument thus:

You will note the difference between the print and the Contract as executed. Under the print there was… a provision which made the Contractor liable and responsible for any defects in the design of the Works; notwithstanding what any such defect might be... In the Contract as signed that clause was cut out, and in place of it you have very significant insertions… which, in my submission, relieves the Contractor from any liability or responsibility for the insufficient and unsuitable design of any portion of the intended Works...Footnote 66

This was the main portion of the argument presented by Macassey at the arbitration. If the legal Contract, as he claimed, held the Commissioners responsible for defects of design then Macassey must need also to establish that the design as provided by the Water Commissioners was unfit or unsuitable for its purpose. According to Macassey’s presentation the important issue would now be whether or not the trench could be excavated as per the method originally stipulated in the Specification.

Design and the boundaries of nature

The initial point at which the design first seems inadequate was the suggestion that a timber-lined trench (as per Specification) would enable excavation. Clause 150 in the contract specified that the trench was to be securely timbered and that in the process of concreting no timbers could be left behind. Macassey claimed that this very specific method being dictated from within the contract was unusual. More frequently engineering contracts of this period simply specified the required results and let the contractors determine methods.Footnote 67 Sir Lynden Macassey summarized the most important bit of his argument. The timber lined trench as the specified means of excavation was the salient error in the design.

Having established what the design required, he now had to demonstrate that the circumstances and the nature of the material made such a method inadequate for excavation. The arbitration had to, in the final instance, resolve a dispute about nature. Thus the procedural level of sovereignty (represented in the Arbitrator’s power to decide) was being asked to make a judgement on the boundaries of nature. As is typical in dispute resolution clauses during this period, the arbitrator was a prominent engineer. Conflicting representations of nature, prepared in the form of charts, graphs, and diagrams, were to be shown to Mr. Binnie so that he might judge which were to be considered matters of fact and how these facts should be arranged. An important question for those involved in the arbitration was ‘What is the nature of the sub-soil?’ For example, is water intrinsic to the material or can the material be dewatered? If it couldn’t then a timber-lined trench was inappropriate design for a fluid material. It was the arbitrator-as-engineer’s expertise (i.e. scientific sovereignty) which was to be the basis for judgement.

Macassey began to describe the circumstances during excavation that led to the initial concerns. The nature of the material was invoked both in the way that it could be seen to relate unusually to water and in the presence of a groundwater level below which excavation was difficult.

The curious thing about this material is that … when you proceed to pat it …—I dare say scientists will differ as to the reason but will agree as to the fact—it proceeds to become a kind of jelly, … the vibration seems to extend in cylindrical rings for a considerable distanceFootnote 68

Then followed an explanation of the investigation of the material, and attempts to drain the sub-soil by building a sump. Around about the depth of 416 feet ordnance datumFootnote 69 the water level was always encountered and the timber runners to uphold the stability of the sump excavation suffered subsidence.

when you get down to that depth the water proceeds, and as the material cannot part with its water without accompanying it you get not merely the water, but a flow of mixture consisting both of water and materialFootnote 70

The relationship of this difficult to excavate semi-fluid material to the possibility that bedrock was also considerably lower than expected was also given. The excavation of the trench from the high sides of the valley had been much easier until the rock suddenly disappeared steeply into the earth.

Macassey concluded by drawing attention to the nature of the sub-soil, which both predicates unforeseen difficulties and founds his argument. The disagreement about the nature of the sub-soil (for example, is water intrinsic to the material) were at one level a classic subject/object boundary disagreement. Knowledge of the object (including the boundaries which define the object) will be constructed within the context of a purpose to which the knowledge will be put. That purpose is based on the boundaries of the subject (who the subject is and what the subject can do) which acts upon the object (both in constructing knowledge about the object and utilizing that knowledge through further actions on the object).

At least one part of the difficulty in ascertaining the material was that the Water Commissioners and the contractors had approached it with different purposes in mind. Their subject positions had been split because of concerns about who will bear the burden of additional costs (and also carry the risk of failure should the reservoir construction fail). Thus instead of investigating with a common purpose each sought to demonstrate the properties of the material which most supported their own best position in relation to the contract. For example, the Water Commissioners felt it was important to determine if the difficulty in de-watering the line of the trench was because the contractors had not sufficiently diverted the Kilkeel River from the works and thus the groundwater level was continually being replenished.Footnote 71 That would not have been an error in design. During the year leading up to the Arbitration a great deal of discussion, gradually hardening into debate and then legal conflict, occurred about the nature of the problem, such that the room was now filled with charts, graphs and diagrams full of evidence prepared to assemble and support one arrangement of facts against another. Until the dispute between them was negotiated they would approach the question of the nature of the material from different subject positions.

