Keywords

1 Introduction and State of the Art

The contemporary manufacturing landscape is characterized by increased volatility shortened product life cycles and increased degree of product customization. Further to that the required quality by the customers has been higher than ever and therefore, manufacturers in order to stay competitive should adapt to these changes and start adopting new strategies that will allow them to achieve higher product qualities keeping costs as low as possible and at the same time respecting the due dates. The minimization of cost is a major consideration for all manufacturing industries and this is directly related with the product’s quality. In addition, the product’s quality is directly related with the inspection policy that has been selected.

One of the strategies that can take into account and provide high quality parts at low costs is called Zero Defect Manufacturing (ZDM), which has as a goal of eliminating with various ways defected parts in the production, but it is not an easy task [1]. As described in [2, 3] there are four main strategies for implementing ZDM the Detect, Prevent, Predict and Repair of a defect. The most critical is the detection strategy because all the other strategies are relying on the data collected during the detection step.

It is common that in most of the manufacturing systems the quality testing of the product is performed at the end the process chain [4]. This is happening for separating the defective parts from the acceptable in order to treat them with different way. ZDM imposes that part inspection should happen in multiple stages [5] and not only at the end of the process chain.

The detection of a defect is a very important step of the manufacturing process [6]. However, there is no clear approach of what would be the acceptable specification of the inspection points, relatively to the total processing time and total product cost. Therefore, this paper aims to develop a methodology for defining what should be the acceptable inspection characteristics in order for the manufacturers to stay competitive and be able to achieve Zero Defect Manufacturing by inspecting all of the parts.

The majority of the literature deals with the development of effective and accurate inspection and monitoring technics without concerning the implications that may have to the actual production [5]. For that reason there is the need for integrated approaches to jointly optimize, at system level, maintenance, quality and production control strategies, in order to avoid local improvements that can bring minor, or even detrimental, effects at system level [7].

Genta et al. developed a method based on which he was able to predict the probability of defect occurrence relevant to each process step and that way they could plan an effective inspection [8]. Sarkar created an economic production quantity model where the process is deteriorated based on production of defective products. To avoid the higher cost of inspection, product inspection policy was performed instead of full inspection policy where the product inspection policy was not error free [9]. Mohammadi et al. developed a mathematical model for deteriorating process representing the expected total cost to obtain the optimal solution. The aim of this research was to determine the production period length and inspection policy such that the expected total cost is minimized [10]. In Sect. 2, the mathematical formulation of the current work is presented. Then in Sect. 3, the implementation of the proposed method to an industrial case is performed and finally in the conclusion section, the paper is summarized.

2 Proposed Methodology

Currently, there are numerous of different inspecting technologies with different characteristics each, and the implementation of inspection points on every manufacturing stage is not possible due to cost and time constrains. Therefore, manufacturers need a tool that could indicate what could be the acceptable combinations between inspection time and inspection cost based on the total processing time and total product cost. This methodology should be applied to the critical points for selecting the most appropriate inspection equipment in order to be able to inspect all the products and that way guaranty 100% defect free order.

The current methodology aims to assist manufacturers in the process of designing, re-designing, or adjusting manufacturing systems to new products in order to determine what inspection equipment they need. The method is quite simple but the outcome has a significant impact to the achievement of ZDM. Two measures were used for the initialization of the process, the Estimated Product Cost (EPC) and the Estimated Production Time (EPT), which includes all the costs and all the times for the manufacturing and inspecting the product, accordingly. Both measures consists the theoretical – nominal values of these product parameters and consider only the manufacturing of the product from start to finish without any inspection. Having those parameters, we define two ratios the Inspection Time Ratio (ITR) and the Inspection Cost Ratio (ICR) that are described by formulas (1) and (2). The ratio approach selected in order to provide a relative indicator that shows how much extra time or cost is needed for the inspection having as reference the nominal values.

$$ ITR = \frac{Inspection\;Time}{EPT} $$
(1)
$$ ICR = \frac{Ispection\;Cost}{EPC} $$
(2)

ITR and ICR take values between 0 and 1. ITR is an independent value whereas the ICR includes the calculated Inspection Time. The goal is to find all the sets of the two ratios that corresponds to acceptable inspection characteristics. Those sets will be used in order to create a map of the acceptable inspection characteristics in order to inspect all the products and that way achieve Zero Defect Manufacturing.

