Limestone quarry production planning for consistent supply of raw materials to cement plant: A case study from Indian cement industry with a captive quarry

  • Mineral Mining Technology
  • Published:
Journal of Mining Science Aims and scope

Abstract

A long term production planning of limestone quarry is presented to supply consistent quantity and quality of limestone to a cement plant. A case study from Indian cement industry is presented where the cement plant has a captive limestone quarry. The objectives of this study are: (a) to investigate how long the limestone quarry can alone supply the desire quality and quantity materials to the cement plant; and (b) to investigated the possibility of extending the quarry life by utilizing some quantity of the limestone from the different source and blending that limestone with the limestone from the quarry to achieve the target quality and quantity of the cement plant. These objectives are achieved by generating the production sequencing of the mining blocks using a sequential branch-and-cut algorithm. The results revealed that up to 15 years, the existing quarry alone can serve the cement plant. If certain quantity of limestone can be brought from the other sources, the life of the study quarry is significantly improved. The life of the quarry increased from 15 years to 85 years. The study also helps to calculate the desire quality of the limestone that will be brought from other sources throughout the life of the quarry.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  1. Ingram, K.D. and Daugherty, K.E., A Review of Limestone Additions to Portland Cement and Concrete, Cement and Concrete Composites, 1991, vol. 13, no. 3.

  2. Hewlett, P., Lea’s Chemistry of Cement and Concrete, Butterworth-Heinemann, 2004.

    Google Scholar 

  3. Asad, M.W.A., Development of Optimum Blend/Minimum Cost Scheduling Algorithm for Cement Quarry Operations, Ph.D. Dissertation, Colorado School of Mines, USA, 2001.

    Google Scholar 

  4. Kathal, K.K. and Mukherjee, M.K., Waste Management: Utilization of Fly Ash in Optimization of Raw Mix Design for the Manufacture of Cement, Journal of Mines, Metals, and Fuels, 1999.

    Google Scholar 

  5. Austin, G.T., Shreve’s Chemical Process Industries, New York: McGraw Hill, 1984.

    Google Scholar 

  6. Lerchs, H. and Grossmann, I.F., Optimum Design of Open Pit Mines, Canad. Inst. Mining Bull., 1965, vol. 58.

  7. Picard, J.C., Maximum Closure of a Graph and Applications to Combinatorial Problems, Management Sc., 1976, vol. 22.

  8. Gershon, M., Heuristic Approaches for Mine Planning and Production Scheduling, Int. Journal of Mining and Geological Engineering, 1987, vol. 5.

  9. Caccetta, L., Kelsey, P., and Giannini, L.M., Open Pit Mine Production Scheduling, A.J. Basu, N. Stockton, and D. Spottiswood (Eds.), Computer Applications in the Minerals Industries Int. Symp. (3rd Regional APCOM), Austral. Inst. Min. Metall. Publication Series 5 (1998).

    Google Scholar 

  10. Dagdelen, K. and Johnson, T.B., Optimum Open Pit Mine Production Scheduling by Lagrangian Parameterization, Proc. 19th APCOM Symp. of the Society of Mining Engineers (AIME), 1986.

    Google Scholar 

  11. Francois-Bongarcon, D.M. and Guibal, D., Parametrization of Optimal Designs of an Open Pit Beginning of a New Phase of Research, Trans. SME, AIME 274, 1984.

    Google Scholar 

  12. Whittle, J., Open Pit Optimization, Surface Mining, 2nd Edition, AMIE, 1990.

    Google Scholar 

  13. Tolwinski, B. and Underwood, R., A Scheduling Algorithm for Open Pit Mines, IMA Journal of Mathematics Applied in Business and Industry, 1996, vol. 7.

  14. Caccetta, L., Giannini, L.M., and Kelsey, P., Application of Optimization Techniques in Open Pit Mining, Proc. 4th Int. Conf. Optimization Techniques and Applications (ICOTA’98), 1998.

    Google Scholar 

  15. Gershon, M., Mine Scheduling Optimization with Mixed Integer Programming, Mining Engineering, 1983, vol. 35.

  16. Asad, M.W.A., Multi-Period Quarry Production Planning through Sequencing Techniques and Sequencing Algorithm, J. Min. Sci., 2008, vol. 44, no. 2, pp. 206–217.

    Article  Google Scholar 

  17. Asad, M.W.A., Implementing a Blending Optimization Model for Short-Range Production Planning of Cement Quarry Operation, J. Min. Sci., 2010, vol. 46, no. 5, pp. 525–535.

    Article  Google Scholar 

  18. Modiri, M., Rabbani, S.M., Gharehbolagh, H.H., Influence of Fuzzy Goal Programming in Production Optimization Case Study: Cement Industry, Journal of Industrial Engineering, 2010, vol. 6.

  19. Dikos, G. and Spyropoulou, S., Supply Chain Optimization and Planning in Heracles General Cement Company, Interfaces, 2013, vol. 43, no. 4.

  20. Rehman, S., Asad, M.W.A., and Khattak, I., A Managerial Solution to Operational Control of the Raw Materials Blending Problem in Cement Manufacturing Operations, Proc. CICM–1, Lahore, Pakistan, 2008.

    Google Scholar 

  21. Goovaerts, P., Geostatistics for Natural Resources Evaluation, Applied Geostatistics Series, New York: Oxford University Press, 1998.

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Sk. Md. Equeenuddin.

Additional information

The article is published in the original.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Joshi, D., Chatterjee, S. & Equeenuddin, S.M. Limestone quarry production planning for consistent supply of raw materials to cement plant: A case study from Indian cement industry with a captive quarry. J Min Sci 51, 980–992 (2015). https://doi.org/10.1134/S1062739115050174

Download citation

  • Received:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1134/S1062739115050174

Keywords

Navigation