On June 26, 1980, Unit One of the E.I. Hatch Nuclear Plant experienced a reactor scram coincident with a temporary loss of the feedwater system and the high pressure coolant systems. The unit transient response is presented in order to highlight the conditions faced by the control room operators.

Findings of followup investigations and critiques are described. The effectiveness of the resulting corrective measures are demonstrated by the description of the subsequent plant operating experience.


Preventive Maintenance Throttle Valve Steam Line Quick Start Turbine Speed 
These keywords were added by machine and not by the authors. This process is experimental and the keywords may be updated as the learning algorithm improves.


Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

Copyright information

© Springer Science+Business Media New York 1984

Authors and Affiliations

  • Bob Keck
    • 1
  1. 1.Plant E.I. HatchGeorgia Power CompanyBaxleyUSA

Personalised recommendations