1 Introduction

Scheduling under risk and uncertainty has attracted considerable attention in the recent literature. In practical applications of scheduling models, the exact values of input parameters, such as job processing times or due dates, are often unknown in advance. Hence, a solution must be computed, before the true realization of the input data is revealed. Typically, a scenario set \(\mathcal {U}\) is a part of the input, which contains all possible realizations of the problem parameters, called scenarios. If the probability distribution in \(\mathcal {U}\) is unknown, then robust optimization framework can be applied and solution performance in a worst case is optimized. First robust scheduling problems have been discussed in Daniels and Kouvelis (1995), Kouvelis and Yu (1997) and Yu and Kouvelis (1993). Two uncertainty representations, namely discrete and interval ones, were considered. In the former, scenario set \(\mathcal {U}\) contains a finite number of distinct scenarios. In the latter, for each uncertain parameter an interval of its possible values is specified and \(\mathcal {U}\) is the Cartesian product of these intervals. In order to compute a solution, the minmax and minmax regret criteria can be applied. Minmax (regret) scheduling problems have various complexity properties, depending on the cost function and the uncertainty representation [see, e.g., Averbakh (2000), Lebedev and Averbakh (2006), Kasperski (2005), Aissi et al. (2011) and Drwal and Rischke (2016)]. For a survey of minmax (regret) scheduling problems we refer the reader to Kasperski and Zieliński (2014).

The robust scheduling models have well-known drawbacks. Minimizing the maximum cost can lead to very conservative solutions. The reason is that the probability of occurrence of the worst scenario may be very small and the information connected with the remaining scenarios is ignored while computing a solution. One method of overcoming this drawback was given in Kasperski and Zieliński (2016), where the OWA criterion, proposed in Yager (1988), was applied to compute an optimal schedule. In this approach, a set of weights is specified by the decision maker, which reflect his attitude toward a risk. The OWA operator contains the maximum, average and Hurwicz criteria as special cases. However, it does not take into account a probabilistic information, which may be available for scenario set \(\mathcal {U}\).

In the case, when a probability distribution in \(\mathcal {U}\) is known, the stochastic scheduling models are considered. The parameters of scheduling problem are then random variables with known probability distributions. Under this assumption, the expected solution performance is typically optimized [see, e.g., Möhring et al. (1999), Pinedo (2008), Skutella and Uetz (2005) and Skutella et al. (2016)]. However, this criterion assumes that the decision maker is risk neutral and leads to solutions that guarantee an optimal long-run performance. Such a solution may be questionable, for example, if it is implemented only once [see, e.g., Kouvelis and Yu (1997)]. In this case, the decision-maker attitude toward a risk should be taken into account.

In Krokhmal et al. (2002), a criterion called conditional value at risk (CVaR) was applied to a stochastic portfolio selection problem. Using this criterion, the decision maker provides a parameter \(\alpha \in [0,1)\), which reflects his attitude toward a risk. When \(\alpha =0\), then CVaR becomes the expectation. However, for greater value of \(\alpha \), more attention is paid to the worst outcomes, which fits into the robust optimization framework. The conditional value at risk is closely connected with the value at risk (VaR) criterion [see, e.g., Pflug (2000)], which is just the \(\alpha \)-quantile of a random outcome. Both risk criteria have attracted considerable attention in stochastic optimization [see, e.g., Natarajan et al. (2014), Chang et al. (2017), Nikolova (2010) and Ogryczak (2012)]. This paper is motivated by the recent papers (Sarin et al. 2014; Atakan et al. 2017), in which the following stochastic scheduling models were discussed. We are given a scheduling problem with discrete scenario set \(\mathcal {U}\). Each scenario \(\xi _i\in \mathcal {U}\) is a realization of the problem parameters (for example, processing times and due dates), which can occur with a known positive probability \(\mathrm{Pr}[\xi _i]\). The cost of a given schedule is a discrete random variable with the probability distribution induced by the probability distribution in \(\mathcal {U}\). The VaR and CVaR criteria, with a fixed level \(\alpha \), are used to compute a best solution.

In Sarin et al. (2014) and Atakan et al. (2017), solution methods, based on mixed integer programming models, were proposed to minimize VaR and CVaR in scheduling problems with the total weighted tardiness criterion. The aim of this paper is to analyze the models discussed in Sarin et al. (2014) and Atakan et al. (2017) from the complexity point of view. We will consider the class of single machine scheduling problems with basic cost functions, such as the maximum tardiness, the total flow time, the total tardiness and the number of late jobs. We will discuss also the weighted versions of these cost functions. We provide a picture of computational complexity for all these problems by proving some positive and negative complexity results. Since VaR and CVaR generalize the maximum criterion, we can use some results known from robust minmax scheduling. The complexity results for the minmax versions of single machine scheduling problems under discrete scenario set were obtained in Aissi et al. (2011), Aloulou and Croce (2008), Daniels and Kouvelis (1995) and Mastrolilli et al. (2013). In this paper, we will show that some of these results can be strengthened.

This paper is organized as follows. In Sect. 2, we recall the definitions of the VaR and CVaR criteria and show their properties, which will be used later on. In Sect. 3, the problems discussed in this paper are defined. In Sect. 4, some general relationships between the problems with various risk criteria are shown. Finally, Sects. 5 and 6 contain some new negative and positive complexity results for the considered problems. These results are summarized in the tables presented in Sect. 3.

2 The risk criteria

Let Y be a random variable. We will consider the following risk criteria (Pflug 2000; Rockafellar and Uryasev 2000):

  • Value at risk (\(\alpha \)-quantile of Y):

    $$\begin{aligned} \mathbf{VaR}_\alpha [Y]=\inf \{t: \mathrm{Pr}[Y\le t] \ge \alpha \}, \alpha \in (0,1], \end{aligned}$$
  • Conditional value at risk:

    $$\begin{aligned} \mathbf{CVaR}_\alpha [Y]= & {} \inf \left\{ \gamma +\frac{1}{1-\alpha }{} \mathbf{E}[Y-\gamma ]^+: \gamma \in \mathbb {R}\right\} ,\\&\alpha \in [0,1), \end{aligned}$$

where \([x]^+=\max \{0,x\}\). Assume that Y is a discrete random variable taking nonnegative values \(b_1,\ldots , b_K\). Then, \( \mathbf{VaR}_\alpha [Y]\) and \(\mathbf{CVaR}_\alpha [Y]\) can be computed by using the following programs, respectively [see, e.g., Atakan et al. (2017), Ogryczak (2012) and Rockafellar and Uryasev (2000)]:

$$\begin{aligned} \text {(a)}\quad&\min \theta&\text {(b)}\quad&\min \gamma + \frac{1}{1-\alpha }\sum _{i\in [K]} \mathrm{Pr}[Y=b_k] u_k\nonumber \\ \text {s.t. }&b_k-\theta \le M \beta _k,\quad k\in [K]&\text {s.t. }&\gamma + u_k \ge \displaystyle b_k,\quad k\in [K] \nonumber \\&\sum _{k\in [K]} \mathrm{Pr}[Y=b_k] \beta _k \le 1-\alpha&u_k\ge 0,\quad k\in [K]\nonumber \\&\beta _k\in \{0,1\},\quad k\in [K]&\end{aligned}$$
(1)

where \(M\ge \max \{b_1,\ldots , b_K\}\) and \([K]=\{1,\ldots ,K\}\). Notice that (1)b is a linear programming problem. In the following, we will use the following dual to (1)b:

$$\begin{aligned} \begin{array}{lll} \displaystyle \max &{}\quad \displaystyle \sum _{k\in [K]} b_k r_k \\ \text {s.t.} &{}\quad \displaystyle \sum _{k\in [K]} r_k=1\\ &{}\quad 0 \le r_k\le \frac{\mathrm{Pr}[Y=b_k] }{1-\alpha }, &{}\quad k\in [K] \end{array} \end{aligned}$$
(2)

The equality constraint in (2) follows from the fact that \(\gamma \) is real-valued decision variable in (1)b. Substituting \(r_k=q_k/(1-\alpha )\) into (2), we get the following equivalent formulation for \(\mathbf{CVaR}_\alpha [Y]\):

$$\begin{aligned} \begin{array}{lll} \displaystyle \max &{}\quad \displaystyle \frac{1}{1-\alpha } \sum _{k\in [K]} b_k q_k\\ \text {s.t.} &{}\quad \displaystyle \sum _{k\in [K]} q_k=1-\alpha \\ &{}0 \le q_k\le \mathrm{Pr}[Y=b_k], &{}\quad k\in [K] \end{array} \end{aligned}$$
(3)

Program (3) can be solved by using a greedy method, which is illustrated in Fig. 1. Namely, we fix the optimal values of \(q_k\) by greedily distributing the amount \(1-\alpha \) among the largest values of \(b_i\). It is easy to see that \(\mathbf{CVaR}_{0}[Y]=\mathbf{E}[Y]=\sum _{k\in [K]} b_k \mathrm{Pr}[Y=b_k]\). On the other hand, \(\mathbf{CVaR}_{1-\epsilon }[Y]= \mathbf{VaR}_1[Y]=\mathbf{Max}[Y]=\max _{k\in [K]} b_k\) for sufficiently small \(\epsilon >0\) and any probability distribution.

Fig. 1
figure 1

A computation of \(\mathbf{CVaR}_{0.5}[Y]\) for Y taking the values of 13, 29, 33, 22 and 36 with the probabilities 0.3, 0.2, 0.1, 0.1, 0.3, respectively, where \(\mathrm{Pr}[Y=b_k]=p_k\). The value of \(\mathbf{CVaR}_{0.5}[Y]\) is the gray area divided by \(1-\alpha =0.5\)

We now show several properties of the risk measures which will be used later on in this paper.