2.1 Performance Indicators Used for the Simulation

Three different PIs were used for the comparison of the different scenarios (SC): (a) the tardiness of the order (OT), (b) the quality of the solution (OQ), measuring how many defected parts were at the end and (c) the actual product cost (PC). The PC should not be mixed with the EPC. PC is the actual product cost as it was calculated after the simulation. Equations 3, 4 and 5 present the formulas that the KPIs are calculated. Those values were normalized and weighted and summed to one value which corresponds to the quality of the solution [11, 12].

$$ OT = { \hbox{max} }\left( {DueDate - Makespan,0} \right) $$
(3)
$$ PC = \sum RawMaterialsC + \sum OperationalC $$
(4)
$$ OQ = \frac{TotalProductsMade - DefectedProducts}{TotalProductsMade} $$
(5)

3 Experimental Results

The use of the proposed method in an Industrial scenario will be described in this chapter. A dynamic scheduling tool was used for the simulation which is described in [3]. In addition, the product used for the simulations is composed out of 13 processes and the corresponding bill of processes (BoP) is shown in the right side of Table 1. The simulation was including only a part of the factory, and more specifically 10 machines, configured as “open shop” [13]. In addition, the simulation was performed for 3000 parts with a specific due date. In addition, the simulations were considering product inspection at the final manufacturing stage. The inspection parameters were defined according to the methodology presented in Sect. 2. The left side of Table 1 depicts the scenarios that were defined for the simulations with the inspection times and costs used for each one. In addition, the product under investigation has EPC = 341.2 € and EPT = 108.2 min. Having these values and using the formulas (1) and (2), we were able to calculate the corresponding Inspection times and Costs.

Table 1. Experiment inspection scenarios & product Bill of Processes (BoP)

All the scenarios were compared among each other and with a benchmark scenario (“B”) in which inspection was performed every 100 parts, but the same number of defects were introduced during the simulation. Four different set of weights were used at the performance indicators (PI), in order to demonstrate the different requirements that each manufacturer has. The results from the simulations are illustrated in Fig. 1. It can be seen that in the three out of four weight sets the quality of the benchmark scenario is lower than 0.66, only in the last weight scenario that Order Quality is not that important (0.2) benchmark is close to the best with 9.52% relative difference from the best of the set.

Fig. 1.
figure 1

Inspection scenarios and benchmark solutions quality

The next step is to use the results from the experiments, illustrated in Fig. 1 and create the maps for the acceptable inspection characteristics. For each weight set the 16 scenarios’ values were compared with the benchmark and if they were above the benchmark then this value is acceptable and should be considered to the corresponding map. The benchmark scenario is the current situation on the shop floor and the current study aims to improve the performance of the system in terms of order quality but keeping production cost and makespan as low as possible.

Then all the revealed points were put in a common graph, Fig. 2 and the area that is below the marked line depicts the acceptable inspection combinations in terms of inspection time and inspection equipment operational cost. The weight scenario with the least possibilities is the scenario in which quality is not that important. This case is not presented in Fig. 2 because only one scenario was better than the benchmark test, scenario 1, which imposes very quick and low cost inspection device.

Fig. 2.
figure 2

Inspection specification map for different criteria weights

4 Conclusions and Future Work

This paper provides a method identifying the acceptable inspection parameters in order to select the appropriate inspection equipment and efficiently inspect all the produced parts and achieve ZDM. In addition, the results were split into four categories, each category was considering different weights to the PIs. It was observed and expected, that the inspection scenarios that had low inspection time and low inspection cost, were common points to three out of four maps. It is obvious that the cheaper and the faster the inspection point the better it is, but when it comes to inspection this combination is not always the case. Therefore, manufactures need methods like the above mentioned in order to be able to decide if an inspection point would be efficient or not.

Future work will focus on the study of multiple inspection point across the manufacturing of a product and simulating the entire shop floor. Further to that, the simulation of multiple product will be investigated as well as different shop floors set ups. In this industrial case, the shop floor was set up as an “open shop” configuration.