The Podilskyi Arch bridge is crossing the river Dnieper in center of Kiev and is part of a 7.4 km long link which connects the center of Kiev with the “sleeping district” on the left bank of the river. The bridge has a main span of 344 m intended for six lanes of vehicles in the top level and two metro lines in the bottom level plus large diameter water pipes. The bridge is of steel, except of the reinforced concrete bases of the lower parts of the arches.

The draft design works began in 1991 and in 2005 parallel design and construction work started. Due to the financial crisis in the Ukraine, the work was interrupted for several years but construction recommenced in 2018 and the bridge shall be completed at the end of 2020.

Keywords

Arch bridge River Dnieper Steel and concrete structure Planning Design Material Installation Tensioning Cables Corrosion protection Galfan Bezinal 3000 

References

  1. 1.
    SNiP 2.05.03-84* Bridges and pipes. Design standards. Moscow (1998)Google Scholar
  2. 2.
    Korniiev, M.M., Fuks, G.B.: Patent SU 1158650 A Upper structure of the railway bridge track, 30 May 1985Google Scholar
  3. 3.
    Korniiev, M.M.: Steel Bridges, vol. 2. Chapter 7, Calculations of fatigueGoogle Scholar
  4. 4.
    Korniiev M.M.: Steel Bridges, vol. 3. Chapter 10, Orthotropic platesGoogle Scholar

Copyright information

© Springer Nature Switzerland AG 2020

Authors and Affiliations

  • Michael Korniiev
    • 1
  • Vladimir Bolikov
    • 2
  • Friedhelm Eric Rentmeister
    • 3
    Email author
  1. 1.KievstroyprojectKievUkraine
  2. 2.PSC “Plant” Kuznya on RybalskyKievUkraine
  3. 3.Bridon-Bekaert – The Ropes GroupGelsenkirchenGermany

Personalised recommendations