Abstract
An automated process control system is developed and commissioned at Russia’s first thermal power station equipped with combined-cycle plants built around small-capacity gas turbine units. The automated process control system is made as a unified direct digital control system constructed using the SIMATIC PCS7 PS software system and local control systems integrated into it.
Similar content being viewed by others
Author information
Authors and Affiliations
Additional information
Original Russian Text © V.G. Ivanov, I.I. Kuryleva, K.A. Molchanov, N.A. Romanov, V.V. Ivanov, 2008, published in Teploenergetika.
Rights and permissions
About this article
Cite this article
Ivanov, V.G., Kuryleva, I.I., Molchanov, K.A. et al. The development and commissioning of an automated process control system at the sochi thermal power station. Therm. Eng. 55, 1044–1051 (2008). https://doi.org/10.1134/S0040601508120100
Published:
Issue Date:
DOI: https://doi.org/10.1134/S0040601508120100