Lemma 1

Let Y be a discrete random variable which can take K nonnegative values \(b_1,\ldots , b_K\). The following inequalities hold for each \(\alpha \in [0,1)\):

$$\begin{aligned} \mathbf{E}[Y]\le \mathbf{CVaR}_\alpha [Y] \le \min \left\{ \frac{1}{{\Pr }_{\min }},\frac{1}{1-\alpha } \right\} \mathbf{E}[Y], \end{aligned}$$
(4)

where \(\mathrm{Pr}_{\min }=\min _{k\in [K]} \mathrm{Pr}[Y=b_k]\).

Proof

Fix \(\alpha \in [0,1)\). The inequality \(\mathbf{E}[Y]\le \mathbf{CVaR}_\alpha [Y]\) follows directly from the definition of the expected value and the conditional value at risk. We now prove the second inequality. Let \(r^*_1, \ldots r^*_k\) be the optimal values in (2). Then, the inequality

$$\begin{aligned} {\mathbf{CVaR}}_\alpha [Y]= & {} \sum _{k\in [K]} r^*_k b_k \le \sum _{k\in [K]} \frac{\mathrm{Pr}[Y=b_k]}{(1-\alpha )} b_k\\= & {} \frac{1}{1-\alpha }{} \mathbf{E}[Y] \end{aligned}$$

holds. Since the value of \(\mathbf{CVaR}_\alpha [Y]\) is a convex combination of \(b_1,\ldots ,b_k\) (see (2)), we have \(\mathbf{CVaR}_\alpha [Y] \le \mathbf{Max}[Y]=b_{\max }\le \sum _{k\in [K]} \frac{\mathrm{Pr}[Y=b_k]}{\mathrm{Pr}_{\min }} b_k=\frac{1}{\mathrm{Pr}_{\min }}{} \mathbf{E}[Y],\) and the lemma follows. \(\square \)

Lemma 2

Let X and Y be two discrete random variables taking nonnegative values \(a_1,\ldots , a_K\), and \(b_1,\ldots , b_K\), respectively, with \(\mathrm{Pr}[{X}=a_i]=\mathrm{Pr}[Y=b_i]\) and \(a_i\le \gamma b_i\) for each \(i\in [K]\) and some fixed \(\gamma \ge 0\). Then \(\mathbf{CVaR}_\alpha [{X}]\le \gamma \mathbf{CVaR}_\alpha [Y]\) for each \(\alpha \in [0,1)\) and \(\mathbf{VaR}_\alpha [{X}]\le \gamma \mathbf{VaR}_\alpha [Y]\) for each \(\alpha \in (0,1]\).

Proof

Let us compute \(\mathbf{CVaR}_\alpha [{X}]\) by using (2) and denote by \(r^*_k\), \(k\in [K]\), the optimal values in (2). Then, \(\mathbf{CVaR}_\alpha [{X}]=\sum _{k\in [K]} r^*_k a_k\le \gamma \sum _{k\in [K]} r^*_k b_k\le \gamma \mathbf{CVaR}_\alpha [Y]\). Let us compute \(\mathbf{VaR}_{\alpha }[Y]\) by solving the problem (1)a. Let \(\theta ^*\), \(\beta ^*_k\), \(k\in [K]\), be an optimal solution to (1)a. Since \(\gamma \ge 0\), the constraint \(\gamma b_k -\gamma \theta ^* \le \gamma M \beta ^*_k\) holds for each \(k\in [K]\). By \(a_k\le \gamma b_k\) for each \(k\in [K]\), we get \(a_k-\gamma \theta ^* \le M' \beta ^*_k,\) where \(M'=\gamma M \ge \max \{a_1,\ldots , a_K\}\), \(k\in [K]\). In consequence,

$$\begin{aligned} \begin{array}{llll} &{} \displaystyle a_k-\gamma \theta ^*\le M' \beta ^*_k &{} k\in [K]\\ &{}\displaystyle \sum _{k\in [K]} \mathrm{Pr}[{X}=a_k] \cdot \beta ^*_k \le 1-\alpha \\ \end{array} \end{aligned}$$
(5)

and \(\mathbf{VaR}_{\alpha }[{X}]\le \gamma \theta ^*=\gamma \mathbf{VaR}_{\alpha }[Y]\). \(\square \)

Fig. 2
figure 2

A sample scheduling problem \(1||\sum C_j\) with 5 processing time scenarios

3 Problem formulations

We are given a set J of n jobs, which can be partially ordered by some precedence constraints. Namely, \(i\rightarrow j\) means that job j cannot start before job i is completed. For each job \(j\in J\), a nonnegative processing time \(p_j\), a nonnegative due date \(d_j\) and a nonnegative weight \(w_j\) can be specified. A schedule \(\pi \) is a feasible (i.e., preserving the precedence constraints) permutation of the jobs and \(\Pi \) is the set of all feasible schedules. We will use \(C_j(\pi )\) to denote the completion time of job j in schedule \(\pi \). Obeying the standard notation, we will use \(T_j(\pi )=[C_j(\pi )-d_j]^+\) to define the tardiness of j in \(\pi \), and \(U_j(\pi )=1\) if \(C_j(\pi )>d_j\) (job j is late in \(\pi \)) and \(U_j(\pi )=0\) (job j is on-time in \(\pi \)), otherwise. In the deterministic case, we seek a schedule \(\pi \in \Pi \) that minimizes a given cost function \(f(\pi )\). The basic cost functions are the total flow time \(\sum _{j\in J} C_j(\pi )\), the total tardiness \(\sum _{j\in J} T_j(\pi )\), the maximum tardiness \(\max _{j\in J} T_j(\pi )\) and the total number of late jobs  \(\sum _{j\in J} U_j(\pi )\). We can also consider the weighted versions of these functions. Scheduling problems \(\mathcal {P}\) will be denoted by means of the standard Graham’s notation [see, e.g., Brucker (2007)].

In this paper, we assume that job processing times and due dates can be uncertain. The uncertainty is modeled by a discrete scenario set\(\mathcal {U}=\{\xi _1,\xi _2,\ldots ,\xi _K\}\). Each realization of the parameters \(\xi \in \mathcal {U}\) is called a scenario. For each scenario \(\xi \in \mathcal {U}\), a probability \(\mathrm{Pr}[\xi ]\) of its occurrence is known. Without loss of generality, we can assume  \(\mathrm{Pr}[\xi ]>0\). We will use \(p_j(\xi )\) and \(d_j(\xi )\) to denote the processing time and due date of job j under scenario \(\xi \in \mathcal {U}\), respectively. We will denote by \(C_j(\pi , \xi )\), \(T_j(\pi , \xi )\) and \(U_j(\pi , \xi )\) the completion time, tardiness and unit penalty of job \(\pi \), respectively, under scenario \(\xi \in \mathcal {U}\). Also, \(f(\pi , \xi )\) stands for the cost of schedule \(\pi \) under scenario \(\xi \in \mathcal {U}\). Given a feasible schedule \(\pi \in \Pi \), we denote by \(\mathrm{F}(\pi )\) a random cost of \(\pi \). Notice that \(\mathrm{F}(\pi )\) is a discrete random variable with the probability distribution induced by the probability distribution in \(\mathcal {U}\).

For a fixed value of \(\alpha \), we can compute a performance measure of \(\pi \), namely the expected cost \(\mathbf E [\mathrm{F}(\pi )]\), the maximum cost \(\mathbf Max [\mathrm{F}(\pi )]\), the value at risk \(\mathbf VaR _\alpha [\mathrm{F}(\pi )]\) and the conditional value at risk \(\mathbf CVaR _\alpha [\mathrm{F}(\pi )]\). A sample problem \(1||\sum C_j\) with 4 jobs and 5 processing time scenarios is shown in Fig. 2. Let \(\pi =(1,2,3,4)\). It is easily seen that \(\mathbf E [\mathrm{F}(\pi )]=26\), \(\mathbf VaR _{0.5}[\mathrm{F}(\pi )]=29\), \(\mathbf CVaR _{0.5}[\mathrm{F}(\pi )]=34\) and \(\mathbf Max [\mathrm{F}(\pi )]=36\).

In this paper, we will study the problems \(\textsc {Min}{-}\textsc {VaR}_\alpha ~\mathcal {P}\), \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\), \(\textsc {Min}{-}\textsc {Exp}\) \(\mathcal {P}\), and \(\textsc {Min}{-}\textsc {Max}~\mathcal {P}\), in which we minimize the corresponding performance measure for a fixed \(\alpha \) and a specific single machine scheduling problem \(\mathcal {P}\), under a given scenario set \(\mathcal {U}\). Notice that the robust \(\textsc {Min}{-}\textsc {Max}~\mathcal {P}\) problem is a special case of both \(\textsc {Min}{-}\textsc {VaR}_\alpha ~\mathcal {P}\) and \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\). Also, \(\textsc {Min}{-}\textsc {Exp}\) \(\mathcal {P}\) is a special case of \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\).

In the next sections, we provide a number of new positive and negative complexity and approximation results for basic single machine scheduling problems \(\mathcal {P}\). Tables 12 and 3 summarize the known and new results. In Table 1, the negative results for uncertain due dates and deterministic processing times are shown. In Table 2, the negative results for uncertain processing times and deterministic due dates are presented. Finally, in Table 3, some positive results are shown.

Table 1 Complexity results for uncertain due dates (processing times are deterministic)
Table 2 Complexity results for uncertain processing times (the due dates are deterministic)
Table 3 Positive complexity results

4 Some general properties

In this section, we will show some general relationships between the problems with various performance criteria. These properties will be used later to establish some positive and negative complexity results for particular problems.

Theorem 1

The following statements hold:

  1. 1.

    If \(\textsc {Min}{-}\textsc {Exp}~\mathcal {P}\) is approximable within \(\sigma >1\)(for \(\sigma =1\) it is polynomially solvable), then \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\) is approximable within \(\sigma \rho \), where \(\rho = \min \{\frac{1}{\mathrm{Pr}_{\min }},\frac{1}{1-\alpha }\}\), for each constant \(\alpha \in [0,1)\).

