The procedures are proposed for determining the parameters and sequence of longitudinal mining inclined deposits by blocks to ensure the rational regime of stripping and dump operations. It is shown that optimization of mining-geometrical parameters of working and dump zones in quarry can increase the internal dump capacity by 10-15%.
Similar content being viewed by others
REFERENCES
V. I. Cheskidov, “Sequence of mining flat and inclined coal seams with overburden placing in internal dumps,” in: Author's Abstr. Dis. Cand. Tech. Sci., Novosibirsk (1999).
A. A. Zaitseva, “Optimization of bank formation in quarrying with division into blocks,” Fiz.-Tekh. Probl. Razrab. Polezn. Iskop., No. 5 (1996).
E. I. Vasil'ev, A. A. Zaitseva, and V. I. Cheskidov, “Mining regime stabilization in working inclined deposits by blocks,” Fiz.-Tekh. Probl. Razrab. Polezn. Iskop., No. 6 (1999).
V. V. Rzhevskii, Opencast Mining. Part I [in Russian], Nedra, Moscow (1985).
V. G. Zoteev, A. V. Frolov, N. A. Voroshilova, et al., “Experience of high dumping into inundated quarry space by bulldozer,” Gorn. Zh., No. 10 (1977).
Author information
Authors and Affiliations
Rights and permissions
About this article
Cite this article
Zaitseva, A.A. Influence of Parameters and Sequence of Mining Inclined Deposit by Blocks on the Internal Dump Capacity. Journal of Mining Science 39, 482–491 (2003). https://doi.org/10.1023/B:JOMI.0000029312.22669.09
Issue Date:
DOI: https://doi.org/10.1023/B:JOMI.0000029312.22669.09