Abstract
The main purpose of a planned construction project is the completion of targeted productions under specified constraints. For this purpose, a wide variety of organizations take place inside and outside of the construction site. Depending on the diversity and complexity of the organizations, the quality and efficiency of the work are directly affected. Achieving the goals of the construction site under various constraints gives workflow and planning prominence. With good planning, the workflow can be provided and the quality of the organizations within the construction site increases depending on this workflow, because efficient planning starts with the installation of the construction site. Mobilization, which means construction site installation, is critical for an efficient construction site. The mobilization plan, which is prepared for taking the construction site and all other criteria into account, is regarded as the first step for a planned construction site. Computer-aided systems are used in many fields with developments in recent years. GIS (Geographical Information Systems) has the potential to generate new information from location data. In this study, a decision support system has been developed utilizing GIS for mobilization, which is critical for construction site efficiency. In this regard, the “Weighted Overlay” plug-in within the ArcGIS software, which is one of the GIS tools, has been used as an auxiliary tool in the site selection of temporary facilities which will be set up in mobilization, as well. In the final stage, a mobilization plan was prepared for a construction site selected for the case study.
Similar content being viewed by others
References
Al Hawarneh A, Bendak S, Ghanim F (2020) Construction site layout planning problem: past, present, and future. Expert Syst Appl 168:114247. https://doi.org/10.1016/j.eswa.2020.114247
Anumba C, Bishop G (1997) Importance of safety considerations in site layout and organization. Can J Civ Eng 24(2):229–236
Bansal VK (2020) Use of GIS to consider spatial aspects in the construction planning process. Int J Constr Manag 20(3):207–222. https://doi.org/10.1080/15623599.2018.1484845
Baradan S, Akboga O, Cetinkaya U, Usmen MA (2016) Ege Bölgesindeki İnşaat İş Kazalarının Sıklık ve Çapraz Tablolama Analizleri [Frequency and Cross Tabulation Analysis of Construction Accidents in the Aegean Region]. IMO Technical Journal 27(1):7345–7370
Benjaoran V, Peansupap V (2020) Grid-based construction site layout planning with particle swarm optimisation and travel path distance. Constr Manag Econ 38(8):673–688. https://doi.org/10.1080/01446193.2019.1600708
Cheng MY, Yang SC (2001) GIS-based cost estimates integrating with material layout planning. J Constr Eng Manag 127(4):291–299. https://doi.org/10.1061/(ASCE)0733-9364(2001)127:4(291)
Evren R, Ulengin F (1992) Yönetimde çok amaçlı karar verme [Multi-purpose decision making in management]. Istanbul Technical University
Han, Z. H., Wang, Z. K., Gao, C., Wang, M. X., & Li, S. T. (2020, June). Application of GIS and BIM integration technology in construction management. In IOP Conference Series: Earth and Environmental Science (Vol. 526, no. 1, p. 012161). IOP Publishing. https://doi.org/10.1088/1755-1315/526/1/012161
Malczewski J (1999) GIS and multicriteria decision analysis. John Wiley & Sons
Mungen, U. (2003). İş Güvenliği Kurs Notları [Job Security Course Notes]. Chamber of Civil Engineers
Ning X, Lam KC, Lam MCK (2010) Dynamic construction site layout planning using max-min ant system. Autom Constr 19(1):55–65. https://doi.org/10.1016/j.autcon.2009.09.002
Ozturk, D., Batuk, F. (2007). Criterion weighting in multicriteria decision making. Journal of Engineering and Natural Sciences
Poku SE, Arditi D (2006) Construction scheduling and progress control using geographical information systems. J Comput Civ Eng 20(5):351–360. https://doi.org/10.1061/(ASCE)0887-3801(2006)20:5(351)
Sebt, M. H., Parvaresh, K. E., Delavar, M.R. (2008). Potential application of GIS to layout of construction temporary facilities
Acknowledgements
The paper is preparedusing the data of master thesis titled “Optimum site layout planning usinggeographical information systems”. The thesis prepared by Murat Atmaca issupervised by Dr. Cemil Akcay.
Author information
Authors and Affiliations
Corresponding author
Ethics declarations
Conflict of interest
The author(s) declare that they have no competing of interests.
Additional information
Responsible Editor: Biswajeet Pradhan
Rights and permissions
About this article
Cite this article
Atmaca, M., Akcay, C. Construction site layout planning using GIS overlay analysis—A case study. Arab J Geosci 14, 543 (2021). https://doi.org/10.1007/s12517-021-06793-1
Received:
Accepted:
Published:
DOI: https://doi.org/10.1007/s12517-021-06793-1