Table. 1 The switching sequence for proper operation of the simulation model in Fig. 5
From: Analysis of rail potential and stray current in MVDC railway electrification system
Simulation time | Sc1/Sk1 | Sc2/Sk2 | Sc3/Sk3 | Sc4/Sk4 | Sc5/Sk5 | Sc6/Sk6 | Sc7/Sk7 | Sc8/Sk8 | Sc9/Sk9 | Sc10/Sk10 |
|---|---|---|---|---|---|---|---|---|---|---|
T0 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 | 0 |
T1 | 0 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 | 0 |
T2 | 0 | 0 | 1 | 1 | 1 | 1 | 1 | 0 | 0 | 0 |
T3 | 0 | 0 | 0 | 1 | 1 | 1 | 1 | 1 | 0 | 0 |
T4 | 0 | 0 | 0 | 0 | 1 | 1 | 1 | 1 | 1 | 0 |
T5 | 0 | 0 | 0 | 0 | 0 | 1 | 1 | 1 | 1 | 1 |