Conclusions
-
1.
The equipment of the Hoabinh hydroelectric plant operates in conformity with the specified parameters and ensures utilization of the installed capacity in the power system of North Vietnam. Further increase in the effectiveness of utilization of the plant capacity and of its specific share in the base portion of the load graph are determined by development of the transmission line system for supply to the consumers and the interconnection with the power system of central Vietnam.
-
2.
As a result of the investigations and the introduced measures for realization of the multistage personnel training system, safe and accident-free operation has been ensured for operation of the first units under conditions of combination with construction-erection work in the underground complex of the hydroelectric plant.
Similar content being viewed by others
Additional information
Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 6, pp. 45–48, June, 1991.
Rights and permissions
About this article
Cite this article
Tul'chinskii, G.A., Khet, B.T. Experience with construction of the first units of the Hoabinh hydroelectric plant. Hydrotechnical Construction 25, 364–367 (1991). https://doi.org/10.1007/BF01423761
Issue Date:
DOI: https://doi.org/10.1007/BF01423761