Abstract
Precise estimation of annual maintenance budget (AMB) drives appropriate maintenance actions. There appears to be a dearth of historical data to evaluate the AMB for a particle accelerator system as these are not many. This paper presents a case study on estimating the AMB of such a system for its contextual conditions using relational matrix of the budget variables. The diagonal elements of the matrix represent the variables while the off-diagonal elements signify the degree of influence among these. The maintenance budget function is evaluated from this matrix and is used to evaluate the AMB for the Pelletron system as a percentage of its asset replacement value. The actual maintenance expenditure on the Pelletron system was found to be within 2.07% of the estimated AMB. The approach is expected to aid the maintenance managers of similar systems, which operate under contextual conditions unique to their laboratory.
Similar content being viewed by others
References
Barbalat O (1994) Applications of particle accelerators. European Organization for Nuclear Research, Geneva. Report No. CERN/AC93-04(BLIT), SW 9412
Barberá L, Crespo A, Viveros P, Stegmaier R (2012) Advanced model for maintenance management in a continuous improvement cycle: integration into the business strategy. Int J Syst Assur Eng Manag 3(1):47–63
Deo N (1974) Graph theory. Prentice Hall, Englewood Cliffs
Gulati R, Smith R (2009) Maintenance and reliability best practices. Industrial Press Inc., New York
Gupta P, Gupta S, Gandhi OP (2013) Modelling and evaluation of mean time to repair at product design stage based on contextual criteria. J Eng Des 24(7):499–523
Gupta P, Gupta S, Gandhi OP (2014) Annual maintenance budget estimation for a plant system—Digraph model and matrix approach. J Qual Maint Eng 20(2):193–210
Gupta S, Kota S, Mishra RP (2015) Modeling and evaluation of product quality at conceptual design stage. Int J Syst Assur Eng Manag. doi:10.1007/s13198-015-0357-3
Jurkat WB, Ryser HJ (1966) Matrix factorization of determinants and permanents. J Algebra 3(1):1–27
Livingston MS (1969) Particle accelerators: a brief history. Harvard University Press, Cambridge
Pai A, Rane S (2014) Development and implementation of maintenance management module of enterprise resource planning in maintenance of power plan. Int J Syst Assur Eng Manag 5(4):534–543
Rao PT, Reddy PRS, Suhasini AVS (2010) Optimal manpower recruitment by stochastic programming in graded manpower systems. Int J Syst Assur Eng Manag 1(2):178–185
Vaisnys P, Contri P, Rieg C, and Bieth M (2006) Monitoring the effectiveness of maintenance programs through the use of performance indicators, DG, JRC- Institute for Energy. ISSN 1018-5593, Luxembourg: Office for official Publications in the European Communities
Verma AK, Srividya A, Rana A (2011) Optimal time scheduling for carrying out minor maintenance on a steam turbine. Int J Syst Assur Eng Manag 2(3):241–252
Author information
Authors and Affiliations
Corresponding author
Rights and permissions
About this article
Cite this article
Gupta, P. Maintenance budget estimation for a particle accelerator system under its contextual conditions: a case study. Int J Syst Assur Eng Manag 8 (Suppl 2), 1143–1153 (2017). https://doi.org/10.1007/s13198-017-0580-1
Received:
Revised:
Published:
Issue Date:
DOI: https://doi.org/10.1007/s13198-017-0580-1