  2. 2.a

    If \(\textsc {Min}{-}\textsc {Exp}~\mathcal {P}\) with K-scenarios is (strongly) NP-hard, then \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\) with \(K+1\) scenarios is also (strongly) NP-hard for each constant \(\alpha \in [0,1)\).

  3. 2.b

    If \(\textsc {Min}{-}\textsc {Exp}~\mathcal {P}\) with K-scenarios is hard to approximate within \(\rho >1\), then \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\) with \(K+1\) scenarios is also hard to approximate within \(\rho >1\) for each constant \(\alpha \in [0,1)\).

Proof

We first prove assertion 1. Let \(\pi ^*\) minimize the expected cost and \(\pi '\) minimize the conditional value at risk for a fixed \(\alpha \in [0,1)\). We will denote by \(\hat{\pi }\) a \( \sigma \)-approximation schedule for \(\textsc {Min}{-}\textsc {Exp}~\mathcal {P}\). Using Lemma 1 we get

$$\begin{aligned} \mathbf{CVaR}_\alpha [\mathrm{F}(\hat{\pi })]\le & {} \rho \mathbf{E}[\mathrm{F}(\hat{\pi })]\le \sigma \rho \mathbf{E}[\mathrm{F}(\pi ^*)] \\\le & {} \sigma \rho \mathbf{E}[\mathrm{F}(\pi ')]\le \sigma \rho \mathbf{CVaR}_\alpha [\mathrm{F}(\pi ')], \end{aligned}$$

and the assertion follows.

Fig. 3
figure 3

Illustration of the proof of Theorem 1

In order to prove assertion 2, consider an instance of \(\textsc {Min}{-}\textsc {Exp}~\mathcal {P}\) with \(\mathcal {U}=\{\xi _1,\ldots ,\xi _K\}\). Fix \(\alpha \in (0,1)\) (the statement trivially holds for \(\alpha =0\)) and add one additional scenario \(\xi '\) under which the cost of each schedule is 0. (For example, all job processing times are 0 under \(\xi '\).) We fix \(\mathrm{Pr}'[\xi ']=\alpha \) and \(\mathrm{Pr}'[\xi _i]=\mathrm{Pr}[\xi _i]\cdot (1-\alpha )\) for each \(i\in [K]\). Denote by \(\mathrm{F}'(\pi )\) the random cost of \(\pi \) under the new scenario set \(\mathcal {U}'\). For each schedule \(\pi \), we get (see Fig. 3):

$$\begin{aligned} \mathbf{CVaR}_{\alpha }[\mathrm{F}'(\pi )]= & {} \frac{1}{1-\alpha }\sum _{i\in [K]} \mathrm{Pr}'[\xi _i] f(\pi , \xi _i) \\= & {} \sum _{i\in [K]}\mathrm{Pr}[\xi _i] f(\pi , \xi _i)=\mathbf{E}[\mathrm{F}(\pi )]. \end{aligned}$$

Hence, there is a cost preserving reduction from \(\textsc {Min}{-}\textsc {Exp}~\mathcal {P}\) with K scenarios to \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\) with \(K+1\) scenarios and the theorem follows. \(\square \)

Theorem 2

Assume that \(w_j=1\) for each job \(j\in J\) in problem \(\mathcal {P}\). The following statements hold:

  1. 1.a

    If MinMax \(\mathcal {P}\) with \(K\ge 2\) scenarios is (strongly) NP-hard, then \(\textsc {Min}{-}\textsc {VaR}_\alpha ~\mathcal {P}\) with \(K+1\) scenarios is (strongly) NP-hard for each constant \(\alpha \in (0,1]\).

  2. 1.b

    If MinMax \(\mathcal {P}\) with \(K\ge 2\) scenarios is hard to approximate within \(\rho >1\), then \(\textsc {Min}{-}\textsc {VaR}_\alpha ~\mathcal {P}\) with \(K+1\) scenarios is hard to approximate within \(\rho >1\) for each constant \(\alpha \in (0,1]\).

  3. 2.

    If MinMax \(\mathcal {P}\) with \(K\ge 2\) scenarios is (strongly) NP-hard, then \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\) with \(K+1\) scenarios is (strongly) NP-hard for each constant \(\alpha \in (0,1)\)

Proof

Choose an instance of the \(\textsc {Min}{-}\textsc {Max}~\mathcal {P}\) problem with \(\mathcal {U}=\{\xi _1,\ldots , \xi _K\}\), \(K\ge 2\). Fix \(\alpha \in (0,1)\) and create \(\mathcal {U}'\) by adding to \(\mathcal {U}\) a dummy scenario \(\xi '\) such that the cost of each schedule under \(\xi '\) equals M and \(M\ge f(\pi , \xi _i)\) for each \(i\in [K]\) and each \(\pi \in \Pi \). It is enough to fix \(p_j(\xi ')=p_{\max }\) and \(d_j(\xi ')=d_{\min }\) for each job \(j\in J\), where \(p_{\max }=\max _{j\in J, i\in [K]} p_j(\xi _i)\) is the maximum job processing time and \(d_{\min }=\min _{j\in J, i\in [K]} d_j(\xi _i)\) is the minimum due date over all scenarios. For each of the two assertions, we define an appropriate probability distribution in \(\mathcal {U}'\). We will use \(\mathrm{F}'(\pi )\) to denote the random cost of \(\pi \) under \(\mathcal {U}'\).

In order to prove statement 1, we fix \(\mathrm{Pr}[\xi ']=1-\alpha \) and \(\mathrm{Pr}[\xi _i]=\frac{\alpha }{K}\) for each \(i\in [K]\) (see Fig. 4a). The equality \(\mathbf{VaR}_\alpha [\mathrm{F}'(\pi )]=\mathbf{Max}[\mathrm{F}(\pi )]\) holds. Hence, there is a cost preserving reduction from \(\textsc {Min}{-}\textsc {Max}~\mathcal {P}\) with K scenarios to \(\textsc {Min}{-}\textsc {VaR}_\alpha ~\mathcal {P}\) with \(K+1\) scenarios and the statement follows. Note that statement 1 holds trivially for \(\alpha =1\).

Let us now prove statement 2. Assume first that \(1-\alpha < \frac{1}{K}\). Define \(\mathrm{Pr}[\xi _i]=\frac{1}{K}\) for each \(i\in [K]\) and \(\mathrm{Pr}[\xi ']=0\). The dummy scenario is not used in this case. We get \(\mathbf{CVaR}_{\alpha }[\mathrm{F}'(\pi )]=\mathbf{Max}[\mathrm{F}(\pi )]\) and the statement is true. Consider the case, when \(1-\alpha \ge \frac{1}{K}\). Fix \(\mathrm{Pr}[\xi ']=\gamma \) and \(\mathrm{Pr}[\xi _i]=\beta \) for each \(i\in [K]\), where \(\gamma \) and \(\beta \) satisfy the following system of equations (see Fig. 4b):

$$\begin{aligned} \left\{ \begin{array}{ll} \beta +\gamma =1-\alpha \\ K\beta +\gamma =1 \end{array}\right. \end{aligned}$$

In consequence, \(\beta =\frac{\alpha }{K-1}\) and \(\gamma =1-\frac{K\alpha }{K-1}\). Observe that \(\beta >1\) as \(\alpha \in (0,1)\) and \(K\ge 2\), and \(\gamma \ge 0\), because \(\frac{K\alpha }{K-1}\le 1\).

Fig. 4
figure 4

Illustration of the proof of Theorem 2

For each schedule \(\pi \), we get

$$\begin{aligned} \mathbf{CVaR}_{\alpha }[\mathrm{F}'(\pi )]=\frac{1}{1-\alpha }(\beta \cdot \mathbf{Max}[\mathrm{F}(\pi )] + \gamma M). \end{aligned}$$

Hence, \(\textsc {Min}{-}\textsc {Max}~\mathcal {P}\) and the corresponding instance of \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\) have the same optimal solutions and the theorem follows. \(\square \)

5 Negative complexity results

In this section, we will prove some negative complexity results for basic single machine scheduling problems. These results are summarized in Tables 1 and 2.

5.1 Uncertain due dates

We first address the problem of minimizing the value at risk criterion. The following theorem characterizes the complexity of some basic problems:

Theorem 3

For each \(\alpha \in (0,1)\), \(\textsc {Min}{-}\textsc {Var}_\alpha ~\mathcal {P}\) is strongly NP-hard and not at all approximable, when \(\mathcal {P} \in \{1|p_j=1| \max T_j,\, 1|p_j=1|\sum T_j, \,1|p_j=1| \sum U_j\}\) and only due dates are uncertain.

Proof

Consider an instance of the following NP-hard Min 3-Sat problem (Kohli et al. 1994; Avidor and Zwick 2002). We are given boolean variables \(x_1,\ldots , x_n\), a collection of clauses \(\mathcal {C}_1,\ldots \mathcal {C}_m\), where each clause is a disjunction of at most 3 literals (variables or their negations), and we ask if there is an assignment to the variables which satisfies at most \(L < m\) clauses. We can ask equivalently, if there is an assignment to the variables for which at least \(l=m-L\) clauses are not satisfied.

Given an instance of Min 3-Sat, we create two jobs \(J_{x_i}\) and \(J_{\overline{x}_i}\) for each variable \(x_i\), \(i\in [n]\). A due date scenario \(\xi _i\) corresponds to clause \(\mathcal {C}_i=(l_1 \vee l_2 \vee l_3)\) and is formed as follows. For each \(q=1,2,3\), if \(l_q=x_j\), then the due date of \(J_{x_j}\) is \(2j-1\) and the due date of \(J_{\overline{x}_j}\) is 2j; if \(l_q=\overline{x}_j\), then the due date of \(J_{x_j}\) is 2j and the due date of \(J_{\overline{x}_j}\) is \(2j-1\); if neither \(x_j\) nor \(\overline{x}_j\) appears in \(\mathcal {C}_i\), then the due dates of \(J_{x_j}\) and \(J_{\overline{x}_j}\) are set to 2j. An example is shown in Table 4.

