Abstract
In July 2011, a PGU-410 combined-cycle power plant was commissioned at the Srendeuralsk district power station owned by Enel OGK-5. The main equipment of this power plant includes an MS9001FB gas turbine unit (produced by GE Energy Power Plant Systems, the United States), a heat recovery boiler (produced by Nooter/Ericsen, the United States), and a >Skoda KT-140-13.3 two-cylinder condensing and cogeneration turbine with steam reheating. In 2011–2012, specialists of the All-Russia Thermal Engineering Institute carried out thermal tests of this power plant in a wide range of loads and under different external conditions. The results from thermal tests of the MS9001FB gas turbine unit are presented and analyzed. The actual indicators of the gas turbine unit and its elements are determined and their characteristics are constructed.
Similar content being viewed by others
References
ISO/DIS 2314. Gas Turbines-Acceptance Tests (MOD).
S. L. Rivkin, Thermodynamic Properties of Air and Fuel Combustion Products (Energoatomizdat, Moscow, 1984) [in Russian].
G. G. Ol’khovskii, N. E. Tuz, Yu. A. Radin, and L. A. Mikheev, “Thermal tests of a 255-MW gas turbine unit operating as part of a single-shaft combined-cycle power plant,” Elektr. Stn., No. 5 (2013).
Author information
Authors and Affiliations
Additional information
Original Russian Text © G.G. Ol’khovskii, Yu.A. Radin, V.A. Mel’nikov, N.E. Tuz, A.V. Mironenko, 2013, published in Teploenergetika.
Rights and permissions
About this article
Cite this article
Ol’khovskii, G.G., Radin, Y.A., Mel’nikov, V.A. et al. Thermal tests of the 9FB gas turbine unit produced by general electric. Therm. Eng. 60, 607–612 (2013). https://doi.org/10.1134/S0040601513090097
Published:
Issue Date:
DOI: https://doi.org/10.1134/S0040601513090097