At this point the case for the Contractor had been stated quite strongly and the session adjourned for lunch. The participants all had much to consider as they went for their meal. By placing the nature of the material at the focal point in the summary of his presentation Macassey makes the fluid nature of the sub-soil the foundation of his argument. From nature came the fluid properties of the sub-soil, from which arose unforeseen difficulties. The design given in the specification was inadequate to deal with these difficulties and the legal arrangements of the contract made errors of design the responsibility of the Water Commissioners. Perhaps, suggested Macassey very quietly inside the minds of the Water Commissioners and the Attorney General, perhaps it was time to negotiate.

From arbitration to negotiation

The informality of lunch allowed conversations to happen which were not as easily pursued in the formal legal setting of the arbitration room. When the session resumed after lunch the Arbitrator intervened to ask if some of the morning’s argument was contested by the Commissioners. The Attorney-General rose to answer this. While gracefully noting minor quibbles, he said that substantially there was not disagreement on these points and that during lunch he had had the opportunity to discuss with Sir Lynden.

…it would be very much better if there were no break as between Messrs. Pearson and the Water Commissioners, and the Water Commissioners themselves recognise that… if we could have a discussion… having regard to the way in which Sir Lynden Macassey has stated the case for Messrs. Pearson, and the attitude they have taken up… we might be able to get rid of the difficulties...Footnote 72

The arbitration was suspended until the following morning at 10 a.m. so that the two parties might negotiate a solution themselves outside of the legal hearing. By achieving a strong position within the procedural level of sovereignty, Sir Lynden was able to push for negotiation. Successful negotiation would help unite subject positions of the Water Commissioners and the contractors, thus enabling knowledge (the arrangement of facts for a particular purpose) to be constructed in the context of common purpose. The nature of the sub-soil could be investigated without diverging intentions. This common subject position at the level of questions of nature is emulated by the construction of commonality at the level of questions of sovereignty. In order to make space for the Water Commissioners and the contractors to have a common purpose (building a reservoir) Sir Lynden picked ‘Providence’ as the reason for difficulties. In this way blame would be drawn away from the Water Commissioners and their political authority (connected to sovereignty) would not be challenged. The identity of the subject position is influenced by opposition to some other. Both the Water Commissioners and the contractors could unite in their opposition to those who would prefer them both to fail. In this case the other was said to be nature or Providence.Footnote 73 However in actuality the blame which was being avoided came from opponents of the Mourne Extension Scheme. Thus implicitly they were another ‘other’ which the Water Commissioners and the contractors both shared. Opponents of the Water Commissioners such as the well-to-do Rate Payers Association and those nationalists who followed the critical position of the Irish News were a source of common opposition which helped align the Commissioners and the contractors to a common subject position.

The following morning comments were brief. Progress was being made but the negotiations were not yet complete so the arbitration hearings were suspended one further day until Wednesday. The Belfast newspapers all covered the arbitration hearings. Even the Daily Mail from London sent a reporter to cover the case. However the press was not admitted into the proceedings. Instead, they were informed by a public statement made at 5.30 in the evening. The Daily Mail article described slightly more details for a London audience. Sir Ernest Moir was described as the engineer-in-chief to Messrs. Pearson. Their article for the second day ended poetically with a description of the weather which had blanketed the negotiations, “snow fell throughout the forenoon. Slieve Donard a white mantle.”Footnote 74 One letter in the Irish News on that day decried the policy of secrecy “in the Silent Valley.” The text of the first morning of the arbitration was never released to the press.

