Risk-integrated cash flow forecasting for overseas construction projects

  • Construction Management
  • Published:
KSCE Journal of Civil Engineering Aims and scope

Abstract

Construction firms have long attempted to forecast a project cash flow at the initial stage of a project, which is closely related to the payment conditions and financing schedules. There are, however, diverse risk factors influencing project cash flow, in particular for the domain of international projects, which often fluctuate because of a myriad of external as well as internal uncertainties. In this research, risk factors that impact the soundness of cash flow are classified into two categories: financial risks and project-specific risks. The former refers to the external economic conditions such as exchange rate, cost escalation, and interest rate which can be analyzed through a probabilistic financial algorithm. Then, the project-specific risks such as host country’s geotechnical conditions, weather and climate differences, and resource delivery conditions are further assessed through utility curves to represent the firm’s unique risk perceptions and thresholds to the amount of risk exposures. Results of cash flow forecasts by the proposed approach are compared with the actual cash flow of a retrospective case project. It is found that construction firms better decide on a decent level of cash contingency and the probable net-profit at completion by the adoption of the proposed approach.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Subscribe and save

Springer+ Basic
EUR 32.99 /Month
  • Get 10 units per month
  • Download Article/Chapter or Ebook
  • 1 Unit = 1 Article or 1 Chapter
  • Cancel anytime
Subscribe now

Buy Now

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  • Abudayyeh, O. Y. and Rasdorf, W. J. (1993). “Prototype of an integrated cost and schedule control system.” Journal of Comp. in Civil Engineering, Vol. 7, No. 2, pp. 181–198.

    Article  Google Scholar 

  • Ahuja, H. N. and Walsh, M. A. (1983). Successful methods in cost engineering, John Wiley & Sons, New York, NY.

    Google Scholar 

  • Arditi, D. and Gutierrez, A. E. (1991). “Factors affecting U.S. contractors’ performance overseas.” Journal of Construction Engineering and Management, Vol. 117, No. 1, pp. 27–46.

    Article  Google Scholar 

  • Ashley, D. B. and Bonner, J. J. (1987). “Political risks in international construction.” Journal of Construction Engineering and Management, Vol. 113, No. 3, pp. 447–467.

    Article  Google Scholar 

  • Ashley, D. B. and Teicholz, P. M. (1977). “Pre-estimated cash flow analysis.” Journal of the Construction Division. Proceedings of ASCE, Vol. 103, No. CO3, pp. 369–379.

    Google Scholar 

  • Aziz, A. M. A. and Russell, A. D. (2006). “Generalized economic modeling for infrastructure and capital investment projects.” Journal of Infrastructure Systems, ASCE, Vol. 12, No. 1, pp. 18–32.

    Article  Google Scholar 

  • Bennett, J. and Ormerod, R. N. (1984). “Simulation applied to construction projects.” Construction Management and Economics, Vol. 2, No. 3, pp. 225–263.

    Article  Google Scholar 

  • Bing, L., Tiong, L. K., Fan, W. W., and Chew, D. A. (1999). “Risk management in international construction joint ventures.” Journal of Construction Engineering and Management, Vol. 125, No. 4, pp. 277–284.

    Article  Google Scholar 

  • Boussabaine, A. H. and Elhag, T. (1999). “Applying fuzzy techniques to cash flow analysis.” Construction Management & Economics, Vol. 17, No. 6, pp. 745–755.

    Article  Google Scholar 

  • Boussabaine, A. H. and Kaka, A. P. (1998). “A neural networks approach for cost flow forecasting.” Construction Management & Economics, Vol. 16, No. 4, pp. 471–479.

    Article  Google Scholar 

  • Chan, E. H. W. and Tse, R. Y. S. (2003). “Cultural considerations in international construction contracts.” Journal of Construction Engineering and Management, Vo l. 129, No. 4, pp. 375–381.

    Article  Google Scholar 

  • Chen, H., O’Brien, W. J., and Herbsman, Z. J. (2005). “Assessing the accuracy of cash flow models: The significance of payment conditions.” Journal of Construction Engineering and Management, Vol. 131, No. 6, pp. 669–676.

    Article  Google Scholar 

  • Decisioneering, Inc. (2005). Crystal ball guide (Version 7.2), Decisioneering, Inc. Denver, CO.

    Google Scholar 

  • Demacopoulos, A. C. (1989). Foreign exchange exposure in international construction, PhD Thesis, Massachusetts Institute of Technology, Boston.

    Google Scholar 

  • Gates, M. and Scarpa, A. (1979). “Preliminary cumulative cash flow analysis.” Cost Engineering, Vol. 21, No. 6, pp. 243–249.

    Google Scholar 

  • Groppelli, A. A. and Nikbaht, E. (2000). Finance, 4th Ed. Barrons, New York, NY.

    Google Scholar 

  • Han, S. H., Diekmann, J. E., and Ock, J. H. (2005). “Contractors’ risk attitudes in the selection of international construction projects.” Journal of Construction Engineering and Management, Vol. 131, No. 3, pp. 283–292.

    Article  Google Scholar 

  • Han, S. H., Park, S. H., Kim, D. Y., Kim, H., and Kang, Y. W. (2007). Causes of bad profits in overseas construction projects.” Journal of Construction Engineering and Management, Vol. 133, No. 12, pp. 932–943.

