Abstract
For the description and solution of many problems in the area of operations research for which graph models have turned out to be an appropriate tool if problem data are fixed and known to enlarge the possibilities of application it is desirable to find corresponding formulations if variation of data has to be taken into consideration. With regard to this view-point problems including stochastic variation of data are of special interest and some efforts in combining stochastic and graphtheoretical aspects are cited in the references omitting, however, the large number of contributions using tools from reliability theory and stochastic programming(except [3] [15]). Of course, maximum flow and shortest path network formulations belong to the problems for which stochastic generalizations were considered (see e.g. [6][9],[25]), however, stochastic versions of project planning models seem to be mostly dealt with in this context. Defining a project to be a finite set of activities A = {a1,…,an} ≠ ∅ with an irreflexive, asymmetric, transitive ordering relation σ ⊂ A×A (which allows representation as an adjacency-relation on the arc-set of a graph at least after introducing dummy activities, see e.g [1] [20] and nonnegative activity durations the problem is to determine the project duration which is yielded by maximizing over the sums of the durations of those activities which form maximal chains(with respect to σ). Assuming stochastic activity durations an intuitive idea is to replace the stochastic variables by their expected values and solve the resulting deterministic problem (using CPM), thus providing a rough estimate for the project duration mean. For this PERT-approach [18] several improvements have been suggested (see [4] [5] [10] [16] [22]). This paper gives a description of a class of estimation possibilities containig some estimators known from the literature as special cases.
Access this chapter
Tax calculation will be finalised at checkout
Purchases are for personal use only
Preview
Unable to display preview. Download preview PDF.
References
Bruns,M./R.Kaerkes:Zur Einbettung strikter Halbordnungen in Netzrelationen. ORV 7(1969) 71–82.
Burt,J.M./D.P.Gavert/M.Perlas:Simple stochastic network: Some problems and procedures.NRLQ 4(1970)439–459.
Charnes,A./W.W.Cooper/G.L.Thompson:Critical path analysis via chance constrained and stochastic programming. J.ORSA 12(1964)460–470.
Clingen,C.T.:A modification of Fulkerson’s PERT algorithm. J.ORSA 12(1964)629–632.
Elmaghraby,S.E.:On the expected duration of PERT-type networks. Manag.Sc. 13(1967)299–306.
Evans,J.R.:Maximum flows in probabilistic graphs-The discrete case. Networks 6(1976)161–183.
Fix,W./K.Neumann/U.Steinhardt:Introduction to time and cost scheduling of decision activity networks. Discussion paper Nr.75,Inst.Wirtschaftstheorie u. Operations Research, Universität Karlsruhe (1977).
Frank,H.: Optimum locations on graphs with correlated normal demands J.ORSA 15 (1967) 552–557.
Frank,H. : Shortest paths in probabilistic graphs. J.0RSA 17(1969)583–599.
Fulkerson,D.R.: Expected critical path lengths in PERT networks J.ORSA 10(1962)808–817.
Gaul,W.:Eine Klasse von Schätzern bei stochastischen Projektplanungsmodellen working paper (1977).
Golenko,D.I.: Statistische Methoden der Netzplantechnik. Teubner Verlag Stuttgart (1972).
Kaerkes,R:Netzplantheorie. Proc.OR 3(1973)107–121.
Kaerkes,R. Ergebnisse der Theorie der Netzpläne mit stochastisch verteilten Vorgangsdauern.Proc.OR 5(1975) 201–210.
Leondes,C.T. /R.K.Nandi:Capacity expansion in convex cost networks with uncertain demand J.ORSA 23(1975) 1172–1178.
Lindsey II,J.H.:An estimate of expected critical-path length in PERT networks.J.ORSA 20(1972) 800–812.
Lohse,D.: Eine spezielle Vorgangsdauerverteilung zur Netzplananalyse durch Simulation.ZOR 20(1976)115–124.
Malcolm,D.G./J.H.Roseboom/C.E.Clark/W.Fazer:Application of a technique for research and development program evaluation J.ORSA 7 (1959)646–669
Martin,J.J.: Distribution of the time through a directed acyclic network J.ORSA 13(1965)46–66.
Möhring,R.:Graphentheoretische Repräsentation endlicher Ordnungen.Proc.OR 3(1973)143–152.
Neumann,K.:Operations Research Verfahren III.Carl Hanser Verlag München (1975).
Robillard,P./M.Trahan:Expected completion time in PERT- networks.J.ORSA 24(1976)177–182.
van Slyke,R.M:Monte Carlo methods and the PERT problem. J.ORSA 11(1963)839–860.
van Slyke,R.M:Stochastic aspects of networks. Networks 5(1975)97–100.
Wollmer,R.D.: Stochastic sensitivity analysis of maximum flows and shortest route networks. Manag.Sc. 14(1968) 551–564.
Author information
Authors and Affiliations
Editor information
Editors and Affiliations
Rights and permissions
Copyright information
© 1978 Springer-Verlag Berlin Heidelberg
About this paper
Cite this paper
Gaul, W. (1978). Remarks on stochastic aspects on graphs. In: Henn, R., Korte, B., Oettli, W. (eds) Optimization and Operations Research. Lecture Notes in Economics and Mathematical Systems, vol 157. Springer, Berlin, Heidelberg. https://doi.org/10.1007/978-3-642-95322-4_11
Download citation
DOI: https://doi.org/10.1007/978-3-642-95322-4_11
Publisher Name: Springer, Berlin, Heidelberg
Print ISBN: 978-3-540-08842-4
Online ISBN: 978-3-642-95322-4
eBook Packages: Springer Book Archive