Abstract
Analysis techniques based on statistical distributions can provide predictive metrics from historically observed trends in a program’s performance. The Rayleigh distribution is a continuous probability distribution that has been historically demonstrated to accurately model large-scale research and development and software development projects. This distribution is the basis of the Rayleigh model, whose shape works particularly well for forecasting software development projects because it can account for the slow ramp-up, peak spending as complexity increases, and a gradual tail-off toward completion. The Rayleigh model relies on accurate and consistent cost and schedule data to fit the distribution, but, because the model is used to fit data that are already collected through traditional project management techniques, there is relatively low additional effort required to realize program benefits, such as early warning of cost overruns and schedule slip. In this study, the predictive ability of the Rayleigh model in evaluating the spending profiles of civil agency IT development programs were evaluated. Using software developed previously by CNA, one completed and one ongoing IT program were analyzed using the Rayleigh model. The predictive ability of the Rayleigh model to estimate final program cost was compared to that of traditional earned value management system (EVMS) methods, with the former found to show earlier and consistent, but more exaggerated, warning indications of cost and schedule slippage. Overall, the Rayleigh model has potential to provide added value to IT program management, especially toward the beginning of a project, when used alongside traditional EVMS metrics.
Access this chapter
Tax calculation will be finalised at checkout
Purchases are for personal use only
Abbreviations
- α :
-
Time parameter
- C(t):
-
Cumulative cost
- D :
-
Cost parameter
- e :
-
Napier’s constant
- t :
-
Time
References
Patanakul, P., Kwak, Y. H., Zwikael, O., & Liu, M. (2016). What impacts the performance of large-scale government projects? International Journal of Project Management, 34(3), 452–466. https://doi.org/10.1016/j.ijproman.2015.12.001
U.S. Government Accountability Office. (2017). High-Risk Series: Progress on Many High-Risk Areas, While Substantial Efforts Needed on Others. GAO-17-317. Report to Congressional Committees. 15 Feb 2017. Washington, D.C.: U.S. Government Publishing Office.
U.S. Office of Inspector General (2014). FAA lacks the metrics and data needed to accurately measure the outcomes of its controller productivity initiatives. AV-2014-062. 9 July 2014. Washington D.C.: U.S. Government Publishing Office.
U.S. Office of Inspector General (2012). The success of FAA’s long-term plan for air traffic facility realignments and consolidations depends on addressing key technical, financial, and workforce challenges. AV-2012-151. 17 July 2012. Washington D.C.: U.S. Government Publishing Office.
U.S. Government Accountability Office. (2012). Air traffic control modernization: Management challenges associated with program costs and schedules could hinder NextGen implementation. GAO-12-223. Report to Congressional Committees. 16 Feb 2012. Washington, D.C.: U.S. Government Publishing Office.
Christle, G. E., & Birchler, D. A. (2006). Strategic management system for navy acquisition (p. 50). Alexandria, VA: CNA Corporation.
Earned Value Management System, 48 C.F.R. § 34.2 2018.
den Dekker, A. J., & Sijbers, J. (2014). Data distributions in magnetic resonance images: A review. Physica Medica, 30(7), 725–741. https://doi.org/10.1016/j.ejmp.2014.05.002
Ahmadi, H. (2017). A mathematical function for the description of nutrient-response curve. PLoS One, 12(11), e0187292. https://doi.org/10.1371/journal.pone.0187292
Davis, D., Christle, G., & Abba, W. (2009). Using the Rayleigh Model to assess future acquisition contract performance and overall contract risk. Alexandria, VA: CNA Corporation.
Putnam, L. H. (1978). A general empirical solution to the macro software sizing and estimating problem. IEEE Transactions on Software Engineering, SE-4(4), 345–361.
Watkins III, H. (1982). An application of Rayleigh curve theory to contract cost estimation and control. Naval Postgraduate School. Monterey, California.
Abernethy, T. S. (1984). An application of the Rayleigh distribution to contract cost data. Naval Postgraduate School. Monterey, California.
Lee, D., Hogue, M., & Hoffman, D. (1993). Time histories of expenditures for defense acquisition programs in the development phase. In Annual Meeting of the International Society for Parametric Analysis.
Acknowledgment
The authors would like to thank Julianne Nelson, Ph.D., for providing background information on the use and implementation of the XCASA tool to generate Rayleigh models for the analysis as well as Maryann Shane, Ph.D., for providing additional review of the paper.
Author information
Authors and Affiliations
Corresponding author
Editor information
Editors and Affiliations
Rights and permissions
Copyright information
© 2019 Springer Nature Switzerland AG
About this paper
Cite this paper
Yang, R. et al. (2019). Application of the Rayleigh Model to Predict Information Technology Program Cost and Schedule Performance. In: Adams, S., Beling, P., Lambert, J., Scherer, W., Fleming, C. (eds) Systems Engineering in Context. Springer, Cham. https://doi.org/10.1007/978-3-030-00114-8_15
Download citation
DOI: https://doi.org/10.1007/978-3-030-00114-8_15
Published:
Publisher Name: Springer, Cham
Print ISBN: 978-3-030-00113-1
Online ISBN: 978-3-030-00114-8
eBook Packages: Intelligent Technologies and RoboticsIntelligent Technologies and Robotics (R0)