Problem space search algorithms for resource-constrained project scheduling

  • Published:
Annals of Operations Research Aims and scope Submit manuscript

Abstract

The Resource-Constrained Project Scheduling (RCPS) problem is a well known and challenging combinatorial optimization problem. It is a generalization of the Job Shop Scheduling problem and thus is NP-hard in the strong sense. Problem Space Search is a local search "metaheuristic" which has been shown to be effective for a variety of combinatorial optimization problems including Job Shop Scheduling. In this paper, we propose two problem space search heuristics for the RCPS problem. These heuristics are tested through intensive computational experiments on a 480-instance RCPS data set recently generated by Kolisch et al. [12]. Using this data set we compare our heuristics with a branch-and-bound algorithm developed by Demuelemeester and Herreolen [9]. The results produced by the heuristics are extremely encouraging, showing comparable performance to the branch-and-bound algorithm.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  1. R. Alvarez-Valdéz and J.M. Tamarit, Heuristic algorithms for resource-constrained project scheduling: A review and empirical analysis, in: Advances in Project Scheduling, R. Slowiński and J. Weglarz, eds., Elsevier Science, Amsterdam, 1989, pp. 113–134.

    Google Scholar 

  2. K.R. Baker, Introduction to Sequencing and Scheduling, Wiley, New York, 1974.

    Google Scholar 

  3. M. Bartusch, R.H. Möhring and F.J. Radermacher, Scheduling project networks with resource constraints and time windows, Annals of Operations Research 16(1988)201–240.

    Article  Google Scholar 

  4. C.E. Bell and J. Han, A new heuristic solution method in resource constrained project scheduling, Naval Research Logistics 38(1991)315–331.

    Google Scholar 

  5. J. Blazewicz, J.K. Lenstra and A.H.G. Rinnooy Kan, Scheduling subject to resource constraints: Classification and complexity, Discrete Applied Mathematics 5(1983)11–24.

    Article  Google Scholar 

  6. E.W. Davis and J.H. Patterson, A comparison of heuristic and optimum solutions in resource constrained project scheduling, Management Science 21(1975)944–955.

    Google Scholar 

  7. R.F. Deckro, E.P. Winkofsky, J.E. Herbert and R. Gangon, Decomposition approach to multi-project scheduling, Eur. J. of Oper. Res. 51(1991)110–118.

    Article  Google Scholar 

  8. A. Drexl, Scheduling of project networks by job assignment, Management Science 37(1991)63–76.

    Google Scholar 

  9. E. Demuelemeester and W. Herreolen, A branch-and-bound procedure for the multiple resource constrained project scheduling problem, Management Science 38(1992)1803–1818.

    Google Scholar 

  10. C. Fowler and R.H. Storer, A problem space genetic algorithm for flow shop scheduling with due dates, Working Paper No. 94W-001, Department of Industrial and Manufacturing Systems Engineering, Lehigh University, Bethlehem, PA, 1994.

    Google Scholar 

  11. S. Kim and R.C. Leachman, Multi-project scheduling with explicit lateness costs, IIE Transactions 25(1993)34.

    Google Scholar 

  12. R. Kolisch, A. Sprecher and A. Drexl, Characterization and generation of a general class of resource constrained project scheduling problems: Easy and hard instances, Nr. 301, Institut für Betriebswirtschaftslehre, Christian-Albrechts-Universität zu Kiel, Olhausenstr., Kiel, Germany, December 1992.

    Google Scholar 

  13. I.S. Kurtulus and S.C. Narula, Multiproject scheduling: Analysis of project performance, IIE Transactions 28(1985)58–66.

    Google Scholar 

  14. O. Osman and B. Hasan, Comparative study of computational procedures for the resource constrained project scheduling problem, Eur. J. of Oper. Res. 72(1994)406–416.

    Article  Google Scholar 

  15. C.H. Papadimitriou and K. Steiglitz, Combinatorial Optimization: Algorithms and Complexity, Prentice-Hall, Englewood Cliffs, NJ, 1982.

    Google Scholar 

  16. J.H. Patterson, A comparison of exact approaches for solving the multiple constrained resource project scheduling problem, Management Science 30(1984)854–867.

    Google Scholar 

  17. J.H. Patterson, R. Slowinski, B. Talbot and J. Weglarz, Computational experience with a backtracking algorithm for solving a general class of precedence and resource constrained scheduling problems, Eur. J. of Oper. Res. 49(1990)68–79.

    Article  Google Scholar 

  18. I. Park, Problem space search for sequencing type problems, unpublished Ph.D. Dissertation, Department of Industrial and Manufacturing Systems Engineering, Lehigh University, 1994.

  19. S.E. Sampson and E.N. Weiss, Local search techniques for the generalized resource constrained project scheduling problem, Naval Research Logistics 40(1993)665–676.

    Google Scholar 

  20. R. Slowinski, Two approaches to the problem of resource allocation among project activities — a comparative study, J. of the Oper. Res. Soc 31(1980)711–723.

    Article  Google Scholar 

  21. R. Slowinski, Multi-objective network scheduling with efficient use of renewable and non-renewable resources, Eur. J. of Oper. Res. 7(1981)265–273.

    Article  Google Scholar 

  22. R.H. Storer, S.D. Wu and R. Vaccari, New search spaces for sequencing problems with application to job shop scheduling, Management Science 38(1992)1495–1509.

    Article  Google Scholar 

  23. R.H. Storer, S.W. Flanders and S.D. Wu, Problem space local search for number partitioning, Annals of Operations Research 63(1996)465–487.

    Article  Google Scholar 

  24. E.B. Talbot, Project scheduling with resource-duration interactions: The non-preemptive case, Management Science 28(1982)1197–1210.

    Google Scholar 

  25. J.D. Weist and F.K. Levy, A Management Guide to PERT/CPM, 2nd ed., Prentice-Hall, Englewood Cliffs, NJ, 1977.

    Google Scholar 

  26. K.K. Yang, F.B. Talbot and J.H. Patterson, Scheduling a project to maximize its net present value: An integer programming approach, Eur. J. of Oper. Res. 64(1992)188–198.

    Article  Google Scholar 

  27. Y. Zong, T. Yang and J.P. Ignizio, Expert system using an exchange heuristic for resource constrained project scheduling, Expert Systems with Applications 6(1993)327–348.

    Article  Google Scholar 

Download references

Authors

Rights and permissions

Reprints and permissions

About this article

Cite this article

Naphade, K.S., David Wu, S. & Storer, R.H. Problem space search algorithms for resource-constrained project scheduling. Annals of Operations Research 70, 307–326 (1997). https://doi.org/10.1023/A:1018982423325

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1023/A:1018982423325

Keywords

Navigation