Table 5 Numerical results for small projects with 30 non-dummy activities

From: Profit-oriented scheduling of resource-constrained projects with flexible capacity constraints

#Schedules Genetic algorithm LocalSolver
\((\lambda |\beta )\) \((\lambda |\hat{z}_r)\) \((\lambda |\hat{z}_{rt})\) \((\lambda |\beta )\) \((\lambda |\hat{z}_r)\) \((\lambda |\hat{z}_{rt})\)
1000 \(1.60\%\) \(1.52\%\) \({1.31\%}\) \(3.00\%\) \(2.57\%\) \(15.31\%\)
5000 \(0.50\%\) \(0.57\%\) \({0.32\%}\) \(0.67\%\) \(0.76\%\) \(4.51\%\)
50,000 \(0.14\%\) \(0.33\%\) \({0.12\%}\) \(0.15\%\) \(0.29\%\) \(0.33\%\)