The Wednesday morning December 15th, the participants of the arbitration reconvened with a negotiated solution and presented it to the Arbitrator, Mr. Binnie, who published his award a week later. Although the resolution of conflict clause in the contract laid out binding arbitration, the written award of the arbitrator was drawn from the results of the negotiations between the two parties to the dispute, Pearsons and the Water Commissioners. Mr. Binnie’s award stated that Contract A was to be rescinded as of December 15th 1926. This was by mutual agreement. The Water Commissioners were to pay the Contractors all costs of construction accrued to date. In addition they would pay 10% extra for profit and 2½% extra towards the administrative costs of the Contractors’ Londonoffice. Exploratory work would continue at the Silent Valleyfor an 18 month period in order to determine the feasibility of completing the reservoir. This exploratory work would be done by Pearsons. The remuneration was to be on the same cost plus percentage basis. In the absence of F.W. McCullough, the Water Commissioners engineer, the exploratory work would be directed by a Board of Engineers. Mr. Binnie, the arbitrator would act as Chairman of the Board of Engineers. Two other engineers were to be nominated, one by the Water Commissioners, and one by Pearsons. Respectively they nominated Mr. Edward Sandeman and Mr. Prescott Hill, M. Inst. C.E. Actions of the Board of Engineers would be by majority decision. Remuneration of these engineers was to be paid by the Commissioners, and negotiated accordingly, or failing agreement between the engineers and the Water Commissioners, to be negotiated by Sir Lynden Macassey and the Attorney General, the barristers for each party. At the end of the 18 month exploratory period, the Board of Engineers would make a recommendation regarding the feasibility of constructing a reservoir on the present line and, if necessary, they would prepare plans for doing so. If the Commissioners decided to go forward with the reservoir construction, the contractors, Pearsons, would be prepared to construct the reservoir on the same basis of remuneration under the direction of the Board of Engineers. The fees and costs of the hearing were to be borne by the contractor as specified in the arbitration clause of the original Contract A. “I have taxed or settled my fees and the costs of this Award at the sum of Four Hundred Pounds,”Footnote 75 concluded William Binnie.

On the final day the press announced agreement, rock had not been found at 75 feet, nor at 150 feet, and presently at 218 feet of depth they were into running sand, claimed one newspaper.Footnote 76 Remarks by Macassey that Pearsons were “surrendering a lucrative contract,” made it into print.Footnote 77 It was also noted that those negotiating were following a precedent set by the Metropolitan water authority.Footnote 78 In the Irish News a correspondent claimed.

A gigantic blunder has been made… Belfast will sink into the Silent Valley financially bankrupted… hastening towards civic ruin… one of the great arguments against any interference with the boundary of the County Down used by the Government while the ‘Border’ humbug lived was the horrible danger of giving the Free State control over the invaluable Silent Valley. We may yet live to regret the Free State’s failure to secure itFootnote 79

The actual content of the negotiation was never made public. Much of it was probably never written down. Most of the outcome of that negotiation (certainly the legal arrangements) is apparent in the agreement published as the Arbitrator's Award a week later. All the negotiation of substance happened on the Monday and Tuesday (if not before) and the final day of the arbitration proceedings seems likely to have been choreographed. The conclusion to the arbitration gave both Water Commissioners and the contractors the appearance of having designed a well-made and mutually agreeable solution to a difficult problem. This would protect the project from potential critics in the city of Belfastwho might make the situation even more difficult if given any opportunity. Neither the Water Commissioners nor the contractors wanted it to look like the contractors had got the best of the Commissioners.

The arbitration of nature

In order to understand the relationship of sovereignty to a judgement at the level of fluid material, let us consider again the two things that Sir Lynden had to accomplish.

  1. 1.

    In terms of ‘nature’, the contractors hoped to find a solution to the excavation difficulties without being forced to pay for it out of their own pockets; whereas

  2. 2.

    In terms of ‘political authority’, the contractors were ambivalent about confronting the Attorney General of Northern Ireland or the Water Commissioners whom he represented.

The presence of the Attorney General indicated a sovereign interest in the outcome. The controversial and expensive project had opposition and was thus subject to possible cancellation in the event of prolonged dispute, a situation which neither the Water Commissioners nor the contractors desired. Pearsons depended on the authority of Water Commissioners for the construction contract. A victorious legal battle resulting in an un-built reservoir would not benefit the contractors. To avoid such a Pyrrhic victory, the contractors’ legal team needed to carefully connect a dispute about the nature of a material to an arrangement of forces in the political and legal arena without directly challenging the sovereign interests of the northern state or its Water Commissioners. On its turn, the northern government sought success for the reservoir project as failure could potentially re-open debates on the authority of their own governing institutions—mainly the Water Commissioners, but possibly much more. The Northern Government had used the reservoir to argue for the territorial integrity of their region of the Ulster province, a boundary to maintain Unionist political majority and economic power. Additionally, putting a major source of the capital city’s water supply under the territorial control of a potentially hostile neighbour would have left Craig’s government vulnerable to demands from the ‘Free State.’Footnote 80 It is unclear whether cancellation could have reopened the boundary dispute or in so doing enabled a new vulnerability which made Northern Ireland unviable. It seems unlikely based on the delayed timing enabling the two crises to slide past each other.Footnote 81 But unionists surely did not want to test this.