    Article  Google Scholar 

  • Jarrah, R., Kulkarni, D., and O’Connor, J. T. (2007). “Cash flow projections for selected txdot highway projects.” Journal of Construction Engineering and Management, Vol. 133, No. 3, pp. 235–241.

    Article  Google Scholar 

  • Jung, D. W., Kim, H. J., Hyun, C. T., and Kim, I. H. (2001). “A study on the financial risk assessment of SOC private investment projects: Focused on light rail transit projects.” Korean Journal of Architectural Engineering, Vol. 17, No. 5, pp. 109–116.

    Google Scholar 

  • Kahneman, D. and Tsversky, A. (1979). “Prospect theory: An analysis of decisions under risk.” Econometrica, Vol. 47, No. 2, pp. 263–291.

    Article  MATH  Google Scholar 

  • Kaka, A. P. and Price, A. D. F. (1991). “Net cash flow models: Are they reliable?.” Construction Management and Economics, Vol. 9, pp. 291–308.

    Article  Google Scholar 

  • Kapilar, P. and Hendrickson, C. (2001). “Exchange rate risk management in international construction ventures.” Journal of Management in Engineering, Vol. 17, No. 4, pp. 186–191.

    Article  Google Scholar 

  • Kenley, R. and Wilson, O. D. (1986). “A construction project cash flow model: An idiographic approach.” Construction Management and Economics, Vol. 4, pp. 213–232.

    Article  Google Scholar 

  • Moore, J. and Weatherford, L. (2001). Decision modeling with microsoft excel, 6th Ed. Prentice Hall, New Jersey.

    Google Scholar 

  • Navon, R. (1994). “Company-level cash flow management.” Journal of Construction Engineering and Management, Vol. 122, No. 1, pp. 22–29.

    Article  MathSciNet  Google Scholar 

  • Navon, R. (1995). “Resource-based model for automatic cash flow forecasting.” Construction Management and Economics, Vol. 13, pp. 501–510.

    Article  Google Scholar 

  • Navon, R. (1997). “Cash flow forecasting and management.” Proceedings of the Construction Congress V. ASCE, Minneapolis (USA), pp. 1056–1063.

    Google Scholar 

  • Park, H. K., Han, S. H., and Russell, J. S. (2005).” Cash flow forecasting model for general contractors using moving weights of cost categories.” Journal of Management in Engineering, Vol. 21, No. 4, pp. 164–172.

    Article  Google Scholar 

  • Peer, S. (1982). “Application of cost flow forecasting models.” Journal of the Construction Division, Proceedings of ASCE, Vol. 108, No. CO2, pp. 226–232.

    Google Scholar 

  • Purtell, M. L. (1982). “Problems in administering overseas projects.” Issues in Engineering. Journal of Professional Activities, Vol. 108, No. 2, pp. 140–144.

    Google Scholar 

  • Reinschmidt, K. F. and Frank, W. E. (1976). “Construction cash flow management system.” Journal of the Construction Division, Proceedings of ASCE, Vol. 102, No. CO4, pp. 615–627.

    Google Scholar 

  • Ross, S. A., Westerfield, R. W., and Jordan, B. D. (2007). Corporate finance: Essentials, 5th Ed. McGraw-Hill/Irwin, Boston.

    Google Scholar 

  • Sears, G. A. (1981). “CPM/COST: An integrated approach.” Journal of the Construction Division. Proceedings of the ASCE, Vol. 107, No. CO2, pp. 227–238.

    MathSciNet  Google Scholar 

  • Shen, L., Lee, R. K. H., and Zhang, Z. (1996). “Application of the BOT system for infrastructure projects in China.” Journal of Construction Engineering and Management, Vol. 122, No. 4, pp. 319–323.

    Article  Google Scholar 

  • Singh, S. and Lakanathan, G. (1992). “Computer-based cash flow model.” Proceedings of the 36th Annual Trans., AM. Association of Cost Engineers, AACE, pp. R.5.1–R.5.14.

    Google Scholar 

  • Tang, C. M., Leung, A. Y. T., and Lam, K. C. (2006). “Entopy application to improve construction finance decisions.” Journal of Construction Engineering and Management, Vol. 132, No. 10, pp. 1099–1113.

    Article  Google Scholar 

  • Tucker, S. N. and Rahilly, M. (1985). Computer user manual for program ‘FINCASH’: A program for predicting the cash flow of a single building project, Commonwealth Scientific and Industrial Research Organization (CSIRO), Division of Building Research, Melbourne, Australia.

    Google Scholar 

  • Wang, S. Q., Tiong, R. L. K., Ting, S. K., and Ashley, D. (2000). “Evaluation and management of political risks in china’s BOT projects.” Journal of Construction Engineering and Management, Vol. 126, No. 3, pp. 242–250.

    Article  Google Scholar 

  • Williams Jr., C. A. and Heins, R. M. (1989). Risk management and insurance, 6th Ed. McGraw Hill Co., New York, NY.

    Google Scholar 

  • Zhi, H. (1995). “Risk management for overseas construction projects.” International Journal of Project Management, Vol. 13, No. 4, pp. 231–237.

    Article  MathSciNet  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to Hyung Keun Park.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Han, S.H., Park, H.K., Yeom, S.M. et al. Risk-integrated cash flow forecasting for overseas construction projects. KSCE J Civ Eng 18, 875–886 (2014). https://doi.org/10.1007/s12205-014-0464-8

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s12205-014-0464-8

Keywords

Navigation