After four years of extensive work, the ROBOMINERS consortium tested their prototype (RM1) of a small-scale mining robot in Rakvere (Estonia). The second field test focused on the perception and analysis equipment of the prototype and was conducted in Mežica (Slovenia).

The RM1 prototype comprises multiple functionalities, ranging from navigation, perception, excavation, and ore transport to in-line analysis. In order to excavate ore continuously, a small-scale part-face cutter head was chosen as a suitable production tool. This cutter head was developed together with Sandvik Mining and Construction in Zeltweg, using their know-how in mechanical cutting tools and acting as a long-standing market leader in the mining machinery industry. Subsequently, this cutter head was tested extensively in the laboratory of the Conveying Technology and Design Methods (Chair of Mining Engineering and Mineral Economics) in Leoben. The tests provided detailed results of the applicability of this small-scale cutter head in different rock conditions.

The final demonstration of the RM1 prototype took place in an open-pit mine (Fig. 1) during July and August 2023 and marked a significant milestone in the project’s mission of enhancing European access to mineral raw materials and reducing import dependency. There were three basic requirements for the test sites:

  • The strength (UCS) of the host rock should be in the range of 20–40 MPa in order to meet the target KPI defined during the first stages of ROBOMINERS for the production tool.

  • Rock self-sustainability: No supporting structures are foreseen. Therefore, the host rock should be strong enough to avoid collapsing.

  • The site should provide “interesting” mineralization structures and elements that allow demonstrating geophysical sensors and mineralogy sensors.

Fig. 1
figure 1

Robominer RM1 in test pit

In the field trials that took place, the ROBOMINERS project subjected its full-scale prototype RM1 to real-world conditions, specifically targeting rock properties. The testing phase concentrated on confirming the efficacy of both the production tool module and locomotion. Control algorithms for both the production tool module and locomotion functions were honed during testing to improve their responsiveness in real-life non-ideal conditions. Demonstrations were conducted with the robot partially submerged, showcasing its capabilities:

  • Locomotion strategies

  • Production tool module operation and rock cutting

  • Cuttings transportation

  • Sensor functions

On site, these activities were accompanied by several members of the project consortium, including Michael Berner and Nikolaus A. Sifferlinger. On August 2nd 2023, the prototype was presented on site to a selected group of people including mining academics and professionals (Fig. 2).

Fig. 2
figure 2

ROBOMINERS project team in Estonia during the tests on August 2nd 2023

Further tests were conducted in an underground mine in Mežica (Slovenia). The RM1 demonstration site featured the Podzemlje Pece touristic mine, where sensor testing took place in both the underground sections of the tourist mine and the underground mine located at the TAB Žerjav industrial site, operated by GM Žerjav. During the tests, the following sensing technologies were tested and validated in a relevant environment: Standoff Laser Induced Breakdown Spectroscopy (ST-LIBS), Electrical Resistivity Tomography and Induced polarization (ERT and IP), Hyperspectral and UV fluorescence. The Žerjav mineralization exhibits disseminated sphalerite (ZnS) with traces of amorphous galena (PbS) found in dolomite and limestone host rocks. In contrast, Mežica mineralization is predominantly characterized by galena veins within a dolomitic host rock. This mineralization serves as an illustrative scenario for the potential application of the ROBOMINERS platform.

The ROBOMINERS project ended in November 2023 and eventually, a follow-up project is planned in the near future to continue this successful story.