The problem of production variability in serial manufacturing lines with unreliable machines is addressed. Bernoulli statistics of machine reliability are assumed. Three problems are considered: the problem of production variance, the problem of constant demand satisfaction, and the problem of random demand satisfaction generated by another (unreliable) production line. For all three problems, bounds on the respective variability measures are derived. These bounds show that long lines smooth out the production and reduce the variability. More precisely, these bounds state that the production variability of a line with many machines is smaller than that of a single machine system with production volume and reliability characteristics similar to those of the longer line. Since all the variability measures for a single machine line can be calculated relatively easily, these bounds provide analytical tools for analysis and design of serial production lines from the point of view of the customer demand satisfaction.
Similar content being viewed by others
References
J.A. Buzacott and J.G. Shantikumar, Stochastic Models of Manufacturing Systems (Prentice Hall, 1993).
M. Carrascosa, Variance of the output in a deterministic two-machine line, M.S. thesis, Laboratory for Manufacturing and Productivity, Massachusetts Institute of Technology (1995).
Y. Dallery and S.B. Gershwin, Manufacturing flow line systems: A review of models and analytical results, Queueing Systems 12 (1992) 3.
S.B. Gershwin, Variance of output of a Tandem Production System, in: Queuing Networks with Finite Capacity, ed. R.O. Onvaral and I.F. Akyildi (Elsevier, 1993).
S.B. Gershwin, Manufacturing Systems Engineering (Prentice Hall, 1994).
K.B. Hendrics, The output process of serial production lines of exponential machines with finite buffers, Operations Research 40 (1992) 1139.
K.B. Hendrics and J.O. McClain, The output process of serial production lines of general machines with finite buffers, Management Science 39 (1993) 1194.
D.A. Jacobs and S.M. Meerkov, A system-theoretic property of serial production lines: improvability, International Journal of System Science 26 (1995) 755.
D.A. Jacobs and S.M. Meerkov, System-theoretic analysis of Due-Time Performance in production systems, Mathematical Problems in Engineering 1 (1995) 225.
D.S. Kim and J.M. Alden, Estimating the distribution and variance of time to produce a fixed lot size given deterministic processing times and random downtimes, International Journal of Production Research 35 (1997) 3405.
J. Li and S.M. Meerkov, A study of production variability in manufacturing systems, Control Group Report no. CGR98–03, Department of Electrical Engineering and Computer Sciences, The University of Michigan (1998).
G.J. Miltenburg, Variance of the number of units produced on a transfer line with buffer inventories during a period of length T, Naval Research Logistics 34 (1987) 811.
B. Tan, An efficient method for variance of the output in a production line with a finite buffer, in: Proceeding of International Workshop on Performance Evaluation and Optimization of Production Lines (Samos Island, Greece, 1997) p. 135.
B. Tan, Variance of the throughput of an N-station production line with no intermediate buffers and time dependent failures, European Journal of Operational Research 101 (1997) 560.
B. Tan, Effects of variability on the Due-Time Performance of production lines, in: Koc University Working Paper Series97–03, Istanbul, Turkey (1997).
B. Tan, Variance of the output as a function of time: production line dynamics, in: Koc University Working Paper Series 97–19, Istanbul, Turkey (1997).
A.M. Law and W.D. Kelton, Simulation Modeling and Analysis (McGraw-Hill, 1991).
Author information
Authors and Affiliations
Rights and permissions
About this article
Cite this article
Li, J., Meerkov, S.M. Production variability in manufacturing systems: Bernoulli reliability case. Annals of Operations Research 93, 299–324 (2000). https://doi.org/10.1023/A:1018928007956