Advertisement

Ujina Floating Ferry Pier and Kan-On Floating Breakwater, Japan

  • Tadasu KusakaEmail author
  • Shigeru UedaEmail author
Chapter
Part of the Ocean Engineering & Oceanography book series (OEO, volume 3)

Abstract

This chapter describes the construction of the Ujina Floating Ferry Pier and Kan-on floating breakwater. This Ferry Pier was set up at Hiroshima Bay in Japan in 1993. At 150 m in length, 30 m in width, and 4 m in height, it is the largest in Japan. Five prestressed concrete pontoons (30 m in length, 30 m in width, and 4 m in height) were fabricated on land and towed to the pier site for assembly to form the floating pier with a total length of 150 m. The Kan-on Floating Breakwater was set up at Hiroshima Bay in 1994. The breakwater is one of the world's largest classes of floating breakwaters made from reinforced concrete and steel plates. Three units of the breakwaters measure 97.8 m in length, 20.0 m in width, and 2.5 m in height while another two units are 70.75 m long, 21.0 m wide, and 2.5 m high.

Keywords

Steel Plate Mooring System Floating Structure Cruise Ship Prestressed Concrete 
These keywords were added by machine and not by the authors. This process is experimental and the keywords may be updated as the learning algorithm improves.

Notes

Acknowledgments

A part of the document of the Project of Ujina Floating Ferry Pier was provided by the Hiroshima Port and Airport Office, Ministry of Land, Infrastructure, Transport and Tourism, and a part of the document regarding the Project of the Kan-on Floating Breakwater was provided by the Hiroshima Port and Harbor Promotion Office, Hiroshima Prefectural Government. The authors wish to express their sincere appreciation to Mr. Hideyuki Hokimoto (from Chuden Engineering Consultants Co., Ltd.) who provided much advice on both projects.

References

  1. Fujita, K. & Kusaka, T. (1977). Two dimensional floating breakwater with energy dispersion. Proceedings of 24th Coastal Engineering in Japan, JSCE (pp. 285–289) (in Japanese).Google Scholar
  2. Fukuda, K., Takamaru, T., Yoshida, H., Kusaka, T., et al. (1996). Breakwater efficiency and influence of river current due to floating breakwater settled near river mouth. Annual Journal of Civil Engineering in the Ocean, JCSE, 12, 195–200. (in Japanese).CrossRefGoogle Scholar
  3. Sakurai, T. (1994). Construction of floating Pier at Ujina Region in Hiroshima Port. Proceedings of the International Workshop on Floating Structures in Coastal Zone (pp. 22.1–22.11).Google Scholar

Copyright information

© Springer Science+Business Media Singapore 2015

Authors and Affiliations

  1. 1.Former Chuden Engineering Consultants Co. LtdHigashi-HiroshimaJapan
  2. 2.Institute of Environment InformationYokohamaJapan