Program Evaluation and Review Technique (PERT)

Reference work entry
DOI: https://doi.org/10.1007/978-1-4419-1153-7_200653

A method for planning and scheduling a project which models uncertainties in activity by using optimistic, likely and pessimistic time estimates for each activity. PERT evolved when the U.S. Navy was developing a system to plan and coordinate the Polaris missile program (Malcolm et al. 1959).