Trajectory Control of Tunnel Boring Machine Based on Adaptive Rectification Trajectory Planning and Multi-cylinders Coordinated Control

  • Regular Paper
  • Published:
International Journal of Precision Engineering and Manufacturing Aims and scope Submit manuscript

Abstract

Trajectory control of tunnel boring machine (TBM) has important implications for excavation efficiency and tunnel quality. A novel rectification trajectory planning method is proposed for TBM with adaptively designed direction and curvature against different attitude deviations and target path, and is comparatively studied with traditional method via numerical simulations. TBM could be fully-actuated by decoupling thrust and torque cylinders in horizontal and vertical planes, respectively. After the tropology analysis of the 4-SPS/PS structure, the real-time expected motions of torque cylinders in vertical plane are derived via reverse kinematics together with synchronous thrust cylinders; so does cylinders in horizontal plane. The proportional direction valves of torque and gripper cylinders are compensated with fixed pressure drop. A compound displacement tracking controller could be established, including flow-speed feed-forward with dead-band compensation and displacement feedback by fuzzy proportional–integral (PI) controller with separated integration. Synchronous controller of integral separated PI structure is also proposed. Experiment results on a Φ 2.5 m scaled TBM indicate that, the displacement tracking performance of cylinders under the compound controller against unbalanced load, which is ± 0.9 mm for high-speed thrust cylinders and ± 0.13 mm for low-speed gripper and torque cylinders, could meet the tolerance of trajectory planning and realize accurate attitude correction.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Fig. 1
Fig. 2
Fig. 3
Fig. 4
Fig. 5
Fig. 6
Fig. 7
Fig. 8
Fig. 9
Fig. 10
Fig. 11
Fig. 12
Fig. 13
Fig. 14
Fig. 15
Fig. 16
Fig. 17
Fig. 18
Fig. 19
Fig. 20
Fig. 21
Fig. 22
Fig. 23
Fig. 24
Fig. 25
Fig. 26
Fig. 27

Similar content being viewed by others

References

  1. Farrokh, E., & Rostami, J. (2008). Correlation of tunnel convergence with TBM operational parameters and chip size in the Ghomroud tunnel, Iran. Tunnelling and Underground Space Technology, 23(6), 700–710.

    Article  Google Scholar 

  2. Bilgin, N., & Algan, M. (2012). The performance of a TBM in a squeezing ground at Uluabat, Turkey. Tunnelling and Underground Space Technology, 32(32), 58–65.

    Article  Google Scholar 

  3. Ramoni, M., & Anagnostou, G. (2010). Tunnel boring machines under squeezing conditions. Tunnelling and Underground Space Technology, 25(2), 139–157.

    Article  Google Scholar 

  4. Shen, X. S., Lu, M., & Chen, W. (2011). Tunnel-boring machine positioning during microtunneling operations through integrating automated data collection with real time computing. Journal of Construction Engineering and Management, 137(1), 72–85.

    Article  Google Scholar 

  5. Mao, S., Shen, X. S., & Lu, M. (2015). Virtual laser target board for alignment control and machine guidance in tunnel-boring operations. Journal of Intelligent and Robotic Systems, 79(3-4), 385–400.

    Article  Google Scholar 

  6. Mok, W., Mak, M., & Poon, F. (2007). Sewer installation by pipejacking in the urban areas of Hong Kong part II—Performance of works, lessons learned and improvements proposed. HKIE Transactions, 14(1), 31–43.

    Article  Google Scholar 

  7. Luo, L. P., Yuan, C., Yan, R. J., Yuan, Q., Wu, J., Shin, K. S., et al. (2015). Trajectory planning for energy minimization of industry robotic manipulators using the Lagrange interpolation method. International Journal of Precision Engineering and Manufacturing, 16(5), 911–917.

    Article  Google Scholar 

  8. Kim, D., Choi, H. S., Kim, J. Y., Park, J. H., & Tran, N. H. (2015). Trajectory generation and sliding-mode controller design of an underwater vehicle-manipulator system with redundancy. International Journal of Precision Engineering and Manufacturing, 16(7), 1561–1570.

    Article  Google Scholar 

  9. Ling, Y. F. (2009). Trajectory planning during shield tunneling process. M. D. Thesis, Dalian University of Technology, China (in Chinese).

  10. Xie, H. B., Duan, X. P., Yang, H. Y., & Liu, Z. B. (2012). Automatic trajectory tracking control of shield tunneling machine under complex stratum working condition. Tunnelling and Underground Space Technology, 32(6), 87–97.

    Article  Google Scholar 

  11. Wang, L. T., Sun, W., Gong, G. F., & Yang, H. Y. (2017). Method to avoid the structural interference of the thrust system of a shield tunneling machine. Science in China Series E: Technological Sciences, 60(5), 701–712.

    Article  Google Scholar 

  12. Yue, M., Sun, W., & Hu, P. (2012). Dynamic coordinated control of attitude correction for the shield tunneling based on load observer. Automation in Construction, 24(24), 24–29.

    Article  Google Scholar 

  13. Yang, H. Y., Shi, H., & Gong, G. F. (2010). Motion control of thrust system for shield tunneling machine. Journal of Central South University, 17(3), 537–543.

    Article  Google Scholar 

  14. Truong, D. Q., Thanh, T. Q., & Ahn, K. K. (2012). Development of a novel linear magnetic actuator with trajectory control based on an online tuning fuzzy PID controller. International Journal of Precision Engineering and Manufacturing, 13(8), 1403–1411.

    Article  Google Scholar 

  15. Huang, T., Wang, X. L., Liu, H. T., & Yang, Y. H. (2016). Force analysis of an open TBM gripping–thrusting–regripping mechanism. Mechanism and Machine Theory, 98, 101–113.

    Article  Google Scholar 

  16. Mccrae, J., & Singh, K. (2009). Sketching piecewise clothoid curves. Computers and Graphics, 33(4), 452–461.

    Article  Google Scholar 

  17. Yang, H. Y., Shi, H., & Gong, G. F. (2009). Earth pressure balance control for EPB shield. Science in China Series E: Technological Sciences, 52, 2840–2848.

    Article  MATH  Google Scholar 

  18. Xie, H. B., Liu, Z. B., & Yang, H. Y. (2016). Pressure regulation for earth pressure balance control on shield tunneling machine by using adaptive robust control. Chinese Journal of Mechanical Engineering, 29(3), 598–606.

    Article  Google Scholar 

  19. Wang, L. T., Gong, G. F., Yang, H. Y., Yang, X., & Hou, D. Q. (2013). The development of a high-speed segment erecting system for shield tunneling machine. IEEE/ASME Transactions on Mechatronics, 18(6), 1713–1723.

    Article  Google Scholar 

Download references

Acknowledgements

The authors would like to offer their gratitude to the National Basic Research Program of China (973 Program, Grant No. 2015CB058103), National Natural Science Foundation of China (Grant Nos. 51675472 and 51521064) and Henan province major science and technology projects (Grant No. 161100211100).

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Guo-fang Gong.

Additional information

Publisher's Note

Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Liu, T., Gong, Gf., Yang, Hy. et al. Trajectory Control of Tunnel Boring Machine Based on Adaptive Rectification Trajectory Planning and Multi-cylinders Coordinated Control. Int. J. Precis. Eng. Manuf. 20, 1721–1733 (2019). https://doi.org/10.1007/s12541-019-00073-5

Download citation

  • Received:

  • Revised:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s12541-019-00073-5

Keywords

Navigation