Abstract
APDPPL has constructed a coal terminal at Dahej, India. The 670-m off-shore jetty head is connected to land with 1170-m pile-supported trestle followed by 1200-m rubble mounted bund. The original plan was to construct the jetty head and approach trestle with 1200-mm concrete bored piles. However, due to site constraints, high tidal variation and to ensure timely completion, it was decided to change the jetty head piles to steel pipe piles at the jobsite. The pile diameter selected was 1422 mm and design done as per API RP2A method. The thickness of the pipe varied from 22 to 38 mm. The piles were generally planned for up to 30 m penetration into seabed and the maximum working load varied from 3228 to 5223 kN. It was required to select a hammer to drive the piles to the required depth. Options were generally limited to Delmag D100-13 or D150-42 hammer due to commercial considerations. A GRLWEAP was performed to evaluate the suitability of the hammer for driving the pile. Both the drivability and bearing graph analysis were done, and also checks were done using soil static analysis. Based on the finding, the Delmag D100-13 hammer was selected and the piles were successfully driven to the required penetration. HSDPTs were performed at EOID with 2 restrikes to confirm the long-term pile capacities due to set-up. The results gave enough confidence about the pile capacity and hammer capability to drive all the piles. Static load testing was eliminated at the project site. 10% of the steel piles, 5% bored piles and 20% integrity tests were done at the jobsite. The entire job was successfully completed, and the berths are in operation currently. The case study is an excellent example of using combination of GRLWEAP, static analysis and HSDPT towards successful completion of the entire job.
References
American Petroleum Institute (2005) API recommended practice for planning, designing and constructing fixed offshore platforms—working stress design. API Report RP 2A-WSD
GRLWEAP 2006 Background Report
Federal Highway Administration Reference Manual—Volume I &II (2006) Design and Construction of Driven Pile Foundations. Publication No. FHWA NHI-05-043
Brzezinski LS, Baba HU (2012) Offshore open end steel tubular piles—a case history. GeoCongress 2012, Oakland, CA, USA
ASTM D4945-08. Standard Test Method for High- Strain Dynamic Testing of Piles
Goble GG, Likins GE (1996) On the Application of PDA Dynamic Pile Testing. In: Fifth international conference on the application of stress wave theory to piles, Orlando, FL, USA
Hussein MH, Choate L, Mangogna R, Gray K. Effective use of steel piles for a large transportation project in Central Florida. Deep Foundations 191–198
Cannon JG (2000) The application of high strain dynamic pile testing to screwed steel piles. Application of Stress-Wave Theory to Piles, 2000 Balkema, Rotterdam, ISBN 90 5809150 3
Morgano CM (1996) Determining Embedment Depths if Deep Foundations Using Non-Destructive Methods. In: Fifth international conference on the application of stress wave theory to piles, Orlando, FL, USA
Vaidya R (2006) Introduction to high strain dynamic pile testing and reliability studies in Southern India. Indian Geotechnical Conference, Chennai, India
Acknowledgements
The authors acknowledge the review of GRLWEAP by Frank Rausche, President, Pile Dynamics, Inc., USA, for this project.
Author information
Authors and Affiliations
Corresponding author
Additional information
Publisher's Note
Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.
Rights and permissions
About this article
Cite this article
Vaidya, R., Basu, A. & Singhal, V.K. Experiences in Drivability Analysis, Testing of Open-Ended Steel Pipe Piles and Drilled Shafts at Dahej LNG Project, India. Indian Geotech J 51, 435–447 (2021). https://doi.org/10.1007/s40098-020-00449-9
Received:
Accepted:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s40098-020-00449-9