Continuous monitoring is carried out after the installation. The pressure readings during tunnel filling, plant operation for a period of about 1 year and dewatering are illustrated in Figs. 11 and 12. Although the frequency of data acquisition is 10 Hz, the figures presented in Sects. 5.1 and 5.2 are based on pressure values averaged to a frequency of 1/60 Hz (one data point per minute) for clarity of the figures which represent the behavior over a larger duration. The short-term changes occurring during pressure transients are presented at a frequency of 10 Hz in Sect. 5.3.
Tunnel Filling and Dewatering
According to Palmstrøm and Broch (2017), the rate of controlled tunnel filling or dewatering in Norwegian unlined headrace tunnel and shafts is generally carried out at a rate of 15 m head increase/decrease per hour with a stop for minimum 2 h per 150 m head change and maximum head of 300 m per day. The tunnel filling and dewatering rates at Roskrepp are shown in Fig. 11a, b, respectively.
During filling, the maximum water pressure of 86 m at the instrumentation location was reached in about 24 h. The deaeration valves for all pipes were opened after 1 week of tunnel filling to release any air entrapped in the pipes, which is indicated by a sharp pressure drop in all pipes (Fig. 12) and plant operation was started afterwards. Simultaneous readings of the pore pressure in the rock mass are also shown and are discussed below.
Pore Pressure Response
At the time of installation, only three sensors were available at site. Therefore, only the pipe directly connected to the tunnel and pipes connected to BH1 and BH2 were equipped with sensors immediately after the installation work was completed. Three remaining sensors were added to the pipes connected to boreholes BH3, BH4 and BH5 on day 63. Hence, the initial pore pressure build-up during tunnel filling could not be recorded in these three holes. Therefore, the general response of BH3, BH4 and BH5, respectively, can be inferred only after day 63.
Borehole 1 (BH1) The pore pressure build-up in BH1 almost follows the same rate as water pressure increase in the tunnel. It regained pressure rapidly (within 5 min) after deaeration. This borehole registered a pressure drop between deaeration and start of operation when the tunnel water pressure was constant which indicates water seepage from the rock mass to the daylight area at the construction adit (i.e. area where the joint is exposed in the tunnel wall). A similar phenomenon is noticed during some intermittent shutdowns (Fig. 12). Also, the pore pressure variations between day 63 and day 166 seem random and did not follow any pattern. During this time, the power plant was shut down and the tunnel water pressure gradually increased due to increased water level in the reservoir. Except for this period, the pressure variations in BH1 during power productions usually follow the same pattern as the tunnel water pressure. Similar behavior is seen during tunnel dewatering. This borehole is responsive to pressure transients in the tunnel such that pore pressure closely follows the pattern of mass oscillation (discussed in Sect. 5.3).
Borehole 2 (BH2) The pore pressure build-up in BH2 is very slow as compared to BH1. It reached a pressure of about 18 m in 7 days. After deaeration, it took about 5 days to regain the same pressure (Fig. 12). This borehole is found to be non-responsive to the pressure transients in the tunnel (discussed in Sect. 5.3). The pore pressure in this borehole is found to be continuously rising as one can see until around day 135 (Fig. 12). This is happening even during intermittent shutdowns (days 72–76) and when water pressure in the tunnel is in static condition.
However, as one can see in Fig. 12, a drastic change in pressure behavior in this borehole occurred after around day 135. At first the water pressure was fluctuating and afterwards a sudden increase in pore pressure was observed making this borehole responsive to plant shutdown and start of operation and also started responding rapidly to the pressure transients.
Borehole 3 (BH3) BH3 registered most of the pressure build-up in 7 days after deaeration. Since the rock mass is already saturated by the time the sensor was installed, pressure build-up in the pipe after deaeration occurred relatively faster as compared to pressure build-up in BH2. It has the lowest magnitude of pore pressure as compared to other boreholes except BH5, which does not respond to pressure transients in the tunnel (discussed in Sect. 5.3).
Between days 78 and 136, the production is stopped and the tunnel water pressure is increasing due to rising water level in the reservoir. During this period the pore pressures in BH2, BH4 and BH5 are also increasing at the same rate. However, pore pressure in BH3 is increasing at a slower rate between days 78 and 102 and further decreasing between days 102 and 136 similar to the behavior seen in BH1, which also indicates water seepage through the rock mass from the daylight area of the construction adit. The rate of pore pressure drop during dewatering is the slowest in this borehole (Fig. 12).
Borehole 4 (BH4) BH4 registered rapid pressure build-up just after deaeration. This borehole has high pore pressure magnitude and is responsive to pressure transients (discussed in Sect. 5.3).
