This article discusses a project being carried out in the BOF shop at the Chelyabinsk Metallurgical Combine to describe the experience of upgrading teeming cranes and increasing their load-carrying capacity. The cost of the upgrades was minimized by maximizing the use of the existing equipment and minimizing expenditures on equipment disassembly and assembly, commissioning, and startup.
Similar content being viewed by others
Author information
Authors and Affiliations
Additional information
Translated from Metallurg, No. 5, pp. 59–61, May, 2013.
Rights and permissions
About this article
Cite this article
Dmitriev, A.P., Tolstikov, A.N. & Dorokhin, S.O. Upgrading of a teeming crane in the BOF shop at the Chelyabinsk metallurgical combine. Metallurgist 57, 417–418 (2013). https://doi.org/10.1007/s11015-013-9747-4