BIM-based framework to quantify delays and cost overruns due to changes in construction projects

  • Original Paper
  • Published:
Asian Journal of Civil Engineering Aims and scope Submit manuscript

Abstract

Architecture, Engineering, and Construction (AEC) projects are inherently complex, risky in nature, and difficult to manage. Due to fragmented nature of design-construction phase, every project witnessing changes throughout project lifecycle. Changes are one of the most common issues in construction projects, and they hurt project execution as far as time, cost, and quality is concerned. To manage projects successfully, it is necessary to investigate the causes of change and analyze its delays and cost overruns systematically. Past studies revealed that Building Information Modeling (BIM) has huge potential to minimize unnecessary delays and increase cost savings. Therefore, the objective of this study is to analyze the changes and their impacts on the schedule and cost of construction projects using BIM platform. This study proposes a one-of-a-kind BIM-based visualization model for changes in architectural, structural, HVAC, Fire, and electrical systems in buildings to assist owners and their stakeholders in considering the consequences of changes that occurred in the project. Before deciding to accept or reject changes, the proposed model enables owners to view the visual impacts of changes. The suggested model compares the “planned” and “actual” BIM models to recognize the grouping of affected changes, taking into consideration the consequences of such presented changes on the amounts and particulars of affected structure parts and their conditions. The proposed model was applied in an ongoing office building construction project, and it was demonstrated to be very helpful in making decisions related to changes.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Subscribe and save

Springer+ Basic
EUR 32.99 /Month
  • Get 10 units per month
  • Download Article/Chapter or Ebook
  • 1 Unit = 1 Article or 1 Chapter
  • Cancel anytime
Subscribe now

Buy Now

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 5
Fig. 6
Fig. 7

Similar content being viewed by others

References

  • Akponeware, A. O., & Adamu, Z. A. (2017). Clash detection or clash avoidance? An investigation into coordination problems in 3D BIM. Buildings. https://doi.org/10.3390/buildings7030075

    Article  Google Scholar 

  • Arunkumar, S., Suveetha, V., & Ramesh, A. (2018). A feasibility study on the implementation of building information modeling (BIM): from the architects’ and engineers’ perspective. Asian Journal of Civil Engineering, 19, 239–247. https://doi.org/10.1007/s42107-018-0020-9

    Article  Google Scholar 

  • Bejarano, E. (2019). Integration of Earn Value Management into BIM Projects. Journal of Architectural Engineering Technology. https://doi.org/10.4172/2168-9717.1000221

    Article  Google Scholar 

  • Braimah, N. (2013). Construction delay analysis techniques-a review of application issues and improvement needs. Buildings. https://doi.org/10.3390/buildings3030506

    Article  Google Scholar 

  • Chua, D. K. H., & Hossain, M. A. (2012). Predicting change propagation and impact on design schedule due to external changes. IEEE Transactions Engineering Management, 59(3), 483–493.

    Article  Google Scholar 

  • Construction industry institute (CII). (1994) Project change management. special publication. Austin (TX): construction industry institute

  • Cox, I. D., Morris, J. P., Rogerson, J. H., & Jared, G. E. (1999). A quantitative study of post contract award design changes in construction. Construction Management & Economics, 17(4), 427–439.

    Article  Google Scholar 

  • Crowther, J., & Ajayi, S. O. (2019). Impacts of 4D BIM on construction project performance. International Journal of Construction Engineering & Management, 21(7), 724–737. https://doi.org/10.1080/15623599.2019.1580832

    Article  Google Scholar 

  • Dawood, N., & Sikka, S. (2009). Development of 4D base performance indicators in construction industry. Engineering, Construction and Architectural Management, 16(5), 438–458.

    Article  Google Scholar 

  • de Vargas, F.B., Bataglin, F S., & , Formoso, C.T. (2018) Guidelines to Develop a BIM model focused on construction planning and control. 26th Annual Conference of the International Group for Lean Construction (IGLC), 18–22 July, Chennai, India

  • Eckert, C., Clarkson, P. J., & Zanker, W. (2004). Change and customisation in complex engineering domains. Research in Engineering Design, 15(1), 1–21.

    Article  Google Scholar 

  • Ghimire, S., & Mishra, A. K. (2019). Comparative study of prospective delay analysis techniques (DATs). Saudi Journal of Civil Engineering. https://doi.org/10.21276/sjce.2019.3.5.1

    Article  Google Scholar 

  • Hegazy, T., Zaneldin, E., & Grierson, D. (2001). Improving design coordination for building projects I: information model. Journal of Construction Engineering & Management, 127(4), 322–329.

    Article  Google Scholar 

  • Hire, S., Sandbhor, S., & Ruikar, K. (2021). BIM usage benefits and challenges for site safety application in Indian construction sector. Asian Journal of Civil Engineering, 22, 1249–1267. https://doi.org/10.1007/s42107-021-00379-8

    Article  Google Scholar 

  • Hire, S., Sandbhor, S., & Ruikar, K. (2022). Bibliometric survey for adoption of building information modeling (BIM) in construction industry– a safety perspective. Arch Computat Methods Eng, 29, 679–693. https://doi.org/10.1007/s11831-021-09584-9

    Article  Google Scholar 

  • Ibbs, W. M., Nguyen, L. D., & Lee, S. (2007). Quantified impacts of project change. Journal of Professional Issues in Engineering Education & Practice, 133(1), 45–52.