Ultimately the resolution enacted happens at several levels. Without being seen to challenge the authority of the northern state or the reputation of the Water Commissioners, the contractors needed to resolve a dispute about nature and this first required the resolution of subject-object promiscuity at the ontological level.Footnote 82 Sir Lynden’s argument, on behalf of the contractors, established dominance at the procedural level of sovereignty suggesting resolution of the dispute at the level of nature (where a water-subsoil ‘object’ was said to not be dissociable, at least under certain design conditions) should be explored through negotiation. The arbitrator enacted his sovereignty in the form of an award mutually agreed during negotiations. At the level of nature there was merely an agreement to “investigate” for 18 months, but crucially the subject positions of the two parties had been united in order that knowledge would be grounded in one purpose rather than two opposing purposes. The threat to the authority of the Water Commissioners was protected by the political cover story of ‘Providence’ or nature. This resolution enacted a particular distribution of sovereignty. The interests of the newly formed state of Northern Ireland were protected and an alignment of engineering expertise from the metropolitan centre of the British jurisdiction affirmed.Footnote 83 Every localized performance of state sovereignty may also provide an arrangement of local actors, their interests, and affirmation of their authority. In this case science was relevant to that distribution.

Political histories rarely link legal sovereignty to scientific knowledge and infrastructure technologies. However, in principle science (‘laws of nature’) and law (‘laws of the land’) are consonant. The cultural practice of expertise (what I am here calling ‘scientific sovereignty’) is closely linked to the experimental method, developed by Robert Boyle during the seventeenth century. Perhaps one reason for the acceptance of Boyle’s controversial new experimental method was that he explicitly modelled it upon the legal practices used by political authorities. Witnesses were more credible if they were aristocratic, male, and close to the establishment. Those who did not own property were not considered independent and thus could not have an independent or ‘modest’ opinion. Boyle adopted the legal standards for witnessing from Clarendon’s 1661 Treason Act, thus directly tying the power to speak for the nonhuman objects of nature to practices of upholding the sovereignty of the Crown during the English Civil War.Footnote 84 Political theorists such as Giorgio Agamben and Mark Neocleous define sovereignty in its ability to ban or exclude.Footnote 85 As such, state sovereignty and the world-establishing experimental method for determining facts about nature—distinguishing (or banning) subjective opinions from objective knowledge—can be connected. While there is a wide history and sociology of technology literature on the use of expertise, including the use of expertise in courtrooms, it is the approximate line-up of questions of expertise with questions of vital state interest that warrants within this study the additional characterization of a particular role or type of expertise which I designate ‘scientific sovereignty’. As a water history, the Silent Valley Reservoir dispute is salient in that a small fledgling state (its sovereignty in question) encountered a state-of-the-art engineering problem in a project aligned to its sovereign interests. Any relation between science and state (each normally appraised at two quite distinct social scales) is in most cases less discernible, more pedestrian.

In summary, the contractors’ legal team put the nature of the sub-soil at the foundation of their argument. According to a particular reading of the contract, the Water Commissioners were responsible for errors of design. Because of the sub-soil, the design was said to be unfit for purpose. At the procedural level of sovereignty, Sir Lynden did not have to conclusively resolve the nature of the sub-soil. The nature of the sub-soil (as understood in court) merely had to be delimited to a range of values where it seemed a timber trench would not be practical for excavation. This delimitation was determined by information conflict with charts, diagrams and graphs. To some extent, the material itself as an unpredictable substance lent credibility to the interpretation. The particular arrangement of the facts at this point enabled the contractors to claim their argument and force renegotiation of the legal and financial arrangements for constructing the reservoir. By displacing blame from both themselves and the Water Commissioners onto ‘Providence’, the contractors achieved the resources and time to pursue a technical solution to the reservoir problem, exploring the role of excavation under increased air-pressure (Fig. 6) until, ultimately, the cut-off trench (braced with iron-cladding) was excavated to bedrock and the first concrete poured in December 1929.Footnote 86 Very little information was provided to the public until this point about the embarrassing and uncertain project. But during the final period of completion the site became a symbol of science and good governance with public tours arranged for many local groups and civic officials, including the entire membership of the British Waterworks Association when Belfast took over the presidency of this organisation in 1931.Footnote 87 The inauguration ceremony in May 1932 had 800 invited guests (Fig. 7). Today the 3000-million-gallon reservoir continues to be a major water source for the city of Belfast. Legal dispute procedures about engineering infrastructure were linked to both the macro-scale governance concerns of the local state (including its territorial sovereignty) and the quite micro-concern about a decision on the nature of a material (scientific sovereignty).