Table 4 The set of jobs and the due date scenarios for the formula \((x_1\vee \overline{x}_2 \vee \overline{x}_3)\wedge (\overline{x}_2 \vee \overline{x}_3 \vee x_4) \wedge (\overline{x}_1 \vee x_2 \vee \overline{x}_4) \wedge (x_1 \vee x_2 \vee x_3) \wedge (x_1 \vee x_3 \vee \overline{x}_4)\)

Let us define a subset of the schedules \(\Pi '\subseteq \Pi \) such that each schedule \(\pi \in \Pi '\) is of the form \(\pi =(J_1,J_1',J_2,J_2',\ldots ,J_n,J_n')\), where \(J_j,J_j'\in \{J_{x_j},J_{\overline{x}_j}\}\) for \(j\in [n]\). Observe that \(\Pi '\) contains exactly \(2^n\) schedules and each such a schedule corresponds to the assignment to the variables such that \(x_j=0\) if \(J_{x_j}\) is processed before \(J_{\overline{x}_j}\) and \(x_j=1\) otherwise. Note that this correspondence is one-to-one. In the following, we assume that \(f(\pi , \xi _i)\) is the maximum tardiness, or the total tardiness, or the sum of unit penalties in \(\pi \) under \(\xi _i\). The reasoning will be the same for each of these cost functions. If \(\pi \notin \Pi '\), then \(f(\pi , \xi _i)>0\) for each scenario \(\xi _i\). Indeed, suppose that \(\pi \notin \Pi '\) and let \(J_j\) (\(J_j')\) be the last job in \(\pi \) which is not placed properly, i.e., \(J_j,(J_j')\notin \{J_{x_j},J_{\overline{x}_j}\}\). Then, \(J_j\) (\(J_j'\)) is late under all scenarios. On the other hand, if \(\pi \in \Pi '\), then the number of scenarios under which no job is late is equal to the number of unsatisfiable clauses for the assignment corresponding to \(\pi \). Fix \(\alpha \in (0,1)\). We will add to \(\mathcal {U}\) one additional scenario \(\xi '\) and define a probability distribution in \(\mathcal {U}\), depending on the fixed \(\alpha \), so that the answer to Min 3-Sat is yes if and only if there is schedule \(\pi \) for which \(\mathbf {VaR}_{\alpha }[\mathrm{F}(\pi )]\le 0\). This will prove the stated result. We consider two cases:

  1. 1.

    \(l/m\ge \alpha \). We create dummy scenario \(\xi '\) under which the due date of all jobs is equal to 0. The probability of this scenario is equal to \(\frac{l-\alpha m}{l}\). The probability of each of the remaining scenarios is equal to \(\frac{1}{m}(1-\frac{l-\alpha m}{l})=\frac{\alpha }{l}\). Assume that the answer to Min 3-Sat is yes. So, there is an assignment to the variables which satisfies at most \(m-l\) clauses. By the above construction, there is a schedule \(\pi \in \Pi '\) whose cost is positive under at most \(m-l\) scenarios plus the dummy one. It holds

    $$\begin{aligned} \mathrm {Pr}[\mathrm{F}(\pi )>0]\le \frac{l-\alpha m}{l} + (m-l)\frac{\alpha }{l}=1-\alpha . \end{aligned}$$

    Hence, \(\mathrm {Pr}[\mathrm{F}(\pi )\le 0]\ge \alpha \) and \(\mathbf {VaR}_{\alpha }[\mathrm{F}(\pi )]\le 0\). Assume that the answer to Min 3-Sat is no. Then, for every schedule \(\pi \) there are more than \(m-l\) scenarios under which the cost of \(\pi \) is positive plus the dummy one. Hence, \(\mathrm {Pr}[\mathrm{F}(\pi )>0]> (1-\alpha )\) and \(\mathrm {Pr}[\mathrm{F}(\pi )\le 0]<\alpha \). In consequence, \(\mathbf {VaR}_{\alpha }[\mathrm{F}(\pi )]>0\).

  2. 2.

    \(l/m<\alpha \). We create dummy scenario \(\xi '\) under which the due date of each job equals 2n. The probability of the dummy scenario is \(\frac{m\alpha -l}{m-l}\). The probability of each of the remaining scenarios is equal to \(\frac{1}{m}(1-\frac{m\alpha -l}{m-l})=\frac{1-\alpha }{m-l}\). Assume that the answer to Min 3-Sat is yes. So, there is an assignment to the variables which satisfies at most \(m-l\) clauses. By the construction, there is a schedule \(\pi \) whose cost is positive under at most \(m-l\) scenarios. Hence,

    $$\begin{aligned} \mathrm {Pr}[\mathrm{F}(\pi )\le & {} 0]=1-\mathrm {Pr}[\mathrm{F}(\pi )>0]\\\ge & {} 1-(m-l)\frac{1-\alpha }{m-l}=\alpha \end{aligned}$$

    and \(\mathbf {VaR}_{\alpha }[\mathrm{F}(\pi )]\le 0\). Assume that the answer to Min 3-Sat is no. Then, for each assignment more than \(m-l\) clauses are satisfied. By the construction, for every schedule \(\pi \) there are more than \(m-l\) scenarios under which the cost \(\pi \) is positive. Therefore, \(\mathrm {Pr}[\mathrm{F}(\pi )>0]>(m-l)\frac{1-\alpha }{m-l}=(1-\alpha )\) and \(\mathrm {Pr}[\mathrm{F}(\pi )\le 0]<\alpha \), so \(\mathbf {VaR}_{\alpha }[\mathrm{F}(\pi )]>0\). \(\square \)

It follows from Theorem 3 that the problem \(\textsc {Min}{-}\textsc {Var}_\alpha ~1||\sum w_jT_j\), discussed in Atakan et al. (2017), is strongly NP-hard and not at all approximable even in the restrictive case, in which all job processing times and weights are equal to 1. This negative result is true for each fixed \(\alpha \in (0,1)\). It was shown in Kasperski and Zieliński (2016) that \(\textsc {Min}{-}\textsc {Exp}~1|p_j=1| \max T_j\) is strongly NP-hard and hard to approximate within \(7/6-\epsilon \) for any \(\epsilon >0\). Hence, we immediately get from Theorem 1 that for each constant \(\alpha \in [0,1)\), \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~1|p_j=1| \max T_j\) is strongly NP-hard and hard to approximate within \(7/6-\epsilon \) for any \(\epsilon >0\).

We consider now the problem with the total tardiness criterion. The deterministic \(1||\sum T_j\) problem is known to be NP-hard (Lawler 1977). However, \(1|p_j=1|\sum T_j\) is polynomially solvable [see, e.g., Brucker (2007)]. The following result characterizes the complexity of the minmax version of this problem:

Theorem 4

MinMax \(1|p_j=1|\sum T_j\) with uncertain due dates is strongly NP-hard and not approximable within \(\frac{5}{4}-\epsilon \) for any \(\epsilon >0\).

Proof

We will show a reduction from the NP-complete 3-Sat problem, in which we are given boolean variables \(x_1,\ldots , x_n\), a collection of clauses \(\mathcal {C}_1,\ldots \mathcal {C}_m\), where each clause is a disjunction of at most 3 literals (variables or their negations) and we ask if there is an assignment to the variables which satisfies all clauses [see, e.g., Garey and Johnson (1979)]. Given an instance of 3-Sat, we create two jobs \(J_{x_j}\) and \(J_{\overline{x}_j}\) for each variable \(x_j\), \(j\in [n]\), \(|J|=2n\). A due date scenario \(\xi _i\) corresponding to clause \(\mathcal {C}_i=(l_1 \vee l_2 \vee l_3)\) is created in the same way as in the proof of Theorem 3. Additionally, for each variable \(x_j\) we create scenario \(\xi _j'\) under which the due dates of \(J_{x_j}\) and \(J_{\overline{x}_j}\) are \(2(j-1)+\frac{1}{2}\) and the due dates of the remaining jobs are set to 2n (see Table 5). We first show that the answer to 3-Sat is yes if and only if there is a schedule \(\pi \) such that \(\max _{\xi \in \mathcal {U}} \sum _{j\in J} T_j(\pi , \xi )\le 2\).

Table 5 The set of jobs and the due date scenarios for the formula \((x_1\vee \overline{x}_2 \vee \overline{x}_3)\wedge (\overline{x}_2 \vee \overline{x}_3 \vee x_4) \wedge (\overline{x}_1 \vee x_2 \vee \overline{x}_4) \wedge (x_1 \vee x_2 \vee x_3) \wedge (x_1 \vee x_3 \vee \overline{x}_4)\). Schedule \(\pi =(J_{x_1},J_{\overline{x}_1}, J_{\overline{x}_2}, J_{x_2}, J_{x_3}, J_{\overline{x}_3}, J_{\overline{x}_4}, J_{x_4}))\) corresponds to a truth assignment

Assume that the answer to 3-Sat is yes. Consider schedule \(\pi =(J_1,J'_1,J_2,J'_2,\ldots ,J_n, J'_n)\), where \(J_j,J'_j\in \{J_{x_j}, J_{\overline{x}_j}\}\). Furthermore, \(J_{x_j}\) is processed before \(J_{\overline{x}_j}\) if and only if \(x_j=1\). Since in every clause at least one literal is true, at most two jobs in \(\pi \) are late under each scenario \(\xi _i\in \mathcal {U}\). The tardiness of each job in \(\pi \) under any \(\xi _i\in \mathcal {U}\) is at most 1. Furthermore, the total tardiness in \(\pi \) under any \(\xi '_j\) is exactly 2. In consequence, \(\max _{\xi \in \mathcal {U}} \sum _{j\in J} T_j(\pi , \xi )\le 2\).

