Robotic Cells with Parallel Machines: Throughput Maximization in Constant Travel-Time Cells

  • H. Neil Geismar
  • Milind Dawande
  • Chelliah SriskandarajahEmail author
Article

Abstract

We present a general analysis of the problem of sequencing operations in bufferless robotic cell flow shops with parallel machines. Our focus will be cells that produce identical parts. The objective is to find a cyclic sequence of robot moves that maximizes the steady state throughput. Parallel machines are used in the industry to increase throughput, most typically at bottleneck processes having larger processing times.

Efficient use of parallel machines requires that several parts be processed in one cycle of robot movements. We analyze such cycles for constant travel-time robotic cells. The number of cycles that produce several parts is very large, so we focus on a subclass called blocked cycles. In this class, we find a dominating subclass called LCM Cycles.

The results and the analysis in this paper offer practitioners (i) guidelines to determine whether parallel machines will be cost-effective for a given implementation, (ii) a simple formula for determining how many copies of each machine are required to meet a particular throughput rate, and (iii) an optimal sequence of robot moves for a cell with parallel machines under a certain common condition on the processing times.

manufacturing robotic cell constant travel-time parallel machines LCM cycles 

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

REFERENCES

  1. Agnetis, A., "Scheduling no-wait robotic cells with two and three machines," European Journal of Operational Research, 123, 303–314 (2000).Google Scholar
  2. Agnetis, A. and D. Pacciarelli, "Part sequencing in three machine no-wait robotic cells," Operations Research Letters, 27, 185–192 (2000).Google Scholar
  3. Blazewicz, J., H. Eiselt, G. Finke, G. LaPorte, and J. Weglarz, "Scheduling tasks and vehicles in a flexible manufacturing system," Internat. J. Flexible Manufacturing Systems, 4, 5–16 (1991).Google Scholar
  4. Brauner, N. and G. Finke, "On a conjecture about robotic cells: New simplified proof for the three-machine case," INFOR, 37, 20–36 (1999).Google Scholar
  5. Che, A., C. Chu, and F. Chu, "Multicyclic hoist scheduling with constant processing times," IEEE Transactions on Robotics and Automation, 18(1), 69–80 (2002).Google Scholar
  6. Chen, H., C. Chu, and J. Proth, "Cyclic scheduling with time window constraints," IEEE Transactions on Robotics and Automation, 14(1), 144–152 (1998).Google Scholar
  7. Crama, Y., V. Kats, J. van de Klundert, and E. Levner, "Cyclic scheduling in robotic flowshops," Annals of Operations Research, 96, 97–124 (2000).Google Scholar
  8. Crama, Y. and J. van de Klundert, "Cyclic scheduling of identical parts in a robotic cell," Operations Research, 6, 952–965 (1997).Google Scholar
  9. Dawande, M., C. Sriskandarajah, and S. Sethi, "On throughput maximization in constant travel-time robotic cells," Manufacturing and Service Operations Management, 4(4), 296–312 (2003).Google Scholar
  10. Hall, N. G., "Operations research techniques for robotic systems," in S. Y. Nof (ed.), Handbook of Industrial Robotics, 2nd edition, John Wiley and Sons, 1999.Google Scholar
  11. Hall, N. G., H. Kamoun, and C. Sriskandarajah, "Scheduling in robotic cells: Classification, two and three machine cells," Operations Research, 45, 421–439 (1997).Google Scholar
  12. Hall, N. G., H. Kamoun, and C. Sriskandarajah, "Scheduling in robotic cells: Complexity and steady state analysis," European Journal of Operational Research, 109, 43–63 (1998).Google Scholar
  13. Hall, N. G., C. Potts, and C. Sriskandarajah, "Parallel machine scheduling with a common server," Discrete Applied Mathematics, 102, 223–243 (2000).Google Scholar
  14. Kats, V. and E. Levner, "Cycle scheduling in a robotic production line," Journal of Scheduling, 5, 23–41 (2002).Google Scholar
  15. Kumar, S., N. Ramanan, and C. Sriskandarajah, "Maximizing throughput in large robotic cells," IIE Transactions (to appear).Google Scholar
  16. Lei, L. and T. J.Wang, "Determining optimal cyclic hoist schedules in a single-hoist electroplating line," IIE Transactions, 26(2), 25–33 (1994).Google Scholar
  17. Levner, E., V. Kats, and V. Levit. "An improved algorithm for cyclic flowshop scheduling in a robotic cell," European Journal of Operational Research, 97, 500–508 (1997).Google Scholar
  18. Logendran, R. and C. Sriskandarajah, "Sequencing of robot activities and parts in two-machine robotic cells," Int. J. Prod. Res, 34(12), 3447–3463 (1996).Google Scholar
  19. Perkinson, T., P.McLarty, R. Gyurcsik, and R. Cavin, "Single-wafer cluster tool performance:An analysis of throughput," IEEE Transactions on Semiconductor Manufacturing, 7, 369–373 (1994).Google Scholar
  20. Pinedo, M., Scheduling: Theory, Algorithms, and Systems. Prentice Hall, Englewood Cliffs, New Jersey, 1995.Google Scholar
  21. J. Blazewicz, and W. Kubiak, "Sequencing of parts and robot moves in a robotic cell," Internat. J. Flexible Manufacturing Systems, 4, 331–358 (1992).Google Scholar
  22. Sriskandarajah, C., N. G. Hall, and H. Kamoun, "Scheduling large robotic cells without buffers," Annals of Operations Research, 76, 287–321 (1998).Google Scholar

Copyright information

© Kluwer Academic Publishers 2004

Authors and Affiliations

  • H. Neil Geismar
    • 1
  • Milind Dawande
    • 1
  • Chelliah Sriskandarajah
    • 1
    Email author
  1. 1.University of Texas

Personalised recommendations