    Article  Google Scholar 

  • Jrade, A., & Lessard, J. (2015). An integrated bim system to track the time and cost of construction projects: a case study. Journal of Construction Engineering, Hindawi Publishing Corporation,. https://doi.org/10.1155/2015/579486

    Article  Google Scholar 

  • Karimidorabati, S., Haas, C. T., & Gray, J. (2016). Evaluation of automation levels for construction change management. Engineering Construction and Architectural & Management, 23(5), 554–570.

    Article  Google Scholar 

  • Khanzadi, M., Kaveh, A., Moghaddam, M. R., & Pourbagheri, S. M. (2019). Optimization of building components with sustainability aspects in BIM environment: optimization of building components with sustainability aspects in BIM environment. Periodica Polytechnica Civil Engineering, 63(1), 93–103. https://doi.org/10.3311/PPci.12551

    Article  Google Scholar 

  • Mejlaender-Larsen, O. (2016). (2016), Using a change control system and building information modelling to manage change in design. Architectural Engineering & Design Manageement, 10(1080/17452007), 1220360.

    Google Scholar 

  • Moayeri, V., Moselhi, O., & Zhu, Z. (2017). Design change management using bim-based visualization model. International Journal of Architectural, Engineering, & Construction, 6(1), 1–11.

    Google Scholar 

  • Motawa, I. A., Anumba, C. J., Lee, S., & Pena-Mora, F. (2007). An integrated system for change management in construction. Automation in Construction, 16(3), 368–377.

    Article  Google Scholar 

  • Padala, S.P.S, & Maheswari, J.U. (2022) Modeling a construction project in a matrix-based framework for managing requirement changes. International Journal of Construction Management https://doi.org/10.1080/15623599.2022.2059739

  • Padala, S. P. S., Maheswari, J. U., & Hirani, H. (2020). Identification and classification of change causes and effects in construction projects. International Journal Construction Management. https://doi.org/10.1080/15623599.2020.1827186

    Article  Google Scholar 

  • Pakhale, P. D., & Pal, A. (2020). Digital project management in infrastructure project: a case study of Nagpur Metro Rail Project. Asian Journal of Civil Engineering, 21, 639–647. https://doi.org/10.1007/s42107-020-00224-4

    Article  Google Scholar 

  • Pilehchian, B., Staub-French, S., & Nepal, M. P. (2015). A conceptual approach to track design changes within a multi-disciplinary building information modeling environment. Canadian Journal of Civil Engineering, 42(2), 139–152.

    Article  Google Scholar 

  • Raya, R. K., & Gupta, R. (2022). Application of BIM framework on rural infrastructure. Asian J Civ Eng, 23, 249–268. https://doi.org/10.1007/s42107-022-00421-3

    Article  Google Scholar 

  • Sabbaghzadeh, M., Sheikhkhoshkar, M., Talebi, S., Rezazadeh, M., Moghaddam, M. R., & Khanzadi, M. (2022). A BIM-based solution for the optimisation of fire safety measures in the building design. Sustainability, 14(3), 1626. https://doi.org/10.3390/su14031626

    Article  Google Scholar 

  • Seong, M. P., Leviakangas, P., & Choi, J. (2020). Making most of BIM in design: analysis of the importance of design coordination. International Journal Construction Management. https://doi.org/10.1080/15623599.2020.1774837

    Article  Google Scholar 

  • Sobhkhiz, S., Taghaddos, H., Rezvani, M., & Ramezanianpour, A. M. (2021). Utilisation of semantic web technologies to improve BIM-LCA applications. Automation in Construction, 130, 103842. https://doi.org/10.1016/j.autcon.2021.103842

    Article  Google Scholar 

  • Society of construction law. (2017). Society of construction law delay and disruption 2nd edition. https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf. Accessed 11 Oct 2021

  • Sun, M., Fleming, A., Senaratne, S., Motawa, I., & Yeoh, M. (2006). A change management toolkit for construction projects. Architectural Engineering & Design Manageement, 2(4), 261–327.

    Article  Google Scholar 

  • Tarek, Z, Amir, H, Hoda. A, Hosny. O, Nassar. K, Zahran. K. (2018) BIM-based delay analysis: a framework; building tomorrow’s society, fredericton, June 13–June 16, Canada

  • Yarramsetty, S., Rohullah, M. S., Sivakumar, M. V. N., et al. (2020). An investigation on energy consumption in residential building with different orientation: a BIM approach. Asian J Civ Eng, 21, 253–266. https://doi.org/10.1007/s42107-019-00189-z

    Article  Google Scholar 

Download references

Funding

The authors declare that no funds, grants, or other support were received during the preparation of this manuscript.

Author information

Authors and Affiliations

Authors

Contributions

All authors have contributed to the study design and execution. Data collection and analysis was performed by first author. The first and revised draft is written by second author. All authors read and approved the final manuscript.

Corresponding author

Correspondence to S. P. Sreenivas Padala.

Ethics declarations

Conflict of interest

On behalf of all authors, the corresponding author declares that there is no conflict of interest. The authors have no relevant financial or non-financial interests to disclose.

Additional information

Publisher's Note

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Supplementary Information

Below is the link to the electronic supplementary material.

Supplementary file1 (DOCX 1408 KB)

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Honnappa, D., Padala, S.P.S. BIM-based framework to quantify delays and cost overruns due to changes in construction projects. Asian J Civ Eng 23, 707–725 (2022). https://doi.org/10.1007/s42107-022-00451-x

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s42107-022-00451-x

Keywords

Navigation