Assume that there is a schedule \(\pi \), such that \(\max _{\xi \in \mathcal {U}} \sum _{j\in J} T_j(\pi , \xi )\le 2\). We claim that \(\pi =(J_1,J'_1,J_2,J'_2,\ldots ,J_n, J'_n)\), where \(J_j,J'_j\in \{J_{x_j}, J_{\overline{x}_j}\}\). Suppose that this is not the case, and let \(J_k\) (\(J'_k\)) be the last job in \(\pi \) which is not placed properly. The completion time of \(J_k\) (\(J'_k\)) is at least \(2k+1\). So, its tardiness under \(\xi '_k\) is at least \(2k+1-(2k-2+\frac{1}{2})=2.5\). Let \(x_j=1\) if and only if \(J_{x_j}\) is processed before \(J_{\overline{x}_j}\) in \(\pi \). Since only two jobs can be late under any \(\xi _i\), this assignment satisfies all clauses and the answer to 3-Sat is yes.

In order to prove the lower approximation bound, it is enough to observe that if the answer to 3-Sat is no, then each schedule has the total tardiness 3 under some scenario \(\xi _i\) or 2.5 under some scenario \(\xi '_j\), which gives a gap at least \(\frac{5}{4}\). \(\square \)

From the fact that \(1||\sum T_j\) is weakly NP-hard [see Du and Leung (1990)], we get immediately that more general \(\textsc {Min}{-}\textsc {Exp}~1||\sum T_j\) problem with uncertain due dates is weakly NP-hard as well. The next theorem strengthens this result.

Theorem 5

\(\textsc {Min}{-}\textsc {Exp}~1||\sum T_j\) with uncertain due dates is strongly NP-hard.

Proof

We will show a polynomial time reduction from the deterministic \(1||\sum w_j T_j\) problem, which is known to be strongly NP-hard (Lawler 1977). Consider an instance of \(1||\sum w_j T_j\). Let \(W=\sum _{j\in J} w_j>0\) and \(P=\sum _{j\in J} p_j\). We build an instance of \(\textsc {Min}{-}\textsc {Exp}~1||\sum T_j\) with the same set of jobs J and job processing times \(p_j\), \(j\in J\). We create \(K=|J|=n\) due date scenarios as follows. Under scenario \(\xi _j\), \(j\in [n]\), job j has due date equal to \(d_j\) and all the remaining jobs have due dates equal to P. We also fix \({\Pr }[\xi _i]=w_i/W\), \(i\in [n]\). For any schedule \(\pi \), we get \(\mathbf{E}[\mathrm{F}(\pi )]=\sum _{i\in [K]} \mathrm{Pr}[\xi _i] \sum _{j\in J} T_j(\pi , \xi _i)=\frac{1}{W}\sum _{i\in [n]} w_i \sum _{j\in J} T_j(\pi , \xi _i)\). By the construction, we get \(\sum _{j\in J} T_j(\pi , \xi _i)=[C_i(\pi )-d_i]^+\), so \(\mathbf{E}[\mathrm{F}(\pi )]=\frac{1}{W}\sum _{i\in [n]} w_i [C_i(\pi )-d_i]^+\). In consequence \(1||\sum w_j T_j\) and \(\textsc {Min}{-}\textsc {Exp}~1||\sum T_j\) have the same optimal solutions and the theorem follows. \(\square \)

It was shown in Aissi et al. (2011) that MinMax \(1|p_j=1|\sum U_j\) with uncertain due dates is strongly NP-hard. The following theorem strengthens this result:

Theorem 6

MinMax \(1|p_j=1|\sum U_j\) with uncertain due dates is not approximable within any constant factor unless P=NP.

Proof

Consider the following MinMax 0–1 Selection problem. We are given a set of items \(E=\{e_1,e_2,\ldots ,e_n\}\) and an integer \(q\in [n]\). For each item \(e_j\), \(j\in [n]\), there is a cost \(c_j(\xi _i)\in \{0,1\}\) under scenario \(\xi _i\), \(i\in [K]\). We seek a selection \(X\subseteq E\) of exactly q items, \(|X|=q\), which minimizes the maximum cost over all scenarios, i.e., the value of \(\max _{i\in [K]} \sum _{e_j\in X} c_j(\xi _i)\). This problem was discussed in Kasperski et al. (2013), where it was shown that it is not approximable within any constant factor \(\gamma > 1\). We will show that there is a cost preserving reduction from MinMax 0–1 Selection to the considered scheduling problem, which will imply the stated result.

Given an instance of MinMax 0–1 Selection, we build the corresponding instance of MinMax \(1|p_j=1|\sum U_j\) as follows. We create a set of jobs \(J=E\), \(|J|=n\), with deterministic unit processing times. For each \(i\in [K]\), if \(c_j(\xi _i)=1\) then \(d_j(\xi '_i)=n-q\), and if \(c_j(\xi _i)=0\), then \(d_j(\xi '_i)=n\). So, we create K due date scenarios that correspond to the cost scenarios of MinMax 0–1 Selection.

Suppose that there is a solution X to MinMax 0–1 Selection such that \(\sum _{e_j\in X} c_j(\xi _i)\le C\) for each \(i\in [K]\). Hence, X contains at most C items, \(C\le q\), with the cost equal to 1 under each scenario. In the corresponding schedule \(\pi \), we first process \(n-q\) jobs from \(J{\setminus } X\) and then the jobs in X in any order. It is easily seen that there are at most C late jobs in \(\pi \) under each scenario \(\xi '_i\), and hence, the maximum cost of schedule \(\pi \) is at most C. Conversely, let \(\pi \) be a schedule in which there are at most C late jobs under each scenario \(\xi '_i\). Clearly \(C\le q\) since the first \(n-q\) jobs in \(\pi \) must be on-time in all scenarios. Let us form solution X by choosing the items corresponding to the last q jobs in \(\pi \). Among these jobs at most C are late under each scenario, and hence, the cost of X is at most C under each scenario \(\xi _i\). \(\square \)

Thus, by Theorem 2, \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~1|p_j=1|\sum U_j\) is strongly NP-hard for any \(\alpha \in (0,1)\). (Notice that \(p_{\max }=1\) in the proof of Theorem 2 and in the new scenario set \(\mathcal {U}'\) still only due dates are uncertain.)

Theorem 7

\(\textsc {Min}{-}\textsc {Exp}~1||\sum U_j\) with uncertain due dates is NP-hard.

Proof

Consider the deterministic \(1||\sum w_j U_j\) problem, which is known to be NP-hard (Karp 1972). The reduction from this problem to \(\textsc {Min}{-}\textsc {Exp}~1||\sum U_j\) is the same as the one in the proof of Theorem 5. \(\square \)

It is worth noting that in the proof of Theorem 7 we require an arbitrary probability distribution in the scenario set and we have shown that the problem is only weakly NP-hard. Its complexity for uniform probability distribution is open.

5.2 Uncertain processing times

In this section, we characterize the complexity of the problems under consideration when only processing times are uncertain. It has been shown in Kouvelis and Yu (1997) that \(\textsc {Min}{-}\textsc {Max}~1||\sum C_j\) is strongly NP-hard. Furthermore, this problem is also hard to approximate within \(\frac{6}{5}-\epsilon \) for any \(\epsilon >0\) (Mastrolilli et al. 2013). Using Theorem 2, we can immediately conclude that the same negative result holds for \(\textsc {Min}{-}\textsc {VaR}_{\alpha }~1||\sum C_j\) for any \(\alpha \in (0,1]\). Also, strong NP-hardness of the min–max problem implies that \(\textsc {Min}{-}\textsc {CVaR}_{\alpha }~1||\sum C_j\) is strongly NP-hard for each fixed \(\alpha \in (0,1)\). Observe that the boundary case \(\alpha =0\) (i.e., \(\textsc {Min}{-}\textsc {Exp}~1||\sum C_j\)) is polynomially solvable, as it easily reduces to the deterministic \(1||\sum C_j\) problem. Since \(1||\sum C_j\) is a special case of \(1||\sum T_j\), with \(d_j=0\) for each \(j\in J\), the same negative results are true for the problem with the total tardiness criterion. Observe, however, that \(\textsc {Min}{-}\textsc {Exp}~1||\sum T_j\) is also NP-hard, since the deterministic \(1||\sum T_j\) problem is known to be weakly NP-hard (Du and Leung 1990).

It has been shown in Aloulou and Croce (2008) that MinMax \(1||\sum U_j\) with uncertain processing times and deterministic due dates is NP-hard. The following theorem strengthens this result:

Theorem 8

MinMax\(1||\sum U_j\) with uncertain processing times is strongly NP-hard. This assertion remains true even when all the jobs have a common deterministic due date.

Proof

We show a polynomial time reduction from the 3-Sat problem (see the proof of Theorem 4). Given an instance of 3-Sat, we create an instance of MinMax \(1||\sum U_j\) in the following way. For each variable \(x_i\), we create two jobs \(J_{x_i}\) and \(J_{\overline{x}_i}\), so J contains 2n jobs. The due dates of all these jobs are the same under each scenario and equal 2. For each clause \(C_j=(l_1,l_2,l_3)\), we construct processing time scenario \(\xi _i\), under which the jobs \(J_{\overline{l}_1}, J_{\overline{l}_2}, J_{\overline{l}_3}\) have processing time equal to 1 and all the remaining jobs have processing times equal to 0. Then, for each pair of jobs \(J_{x_i}, J_{\overline{x}_i}\) we construct scenario \(\xi '_i\) under which the processing times of \(J_{x_i}, J_{\overline{x}_i}\) are 2 and all the remaining jobs have processing times equal to 0. A sample reduction is shown in Table 6. We will show that the answer to 3-Sat is yes if and only if there is a schedule \(\pi \) such that \(\max _{\xi \in \mathcal {U}} \sum _{j\in J} U(\pi ,\xi )\le n\).

