The article discusses the stages of determining the fault localization in a 10-kV overhead line during the breakage of the phase wire with and without a single-phase ground short circuit and in an automated detection system for the damaged section of the overhead line of an electrical network. A comparative analysis was performed for the durations of the technological disturbances and power supply interruptions, and the damaged area under voltage and the fault localization were determined.
Similar content being viewed by others
References
A. M. Ershov, A. V. Khlopova, A. I. Sidorov, “System for protecting overhead lines with a voltage of 0.38 and 6 – 10 kV from wire breaks,” Élektr. Stantsii, No. 4, 28 – 32 (2020).
A. V. Khlopova, “Analysis of the causes of breaks in the phase wires of overhead lines with a voltage of 6 – 10 kV,” Bezopasn. Zhiznedeyat., No. 4, 38 – 43 (2018).
A. A. Kucheryavenkov, E. A. Kondratenko, “How to return light to people?” Élektroenerg. Peredacha Raspred., No. 5(38), 74 – 75 (2016).
A. A. Kucheryavenkov, E. A. Kartasheva, “Economic efficiency of the implementation of short circuit indicators in distribution networks of 6 – 35 kV,” Énergoékspert, No. 6, 52 – 53 (2014).
A. V. Khlopova, Ensuring Safety in the Event of a Break in the Phase Wire of Overhead Lines with a Voltage of 6 – 10 kV. Candidate’s Thesis. 26.05.01 [in Russian], YuUrGU, Chelyabinsk (2019).
Author information
Authors and Affiliations
Corresponding author
Additional information
Translated from Élektricheskie Stantsii, No. 4, April 2022, pp. 28 – 33. DOI: https://doi.org/10.34831/EP.2022.1089.4.004
Rights and permissions
Springer Nature or its licensor (e.g. a society or other partner) holds exclusive rights to this article under a publishing agreement with the author(s) or other rightsholder(s); author self-archiving of the accepted manuscript version of this article is solely governed by the terms of such publishing agreement and applicable law.
About this article
Cite this article
Ershov, A.M., Khlopova, A.V. & Sidorov, A.I. Stages of Restoring the Operation of a 10-kV Overhead Line during a Phase Conductor Breakage. Power Technol Eng 56, 441–446 (2022). https://doi.org/10.1007/s10749-023-01534-8