Rail Ground-Borne Noise and Vibration Prediction Uncertainties

  • Conference paper
  • First Online:
Noise and Vibration Mitigation for Rail Transportation Systems

Part of the book series: Notes on Numerical Fluid Mechanics and Multidisciplinary Design ((NNFM,volume 139))

Abstract

On projects where there is limited or only high-level information relating to source, path and receiver components, the uncertainty associated with ground-borne noise and vibration predictions can be large and prediction uncertainties of up to 10 dB(A) have been reported and sometimes applied as a safety factor (engineering margin) on underground railway projects. However, this simplistic and somewhat ad hoc approach is not well founded quantitatively. Furthermore, during the detailed design stage of projects, such large safety factors can be very costly in terms of the required mitigation measures. The uncertainty associated with some modelling input parameters can be quantified and minimised via repeated measurements, however many other parameters and the uncertainty associated with predictions can only be established via published data or engineering judgement. On a recent underground railway tunnel project, a quantitative approach was used with the aim of improving estimates of prediction uncertainties and to better advise the design team of the level of design risk associated with the predictions. Field measurements were also utilised to reduce the uncertainty associated with the ground-borne noise and vibration predictions. Prediction uncertainties were determined on the basis of the methodologies described in the ‘Guide to the expression of uncertainty in measurement’ (GUM) and by establishing an uncertainty budget for each part of the ground-borne noise and prediction process (source, path and receiver). For each modelling input parameter (or source of uncertainty), an estimate of the likely range (minimum and maximum) of values was made on the basis of measurement results, published data and engineering judgement. This paper presents the uncertainty budget calculations where for each parameter, an estimate of the standard uncertainty (uncertainty contribution) has been made on the basis of the half range, the probability distribution and associated distribution divisor. This paper focuses on the results and outcomes at a representative receiver above the railway tunnel which was selected to establish and illustrate the uncertainties in the modelling predictions. The combined standard uncertainty at this location was calculated at 2.5 dB(A) for the source parameters, 2.0 dB(A) for the path parameters and 2.2 dB(A) for the receiver parameters. The combined standard uncertainty for the whole prediction path was calculated to be 3.9 dB(A). A Monte Carlo simulation with 100,000 iterations was also undertaken to provide an independent calculation of the combined standard uncertainty.

In summary, the prediction uncertainty analysis found:

  • the predicted ground-borne noise levels are expected to lie within ±3.9 dB(A) [±1σ] of the mean with 68% confidence;

  • by adding an engineering margin of 1σ or 3.9 dB(A) to the predicted noise level, the probability of the actual (or true) noise level being less than the predicted noise level is 84%, or conversely, the risk that the actual noise level will be higher than the predicted noise level is 16%; and

  • for a 90 and 95% confidence that the actual (or true) noise level will be less than the predicted noise level, the following engineering margins should respectively be added to the modelling results: 5.0 and 6.4 dB(A).

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 169.00
Price excludes VAT (USA)
  • Available as EPUB and PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 219.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info
Hardcover Book
USD 219.99
Price excludes VAT (USA)
  • Durable hardcover edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

References

  1. International Standards, ISO 14837-1:2005—Mechanical vibration—Ground-borne noise and vibration arising from rail systems (2005)

    Google Scholar 

  2. ISO/IEC Guide 98-3, Uncertainty of measurement—Part 3: Guide to the expression of uncertainty in measurement, ISBN 92-67-10188-9, 1st Edition 1993, corrected and reprinted 1995 (GUM:1995)

    Google Scholar 

  3. Craven, N.J., Kerry, G.: School of Computing, Science & Engineering, The University of Salford. A Good Practice Guide on the Sources and Magnitude of Uncertainty Arising in the Practical Measurement of Environmental Noise Edition 1a—May 2007

    Google Scholar 

  4. International Standards, ISO 3381-2005 Railway applications—Acoustics—Measurement of noise inside railbound vehicles, ISO (2005)

    Google Scholar 

  5. Hassan, O.A.B.: Train-Induced Ground-borne Vibration and Noise is Buildings. Multi-Science Publishing Co., Ltd., Essex (2006)

    Google Scholar 

  6. Nelson, P.: Chapter 16 Low Frequency Noise and Vibration from Trains (Remington, Kurzweil and Towers), in Transportation Noise Reference Book, Butterworths (1987)

    Google Scholar 

  7. Transit Noise and Vibration Impact Assessment, United States Federal Transit Association (2006)

    Google Scholar 

  8. Walpole, R., Myers, H.: Probability and Statistics for Engineers and Scientists (5th ed.)—Appendix A.3, Macmillan Publishing Company (1993)

    Google Scholar 

  9. International Standards, ISO 3095:2005 Railway applications—Measurement of noise emitted by railbound vehicles (2005)

    Google Scholar 

  10. Hunt, H., Hussain, M.: Accuracy, and the prediction of ground vibration from underground railways, 5th Australasian Congress on Applied Mechanics, Australia (2007)

    Google Scholar 

  11. KTE Rail Tunnel Project–Hong Kong—http://www.epd.gov.hk/eia/register/report/eiareport/eia_1842010/EIA/html/8%20-%20GB%20Noise.htm. Available online—accessed 4 July 2016

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to C. Weber .

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2018 Springer International Publishing AG, part of Springer Nature

About this paper

Check for updates. Verify currency and authenticity via CrossMark

Cite this paper

Weber, C., Karantonis, P. (2018). Rail Ground-Borne Noise and Vibration Prediction Uncertainties. In: Anderson, D., et al. Noise and Vibration Mitigation for Rail Transportation Systems. Notes on Numerical Fluid Mechanics and Multidisciplinary Design, vol 139. Springer, Cham. https://doi.org/10.1007/978-3-319-73411-8_22

Download citation

  • DOI: https://doi.org/10.1007/978-3-319-73411-8_22

  • Published:

  • Publisher Name: Springer, Cham

  • Print ISBN: 978-3-319-73410-1

  • Online ISBN: 978-3-319-73411-8

  • eBook Packages: EngineeringEngineering (R0)

Publish with us

Policies and ethics