Table 6 Processing time scenarios for the formula \((x_1\vee \overline{x}_2 \vee \overline{x}_3)\wedge (\overline{x}_2 \vee \overline{x}_3 \vee x_4) \wedge (\overline{x}_1 \vee x_2 \vee \overline{x}_4) \wedge (x_1 \vee x_2 \vee x_3) \wedge (x_1 \vee x_3 \vee \overline{x}_4)\). Schedule \(\pi =(J_{x_1},J_{\overline{x}_2},J_{x_3},J_{\overline{x}_4} | J_{\overline{x}_1}, J_{x_2}, J_{\overline{x}_3}, J_{x_4})\) corresponds to a satisfying truth assignment

Assume that the answer to 3-Sat is yes. Then, there exists a truth assignment to the variables which satisfies all the clauses. Let us form schedule \(\pi \) by processing first the jobs corresponding to true literals in any order and processing then the remaining jobs in any order. From the construction of the scenario set, it follows that the completion time of the nth job in \(\pi \) under each scenario is not greater than 2. In consequence, at most n jobs in \(\pi \) are late under each scenario and \(\max _{\xi \in \mathcal {U}} \sum _{j\in J} U(\pi ,\xi )\le n\).

Assume that there is a schedule \(\pi \) such that \(\sum _{j\in J} U(\pi ,\xi )\le n\) for each \(\xi \in \mathcal {U}\), which means that at most n jobs in \(\pi \) are late under each scenario. Observe first that \(J_{x_i}\) and \(J_{\overline{x}_i}\) cannot appear among the first n jobs in \(\pi \) for any \(i\in [n]\); otherwise, more than n jobs would be late in \(\pi \) under \(\xi '_i\). Hence, the first n jobs in \(\pi \) correspond to a truth assignment to the variables \(x_1,\ldots ,x_n\), i.e., when \(J_l\) is among the first n jobs, then the literal l is true. Since \(f(\pi ,\xi _i)\le n\), the completion time of the n-th job in \(\pi \) under \(\xi _i\) is not greater than 2. We conclude that at most two jobs among the first n job have processing time equal to 1 under \(\xi _i\), so there are at most two false literals for each clause and the answer to 3-Sat is yes. \(\square \)

We thus get from Theorems 2 and 8 that \(\textsc {Min}{-}\textsc {VaR}_{\alpha }~1||\sum U_j\) is strongly NP-hard for any \(\alpha \in (0,1]\) and \(\textsc {Min}{-}\textsc {CVaR}_{\alpha }~1||\sum U_j\) is strongly NP-hard for any \(\alpha \in (0,1)\). The boundary case with \(\alpha =0\) (i.e., MinExp \(1||\sum U_j\) with uncertain processing times) is an interesting open problem.

6 Positive complexity results

In this section we establish some positive complexity results. Namely, we provide several polynomial and approximation algorithms for particular problems. A summary of the results can be found in Table 3.

6.1 Problems with uncertain due dates

Consider the \(\textsc {Min}{-}\textsc {Exp}~1|p_j=1|\sum w_jU_j\) problem with uncertain due dates. We introduce variables \(x_{ij}\in \{0,1\}\), \(i\in [n]\), \(j\in [n]\), where \(x_{ij}=1\) if \(j\in [n]\) is the ith job in the schedule constructed. The variables satisfy the assignment constraints, i.e., \(\sum _{i\in [n]} x_{ij}=1\) for each \(j\in [n]\) and \(\sum _{j\in [n]} x_{ij}=1\) for each \(i\in [n]\). If \(x_{ij}=1\), then the completion time of job j equals i. Define \(c_{ijk}=w_j\) if \(i>d_j(\xi _k)\) and \(c_{ijk}=0\) otherwise, for each \(i,j\in [n]\) and \(k\in [K]\). If the variables \(x_{ij}\) describe \(\pi \), then

$$\begin{aligned} \mathbf{E}[\mathrm{F}(\pi )]=\sum _{k\in [K]} \sum _{i\in [n]}\sum _{j\in [n]}\mathrm{Pr}[\xi _k] c_{ijk}x_{ij}=\sum _{i\in [n]}\sum _{j\in [n]}c^*_{ij} x_{ij}, \end{aligned}$$

where \(c^*_{ij}=\sum _{k\in [K]} \mathrm{Pr}[\xi _k] c_{ijk}\). Hence, the problem is equivalent to the Minimum Assignment with the cost matrix \(c^*_{ij}\). The same result holds for \(\textsc {Min}{-}\textsc {Exp}~1|p_j=1|\sum w_j T_j\). It is enough to define \(c_{ijk}=w_j[i-d_j(\xi _k)]^+\) for \(i,j\in [n]\), \(k\in [K]\). We thus get the following results:

Theorem 9

\(\textsc {Min}{-}\textsc {Exp}~\mathcal {P}\) with uncertain due dates is polynomially solvable, when \(\mathcal {P}\in \{1|p_j=1|\sum w_j U_j,\, 1|p_j=1|\sum w_j T_j\}\)

From Theorems 9 and 1, we immediately get the following approximation result:

Theorem 10

\(\textsc {Min}{-}\textsc {CVaR}_{\alpha }~\mathcal {P}\) with uncertain due dates is approximable within \(\rho =\min \{\frac{1}{\mathrm{Pr}_{\min }},\frac{1}{1-\alpha }\}\), when \(\mathcal {P}\in \{1|p_j=1|\sum w_j U_j, \,1|p_j=1|\sum w_j T_j\}\).

Since \(\textsc {Min}{-}\textsc {Max}~1|p_j=1|\sum w_jU_j\) and \(\textsc {Min}{-}\textsc {Max}~1|p_j=1|\sum w_jT_j\) are special cases of the min–max version of Minimum Assignment, which is approximable within K [see, e.g., Aissi et al. (2009)], both problems are approximable within K as well.

We now study the \(\textsc {Min}{-}\textsc {Exp}~1|| \sum w_j T_j\) problem with uncertain due dates and deterministic processing times. This problem is strongly NP-hard since \(1||\sum w_j T_j\) is strongly NP-hard. The expected cost of \(\pi \) can be rewritten as \(\mathbf{E}[\mathrm{F}(\pi )]=\sum _{j\in J} \sum _{i\in [K]} \mathrm{Pr}[\xi _i] [C_j(\pi )-d_j(\xi _i)]^+\). We thus get a single machine scheduling problem \(1||\sum f_j\) with job-dependent cost functions of form \(f_j(C_j(\pi ))= \sum _{i\in [K]} \mathrm{Pr}[\xi _i] [C_j(\pi )-d_j(\xi _i)]^+\), \(j\in J\). Note also that these functions are nonnegative and nondecreasing with respect to \(C_j(\pi )\). The same analysis can be done for the \(\textsc {Min}{-}\textsc {Exp}~1|| \sum w_j U_j\) problem with uncertain due dates and deterministic processing times. Hence and from Cheung et al. (2017), where a \((4+\epsilon )\)-approximation algorithm, for any \(\epsilon >0\), for this class of problems was provided, we get the following result (see also Theorem 1).

Theorem 11

If \(\mathcal {P}\in \{1||\sum w_j U_j,\, 1||\sum w_j T_j\}\), then \(\textsc {Min}{-}\textsc {Exp}\) \(\mathcal {P}\) with uncertain due dates is approximable within \(4+\epsilon \) and \(\textsc {Min}{-}\textsc {CVaR}_\alpha ~\mathcal {P}\) is approximable within \(\min \{\frac{4+\epsilon }{\mathrm{Pr}_{\min }},\frac{4+\epsilon }{1-\alpha }\}\), \(\epsilon >0\), for any \(\epsilon >0\) and each constant \(\alpha \in [0,1)\).

When the probability distribution in \(\mathcal {U}\) is uniform, then the approximation ratio in Theorem 1 can be improved to \(\min \{(4+\epsilon )K, \frac{4+\epsilon }{1-\alpha }\}\). Since MinMax \(\mathcal {P}\) is a special case of \(\textsc {Min}{-}\textsc {CVar}_{\alpha }~\mathcal {P}\) with uniform probability distribution and \(\alpha \) sufficiently large, we get that \(\textsc {Min}{-}\textsc {Max}\) \(\mathcal {P}\), \(\mathcal {P}\in \{1||\sum w_j U_j,\, 1||\sum w_j T_j\}\), is approximable within \((4+\epsilon )K\) for any \(\epsilon >0\).

6.2 The total weighted flow time criterion

In this section, we focus on the problems with the total weighted flow time criterion. We start by recalling a well-known property [see, e.g., Mastrolilli et al. (2013)], which states that every such a problem with uncertain processing times and deterministic weights can be transformed into an equivalent problem with uncertain weights and deterministic processing times. This transformation goes as follows. For each processing time scenario \(\xi _i\), \(i\in [K]\), we invert the role of processing times and weights obtaining the weight scenario \(\xi '_i\). Formally, \(p_j=w_j\) and \(w_j(\xi '_i)=p_j(\xi _i)\) for each \(i\in [K]\). The new scenario set \(\mathcal {U}'\) contains scenario \(\xi '_i\) with \(\mathrm{Pr}[\xi _i']=\mathrm{Pr}[\xi _i]\) for each \(i\in [K]\). We also invert the precedence constraints, i.e., if \(i\rightarrow j\) in the original problem, then \(j\rightarrow i\) in the new one. Given a feasible schedule \(\pi =(\pi (1),\ldots ,\pi (n))\), let \(\pi '=(\pi (n),\ldots ,\pi (1))\) be the corresponding inverted schedule. Of course, schedule \(\pi '\) is feasible for the inverted precedence constraints. It is easy to verify that \(f(\pi , \xi _i)=f(\pi ',\xi '_i)\) for each \(i\in [K]\). In consequence \(\mathbf{CVaR}_\alpha [\mathrm{F}(\pi )]=\mathbf{CVar}_\alpha [\mathrm{F'}(\pi ')]\) and \(\mathbf{VaR}_\alpha [\mathrm{F}(\pi )]=\mathbf{VaR}_\alpha [\mathrm{F'}(\pi ')]\), where \(\mathrm{F'}(\pi ')\) is the random cost of \(\pi '\) for scenario set \(\mathcal {U}'\). Hence, the original problem with uncertain processing times and the new one with uncertain weights have the optimal solutions with the same performance measure.