Fig. 6
figure 6

Source: McIldowie, p10

Plan of the Air-shaft device. The fluid materiality of the subsoil was addressed by compressed air technology. The device was able to be developed only after resolution of the contract dispute.

Fig. 7
figure 7

Source: Pearson Archive

Innauguration of the Reservoir. May 24, 1932. The hymn “O God, our help in ages past” was accompanied by the Regimental Band of H.M. 1st Battalion the Border regiment, followed by prayers and readings from the Old and New Testaments by a variety of protestant religious leaders. Perhaps fortuitously for a ceremony held in a catchment valley, umbrellas indicate rain from the heavens.

Discussion

I have argued at the beginning of this article that certain seemingly contingent moments warrant close examination because, it does indeed seem, the story could have gone differently, perhaps very differently. Since we only ever have one instance of any event, it will always be impossible for the historian to prove empirically that this is so. Thus the action is always to document what did happen as best as possible—as I have done in the above.

I suggest the sovereign might be recognized by the historian not as pre-existing and determining, but as contingent, emergent from a historical process separating subject from object. The subject-object-sovereign triad is historical, contingent. However, over time it may develop some amount of path dependency. When a particular group of subjects achieve dominance in decision-making, they may be able to organize objects in such a way as to reinforce their subject position. At the most subtle level, this can be how knowledge is constructed about the nature of materials. It’s worth noting that the sub-soil ultimately was dewatered, so the soil–water ‘object’ to which Sir Lynden momentarily lends his credibility became the two separate objects of knowledge, soil and water, which the Water Commissioners wanted them to be. Here I sympathise with the perhaps common-sense approach of a contemporary engineer that of course, water and soil are dissociable(!), and the (perhaps accurate?) suspicion that Sir Lynden lingers on ambiguity for performative reasons of legal strategy.Footnote 88 But power relations in the court case opened up a temporary space of ambiguity long enough for the dominant parties to align their subject interests (partly in relation to sovereignty and partly as a localized construction of sovereignty) so as to agree upon what the object/objects were, i.e. dissociable/indissociable, both in the circumstances of design by timber-line trench and of design by cost plus percentage (within an iron-lined trench and excavated under air-pressure). Using only common-sense in an uncommon situation can be expensive.

I proposed a water history through the particular nuances of a contract arbitration.Footnote 89 It is precisely because engineering practice and scientific knowledge become standardized that they are so easily written out of political histories. We can write them back in by telling histories of how these knowledge practices became standardized. Sometimes these practices have become physically standardized as material objects, instruments, or technologies with interchangeable standardized parts.Footnote 90 And sometimes these practices have become socially standardized in conventions of use or dispute resolution, for example, contract. Socio-legal scholar Mark Suchman has extended a materiality-of-the-document approach to legal contracts by emphasizing “(1) the microdynamics of why and how transacting parties craft individual contract devices, and (2) the macrodynamics of why and how larger social systems generate and sustain distinctive contract regimes.”Footnote 91

We can also write them back in by finding curious moments in the breakdown of routine structure where the fabric of social relations struggling to put itself back together can be seen. It is often these moments which seem most contingent because skilled (or unskilled) social actors must navigate some absence of technical and social convention. The unique coincidence of a water engineering crisis temporally contingent to the recent and still formulating partition of Ireland is one such moment within which the torn fabric of social relations can be seen being reconstituted within a legal, engineering, and scientific dispute. In this moment, by following the legal, scientific, and political positioning of social actors, the usually invisible connection of science and sovereignty becomes discernible to the historian in the performative allocation of engineering judgement within legal judgement, when engineer-arbitrator is asked to decide the fate of the nature of a material.

Archival sources

Pearsons Collection, The Science Museum Library and Archives at Wroughton.

Water Commissioners’ Papers, WAT/1, Public Record Office of Northern Ireland (PRONI), Titanic Boulevard, Belfast.

Note on periodicals—Irish News, Belfast Telegraph, Ulster News-letter, Northern Whig, Daily Mail: Newspapers were accessed through ‘Newspaper Clippings’ located in the WAT/1 archive at the Public Record Office of Northern Ireland. The following records contained newspapers from the following dates:

WAT/1/3F/3/5 1916–1926

WAT/1/3F/3/6 1927–1929

Although not paginated, these books are organized chronologically, thus date and name of the newspaper (when given) serves to locate references.