Borehole 5 (BH5) The pressure build-up in BH5 is faster as compared to BH3 but it has the lowest magnitude of pore pressure among all the boreholes. This borehole is non-responsive to pressure transients. However, the pore pressure changes occur much faster during transients as compared to other non-responsive boreholes (Fig. 12). During dewatering, the rate of pressure drop is almost as steep as responsive boreholes to a certain level and then becomes slower, which is similar to the non-responsive boreholes.
Response to Pressure Transients
Figures 13 and 14 show typical events of a normal shutdown and an emergency shutdown, respectively. These events are representative of the load changes and shutdowns that are occurring very frequently in recent years. The difference between these two shutdowns is the speed of closure of the turbine guide vanes. In this case of normal shutdown, complete closure of guide vanes takes place within 160 s. On the other hand, during an emergency shutdown, complete closure of guide vanes takes place within 10 s. The time period of water hammer and mass oscillation is about 2 s and 220 s, respectively.
Two distinct behaviors of rock mass response from different boreholes in terms of pore pressure change can be seen in both shutdown cases (Figs. 13 and 14). The behavior of BH1 and BH4 is responsive with pressure variation inside the borehole almost identical to the pressure variation in the tunnel, but with reduced amplitude of pressure. The second behavior shown by BH2, BH3 and BH5 is non-responsive and shows very little or no variation in pore pressure inside the rock mass during load changes.
For the responsive case, the effect of mass oscillation can be clearly seen in both shutdown cases (Figs. 13a and 14a). It is observed that the mass oscillations cause significant changes in rock mass pore pressure. However, the effect of water hammer is different between normal and emergency shutdowns even though they have similar frequencies. It is observed that during normal shutdown the water hammer travels into the rock mass (Fig. 13b) causing the pore pressure to vary with almost the same frequency but with reduced amplitude. This effect is more pronounced in BH1 than BH4. On the other hand, during emergency shutdown, water hammer shows very little impact on the rock mass pore pressure in both BH1 and BH4 (Fig. 14b).
Normally, the magnitude of water hammer should be higher during an emergency shutdown as compared to a normal shutdown but is just the opposite as seen above. This could be explained by the fact that during emergency shutdown at Roskrepp, the guide vanes are closed first, then reopened slightly to reduce water hammer, and then fully closed. This reopening dampens the water hammer but it is triggered two times (Fig. 14b). Further, to confirm that pressure peaks seen during normal shutdown is due to water hammer, a fast Fourier transform (FFT) analysis of the pressure signals after final closure was carried out. The result is shown in Fig. 15.
This figure shows five different peaks of different frequencies during normal shutdown. In a simple system, there should only be one peak, the water hammer traveling from turbine to reservoir and back to the turbine. However, at Roskrepp power plant there is a waterway system consisting of penstock shaft, transition from penstock shaft to unlined tunnel, sand trap, surge shaft and the unlined headrace tunnel. These structures act as obstacles for the pressure waves and reflect parts of the water hammer, resulting in multiple peaks at different frequencies.
It is seen that the two largest peaks during shutdown events have frequencies of 0.38 Hz and 0.52 Hz, which is equivalent to the time periods of 2.6 s and 1.9 s, respectively. The distance between turbine and free water surface at the surge shaft is 560 m and thus the wave propagation speed for these frequencies is 830 m/s and 1166 m/s, respectively. Both these velocities are within the normal range of water hammer propagation speed (800–1200 m/s). However, the water hammer speed is dependent on the stiffness of water and the conduit wall. In stiffer material such as steel pipe, the velocity will be higher as compared to a relatively flexible material such as the rock mass in an unlined tunnel wall. Hence, out of these two pressure waves, it is likely that the pressure wave with the higher velocity could be due to reflection from the cone area at transition between steel-lined and unlined section of the waterway. The one with lower speed could be the water hammer wave traveling through both steel-lined and unlined section between the turbine and free water surface in the surge tank.
Delayed Pore Pressure Response
There is a delayed pore pressure response in the rock mass, which can be observed during pressure transients in one of the responsive borehole BH4 as an example (Fig. 16). As one can see, during negative pressure transients, the drop in rock mass pore pressure is slower than the tunnel water pressure, which causes the rock mass pore pressure to be higher for some time. This situation occurs for the first few cycles of the pressure transient and then the pressure gradient gradually decreases as the mass oscillation attenuates.
BH1 also shows such time delay but for a shorter time period than BH4 (Fig. 14b). It is interesting to note here that the pore pressure in BH1 becomes equal to the tunnel water pressure faster than in BH4 indicating joint roughness, joint opening and infilling condition have an important role in the pore pressure behavior. After this, the pore pressure changes in BH1 are almost as fast as the tunnel water pressure during the entire period of mass oscillation and hence the pressure gradient does not change during transients. As a result, the rock mass pore pressure is always less than tunnel water pressure.