From now on we make the assumption that the jobs have deterministic processing times \(p_j\), \(j\in J\) and \(w_j(\xi _i)\) is the weight of job j under scenario \(\xi _i\), \(i\in [K]\). The value of \(\mathbf{CVaR}_\alpha [\mathrm{F}(\pi )]\), for a fixed schedule \(\pi \), can be computed by solving the following optimization problem (see the formulation (1)b):

$$\begin{aligned} \begin{array}{llll} \min &{}\quad \displaystyle \gamma + \frac{1}{1-\alpha }\sum _{i\in [K]} \mathrm{Pr}[\xi _k] u_k\\ \text {s.t.}&{}\quad \gamma + u_k \ge \displaystyle \sum _{j\in J}w_j(\xi _k) C_j(\pi ) &{}\quad k\in [K]\\ &{}\quad u_k\ge 0 &{}\quad k\in [K] \end{array} \end{aligned}$$
(6)

Let \(\delta _{ij}\in \{0,1\}\), \(i,j\in [n]\), be binary variables such that \(\delta _{ij}=1\) if job i is processed before job j in a schedule constructed. The vectors of all feasible job completion times \((C_1,\ldots , C_n)\) can be described by the following system of constraints (Potts 1980):

$$\begin{aligned} \begin{array}{llll} VC: &{} C_j=p_j+\sum _{i\in J{\setminus }\{j\}} \delta _{ij} p_i &{} j\in J\\ &{}\delta _{ij}+\delta _{ji}=1 &{} i,j\in J, i\ne j \\ &{}\delta _{ij}+\delta _{jk}+\delta _{ki} \ge 1 &{} i,j,k \in J\\ &{}\delta _{ij}=1 &{} i\rightarrow j\\ &{}\delta _{ij}\in \{0,1\}&{} i,j \in J \end{array} \end{aligned}$$
(7)

Let us denote by \(VC'\) the relaxation of VC, in which the constraints \(\delta _{ij}\in \{0,1\}\) are relaxed with \(0\le \delta _{ij}\le 1\). It has been proved in Schulz (1996) and Hall et al. (1997) that each vector \((C_1,\ldots , C_n)\) that satisfies \(VC'\) also satisfies the following inequalities:

$$\begin{aligned} \sum _{j\in I} p_jC_j\ge \frac{1}{2}\left( \left( \sum _{j\in I} p_j\right) ^2+\sum _{j\in I} p_j^2\right) \text { for all } I \subseteq J.\nonumber \\ \end{aligned}$$
(8)

The formulations (7) and (6) lead to the following mixed integer programming model for \(\textsc {Min}{-}\textsc {CVaR}_{\alpha }~1|prec|\sum w_j C_j\) with uncertain weights:

$$\begin{aligned} \begin{array}{llll} \min &{}\quad \displaystyle \gamma + \frac{1}{1-\alpha }\sum _{i\in [K]} \mathrm{Pr}[\xi _k] u_k\\ \text {s.t.}&{}\quad \gamma + u_k \ge \sum _{j\in J}w_j(\xi _k) C_j &{}\quad k\in [K]\\ &{}\quad \text {Constraints VC} \\ &{}\quad u_k\ge 0 &{}\quad k\in [K] \end{array} \end{aligned}$$
(9)

We now solve the relaxation of (9), in which VC is replaced with \(VC'\). Let \((C_1^*, \ldots , C_n^*)\) be the relaxed optimal job completion times and \(z^*\) be the optimal value of the relaxation. Consider discrete random variable Y, which takes the value \(\sum _{j\in J} w_j(\xi _i)C^*_j\) with probability \(\mathrm{Pr}[\xi _i]\), \(i\in [K]\). The equality \(z^*=\mathbf{CVaR}_\alpha [Y]\) holds. We relabel the jobs so that \(C^*_1\le C^*_2\le \cdots \le \ C_n^*\) and form schedule \(\pi =(1,2,\ldots ,n)\) in nondecreasing order of \(C^*_j\). Since the vector \((C_j^*)\) satisfies \(VC'\), it must also satisfy (8). Hence, setting \(I=\{1,\ldots ,j\}\), we get

$$\begin{aligned} \sum _{i=1}^j p_iC^*_i\ge \frac{1}{2}\left( \left( \sum _{i=1}^j p_i\right) ^2+\sum _{i=1}^j p_i^2\right) \ge \frac{1}{2}\left( \left( \sum _{i=1}^j p_i\right) ^2\right) . \end{aligned}$$

Since \(C^*_j\ge C_i^*\) for each \(i\in \{1\ldots j\}\), we get \(C^*_j\sum _{i=1}^j p_i\ge \sum _{i=1}^j p_iC^*_i \ge \frac{1}{2}(\sum _{i=1}^j p_i)^2\) and, finally \(C_j=\sum _{i=1}^j p_j \le 2 C^*_j\) for each \(j\in J\)—this reasoning is the same as in Schulz (1996).

For each scenario \(\xi _i\in \mathcal {U}\), the inequality \(f(\pi ,\xi _i)=\sum _{j\in J} w_j(\xi _i)C_j \le 2 \sum _{j\in J} w_j(\xi _i)C^*_j \) holds. By Lemma 2, we have \(\mathbf{CVaR}_\alpha [\mathrm{F}(\pi )]\le 2\cdot \mathbf{CVaR}_\alpha [Y]=2z^*\). Since \(z^*\) is a lower bound on the value of an optimal solution, \(\pi \) is a 2-approximate schedule. Let us summarize the obtained result.

Theorem 12

\(\textsc {Min}{-}\textsc {CVaR}_{\alpha }~1|prec|\sum w_j C_j\) with uncertain processing times is approximable within 2 for each \(\alpha \in [0,1)\).

This result can be refined when the deterministic \(1|prec|\sum w_j C_j\) problem is polynomially solvable [for example, when the precedence constraints form an sp-graph, see, e.g., Brucker (2007)]. In this case \(\textsc {Min}{-}\textsc {Exp}~1|prec|\sum w_j C_j\) is polynomially solvable, and we can also apply Theorem 1, which leads to the following result.

Theorem 13

If \(1|prec|\sum w_j C_j\) is polynomially solvable, then \(\textsc {Min}{-}\textsc {CVaR}_{\alpha }~1|prec|\sum w_j C_j\) with uncertain processing times is approximable within \(\min \{\frac{1}{1-\alpha }, 2\}\) for each \(\alpha \in [0,1)\).

Observe that \(\frac{1}{1-\alpha }<2\) for each \(\alpha <0.5\). Let us consider \(\textsc {Min}{-}\textsc {VaR}_{\alpha }~1|prec|\sum w_j C_j\) problem. The value of \(\mathbf{VaR}_\alpha [\mathrm{F}(\pi )]\), for a fixed schedule \(\pi \), can be computed by solving the following MIP problem (see (1)a):

$$\begin{aligned} \begin{array}{llll} \min &{}\quad \theta \\ \text {s.t.} &{}\quad \displaystyle \sum _{j\in J} w_j(\xi _k)C_j(\pi )-\theta \le M_k \beta _k &{} k\in [K]\\ &{}\quad \displaystyle \sum _{k\in [K]} \mathrm{Pr}[\xi _i] \beta _k \le 1-\alpha \\ &{}\quad \beta _k\in \{0,1\} &{}\quad k\in [K] \end{array} \end{aligned}$$
(10)

where \(M_k\) is an upper bound on the schedule cost under scenario \(\xi _k\), \(k\in [K]\). Using the formulation (7) together with (1), we can get a mixed integer programming formulation for \(\textsc {Min}{-}\textsc {VaR}_{\alpha }~1|prec|\sum w_j C_j\). By replacing the constraints VC with relaxed \(VC'\) in the constructed model, we get a mixed integer problem with K binary variables. This problem can be solved in polynomial time when K is a constant. The same analysis as for \(\textsc {Min}{-}\textsc {CVaR}_{\alpha }~1|prec|\sum w_j C_j\) (we also use Lemma 2) leads to the following result:

Theorem 14

If the number of scenarios is constant, then \(\textsc {Min}{-}\textsc {VaR}_{\alpha }~1|prec|\sum w_j C_j\) with uncertain processing times is approximable within 2 for each \(\alpha \in (0,1]\).

6.3 The bottleneck objective

In this section, we address a class of single machine scheduling problems with a bottleneck objective, i.e., in which \(f(\pi )=\max _{j\in J} f_j(C_j(\pi ))\), where \(f_j(t)\) is the cost of completing job j at time t. An important and well-known example is \(1|prec| \max w_j T_j\), in which the maximum weighted tardiness is minimized. This problem can be solved in \(O(n^2)\) time by Lawler’s algorithm (Lawler 1973). We will use the fact that the minmax versions of the bottleneck problems are polynomially solvable for a wide class of cost functions (Brauner et al. 2016; Kasperski and Zieliński 2016). In particular, the minmax version of \(1|prec| \max w_j T_j\) with uncertain processing times and uncertain due dates can be solved in \(O(Kn^2)\) time by using the algorithm constructed in Kasperski and Zieliński (2016). In the following, we will assume that \(f(\pi , \xi )=\max _{j\in J} w_j T_j(\pi , \xi )\) for a given scenario \(\xi \in \mathcal {U}\). We also assume that job processing times and due dates are nonnegative integers under all scenarios and job weights are positive integers. In consequence, the value of \(f(\pi , \xi )\) is a nonnegative integer for each \(\xi \).

