The Use and Non-use of Time in New Construction of Residential Buildings: The Case of Sweden

  • Conference paper
  • First Online:
Proceedings of the 17th International Symposium on Advancement of Construction Management and Real Estate
  • 2039 Accesses

Abstract

There is a continuous debate on costs in construction. Customers are complaining on the high costs, while suppliers are focusing on cutting costs. Experiences from successful companies in other industries show another logical way for lowering costs. By prioritizing reduction of errors and other disturbances there is easier to foresee the processes as well as benchmarking processes in order to shorten lead-times. Shorter lead-times lead to lower costs. While costs, defects and delays are discussed among academics, the use of available time seems to be less covered in research papers. This paper aims to describe how time is used and not used in construction. Examples from Swedish construction are given. Some examples from Chinese construction projects are given as a benchmark. One perspective on how time is used concerns lead-times from briefing to final delivery. A second perspective concerns the fact that work is only going on 40 h a week. A third perspective concerns to what extent resources, here human resources and equipment, are used. The main argument is to focus more on the use and non-use of time as a way to improve construction.

This is a preview of subscription content, log in via an institution to check access.

Access this chapter

Chapter
USD 29.95
Price excludes VAT (USA)
  • Available as PDF
  • Read on any device
  • Instant download
  • Own it forever
eBook
USD 169.00
Price excludes VAT (USA)
  • Available as EPUB and PDF
  • Read on any device
  • Instant download
  • Own it forever
Softcover Book
USD 219.99
Price excludes VAT (USA)
  • Compact, lightweight edition
  • Dispatched in 3 to 5 business days
  • Free shipping worldwide - see info

Tax calculation will be finalised at checkout

Purchases are for personal use only

Institutional subscriptions

References

  1. Josephson PE, Lindström J (2010) Kvalitetsbristkostnader i byggandet-lärdomar från annan industri. Chalmers University of Technology

    Google Scholar 

  2. Josephson PE, Hammarlund Y (1999) The causes and costs of defects in construction: a study of seven building projects. Automat Constr 8(6):681–687

    Article  Google Scholar 

  3. Love PED, Li H (2000) Quantifying the causes and costs of rework in construction. Constr Manag Econ 18(4):479–490

    Article  Google Scholar 

  4. Hwang B-G, Thomas ST, Haas CT, Caldas CH (2009) Measuring the impact of rework on construction cost performance. J Constr Eng Manag 135(3):187–198

    Article  Google Scholar 

  5. Chan DW, Kumaraswamy MM (1997) A comparative study of causes of time overruns in Hong Kong construction projects. Int J Proj Manag 15(1):55–63

    Article  Google Scholar 

  6. Kaming P, Olomolaiye P, Holt G, Harris F (1997) Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Constr Manag Econ 15:83–94

    Article  Google Scholar 

  7. Assaf SA, Al-Hejji S (2006) Causes of delay in large construction projects. Int J Proj Manag 24:349–357

    Article  Google Scholar 

  8. Hixon (1995) Activity-based management: its purpose and benefits. Manag Account: Mag Chart Manag Account 73(6):30–33

    Google Scholar 

  9. Formoso CT, Soibelman L, De Cesare CM, Isatto EL (2002) Material waste in buildingindustry: maincauses and prevention. J Constr Eng Manag 128(4):316–325

    Article  Google Scholar 

  10. Womack, JP, Jones, DT (1996) Lean thinking: banish waste and create wealth in your corporation. Simon and Schuster

    Google Scholar 

  11. Strandberg J, Josephson P-E (2005) What do construction workers do?Direct observations in housing projects. In: Proceedings of 11th Joint CIB international symposium combining forces advancing facilities management and construction through innovation, Helsinki 13–16 June 2005, Section 3, pp 184–193

    Google Scholar 

  12. Josephson PE, Björkman L, Kling R (2010) Arbetstidens användning vid VVS-montage-en fråga om struktur och ledarskap

    Google Scholar 

  13. Ekstedt E, Wirdenius H (1995) Renewal projects: sender target and receiver competence in ABB “T50” and Skanska “3T”. Scand J Manag 11(4):409–421

    Article  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Per-Erik Josephson .

Editor information

Editors and Affiliations

Rights and permissions

Reprints and permissions

Copyright information

© 2014 Springer-Verlag Berlin Heidelberg

About this paper

Cite this paper

Josephson, PE., Mao, C. (2014). The Use and Non-use of Time in New Construction of Residential Buildings: The Case of Sweden. In: Wang, J., Ding, Z., Zou, L., Zuo, J. (eds) Proceedings of the 17th International Symposium on Advancement of Construction Management and Real Estate. Springer, Berlin, Heidelberg. https://doi.org/10.1007/978-3-642-35548-6_66

Download citation

Publish with us

Policies and ethics