The engineering solutions for PGU-200 MW unit, the electrical distribution system layout, and the results of implementing the SPPA-T3000 control system are presented. The results of performance adjustment confirm that the requirements by the System Operator of the Unified Power System are met. The organizational structure for operating personnel is described.
Similar content being viewed by others
Author information
Authors and Affiliations
Additional information
Translated from Élektricheskie Stantsii, No. 2, February 2014, pp. 16 – 23.
Rights and permissions
About this article
Cite this article
Chugin, A.V., Tsvetkov, M.S., Kostyuk, R.I. et al. Experience of Implementing a PGU-200 MW Two-Boiler One-Turbine Unit at the South-West CHP. Power Technol Eng 48, 140–146 (2014). https://doi.org/10.1007/s10749-014-0498-6