Let \(f_{\max }\) be an upper bound on the schedule cost over all scenarios. Let \(h:\mathbb {Q}_{+}^K\rightarrow \mathbb {Q}_{+}\) be a nondecreasing function with respect to \(\mathbb {Q}_{+}^K\), i.e., for any \(\pmb {t},\pmb {t}'\in \mathbb {Q}_{+}^K\) if \(t'_i\le t_i\) for each \(i\in [K]\), then \(h(t_1',\ldots ,t_K')\le h(t_1,\ldots ,t_K)\). Suppose that h can be evaluated in g(K) time for a given vector \(\pmb {t}=(t_1,\ldots ,t_K)\in \mathbb {Z}_{+}^K\). Consider the corresponding scheduling problem \(\mathcal {PS}\), in which we seek a feasible schedule \(\pi \in \Pi \) minimizing \(H(\pi )=h(f(\pi ,\xi _1),\ldots , f(\pi , \xi _K))\). We can find such a schedule by solving a number of the following auxiliary problems: given a vector \(\pmb {t}\in \mathbb {Z}_{+}^K\), check if \(\Pi (\pmb {t})=\{\pi \in \Pi \,:\, f(\pi ,\xi _i)\le t_i, i\in [K]\}\) is nonempty, and if so, return any schedule \(\pi _{\pmb {t}}\in \Pi (\pmb {t})\). From the monotonicity of the function h, it follows that for each \(\pi \in \Pi (\pmb {t})\) the inequality \(h(f(\pi ,\xi _1),\ldots , f(\pi , \xi _K))\le h(\pmb {t})\) is true. Thus, in order to solve the problem \(\mathcal {PS}\), it suffices to enumerate all possible integral vectors \(\pmb {t}=(t_1,\ldots ,t_K)\), where \(t_i\in \{0,1,\ldots ,f_{\max }\}\), \(i\in [K]\), and compute \(\pi _{\pmb {t}}\in \Pi (\pmb {t})\) if \(\Pi (\pmb {t})\) is nonempty. The number of such vectors is \((f_{\max }+1)^K\). A schedule \(\pi _{\pmb {t}}\) with the minimum value of \(H(\pi _{\pmb {t}})\) is returned.

The crucial step in this method is solving the auxiliary problem. We now show that this can be done in polynomial time for the bottleneck problem with the maximum weighted tardiness criterion. Given any \(\pmb {t}\in \mathbb {Z}_{+}^K\), we first form scenario set \(\mathcal {U}'\) by specifying the following parameters for each \(\xi _i \in \mathcal {U}\) and \(j\in J\):

$$\begin{aligned} p_j(\xi _i')= & {} p_j(\xi _i), \quad w'_j = 1, \\ d_j(\xi _i')= & {} \max \{C\ge 0\,:\,w_j(C-d_j(\xi _i)){\le } t_i\} \\= & {} t_i/w_j+d_j(\xi _i). \end{aligned}$$

The scenario set \(\mathcal {U}'\) can be built in O(Kn) time. We then solve the minmax problem with scenario set \(\mathcal {U}'\), which can be done in \(O(Kn^2)\) time by using the algorithm constructed in Kasperski and Zieliński (2016). If the maximum cost of the schedule \(\pi \) returned is 0, then \(\pi _{\pmb {t}}=\pi \); otherwise, \(\Pi (\pmb {t})\) is empty. Since all the risk criteria considered in this paper are nondecreasing functions with respect to schedule costs over scenarios (see Lemma 2 for \(\gamma =1\)) and g(K) is negligible in comparison with \(Kn^2\), we get the following result.

Theorem 15

\( \textsc {Min}{-}\textsc {Exp}~\mathcal {P}\), \(\textsc {Min}{-}\textsc {VaR}_{\alpha }~\mathcal {P}\) and \(\textsc {Min}{-}\textsc {CVaR}_{\alpha }\mathcal {P}\) with uncertain processing times and uncertain due dates are solvable in \(O((f_{\max }+1)^K Kn^2)\) time, when \(\mathcal {P}\) is \(1|prec|\max w_j T_j\).

The above running time is pseudopolynomial if K is constant. Notice that the special cases, when \(\mathcal {P}\) is \(1|prec, p_j=1| \max T_j\) are solvable in \(O(K(n+1)^{K+2})\) time, which is polynomial if K is constant (as we can fix \(f_{\max }=n\)).

We now show that the problems admit an FPTAS if K is a constant and \(h(\gamma \pmb {t})\le \gamma h( \pmb {t})\), for any \(\pmb {t}\in \mathbb {Q}_{+}^K\), \(\gamma \ge 0\). First we partition the interval \([0,f_{\max }]\) into geometrically increasing subintervals: \([0,1)\cup \bigcup _{\ell \in [\eta ]}[(1+\epsilon )^{\ell -1}, (1+\epsilon )^{\ell })\), where \(\eta =\lceil \log _{1+\epsilon } f_{\max } \rceil \) and \(\epsilon \in (0,1)\). Then, we enumerate all possible vectors \(\pmb {t}=(t_1,\ldots ,t_K)\), where \(t_i\in \{0,1\}\cup \bigcup _{\ell \in [\eta ]}\{(1+\epsilon )^{\ell }\}\), \(i\in [K]\), and find \(\pi _{\pmb {t}}\in \Pi (\pmb {t})\) if \(\Pi (\pmb {t})\not =\emptyset \). Finally, we output a schedule \(\pi _{\hat{\pmb {t}}}\) that minimizes value of \(H(\pi _{\pmb {t}})\) over the nonempty subsets of schedules. Obviously, the running time is \(O(( \log _{1+\epsilon } f_{\max })^K (Kn^2+g(K)))= O((\epsilon ^{-1} \log f_{\max })^K (Kn^2+g(K)))\). Let \(\pi ^*\) be an optimal schedule. Fix \(\ell _i\in \{0,1,\ldots ,\eta \}\) for each \(i\in [K]\), such that \((1+\epsilon )^{\ell _i-1}\le f(\pi ^*,\xi _i)<(1+\epsilon )^{\ell _i}\), where we assume that \((1+\epsilon )^{\ell _i-1}=0\) for \(\ell _i=0\). This clearly forces \(\Pi ((1+\epsilon )^{\ell _1},\ldots ,(1+\epsilon )^{\ell _K})\not =\emptyset \). Moreover, \((1+\epsilon )^{\ell _i}\le (1+\epsilon ) f(\pi ^*,\xi _i)\) for \(\ell _i\), \(i\in [K]\). By the definition of \(\pi _{\hat{\pmb {t}}}\), we get \(H(\pi _{\hat{\pmb {t}}})\le h((1+\epsilon )^{\ell _1},\ldots ,(1+\epsilon )^{\ell _K})\). Since h is a nondecreasing function and \(h(\gamma \pmb {t})\le \gamma h( \pmb {t})\), \(h((1+\epsilon )^{\ell _1},\ldots ,(1+\epsilon )^{\ell _K})\le (1+\epsilon )h(f(\pi ^*,\xi _1),\ldots ,f(\pi ^*,\xi _K))\). Hence, \(H(\pi _{\hat{\pmb {t}}})\le (1+\epsilon )H(\pi ^*)\). By Lemma 2, the risk criteria satisfy the additional assumption on the function \(h(\pmb {t})\). This leads to the following theorem:

Theorem 16

\( \textsc {Min}{-}\textsc {Exp}~\mathcal {P}\), \(\textsc {Min}{-}\textsc {VaR}_{\alpha }~\mathcal {P}\) and \(\textsc {Min}{-}\textsc {CVaR}_{\alpha }\mathcal {P}\) with uncertain processing times and uncertain due dates admit an FPTAS, when \(\mathcal {P}\) is \(1|prec|\max w_j T_j\) and the number of scenarios is constant.

It is worth pointing out that the problems from Theorem 16 are strongly NP-hard when the number of scenarios is a part of the input (see Sect. 5.1). If the number of scenarios is constant, then proving their weak NP-hardness is an interesting open problem.

7 Conclusions and open problems

In this paper, we have discussed a wide class of single machine scheduling problems with uncertain job processing times and due dates. This uncertainty is modeled by a discrete scenario set with a known probability distribution. In order to compute a solution, we have applied the risk criteria, namely the value at risk and conditional value at risk. The expectation and the maximum criteria are special cases of these risk measures. We have provided a number of negative and positive complexity results for problems with basic cost functions. Moreover, we have sharpened some negative ones obtained in Aissi et al. (2011) and Aloulou and Croce (2008). The picture of the complexity is presented in Tables 12 and 3. Obviously, the negative results obtained remain true for more general cases, for instance, for the problems with more than one machine.

There is still a number of interesting open problems on the models discussed. The negative results for uncertain due dates assume that the number of due dates scenarios is a part of input. The complexity status of the problems when the number of due date scenarios is fixed (in particular, equals 2) is open. For uncertain processing times, an interesting open problem is \(\textsc {Min}{-}\textsc {Exp}~1||\sum U_j\) (see Table 2). There is still a gap between the positive and negative results; in particular, we conjecture that the negative results for \(\textsc {Min}{-}\textsc {Var}~\mathcal {P}\) for uncertain processing times (see Table 2) can be strengthened. Now they are just the same as for the \(\textsc {Min}{-}\textsc {Max}~\mathcal {P}\).