Closure of the Bureya River in April 2016 and Filling of the Plinth of the Lower Bureya Dam

  • Published:
Power Technology and Engineering Aims and scope

At the preliminary design stage, the closure of the Bureya river was scheduled for October 20, 2015. The actual status of construction necessitated rescheduling the river closure for March 20, 2016, alteration of design discharges, 3D simulation, and adjustment of design solutions. The actual conditions of river closure on April 19, 2016 are described.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Reference

  1. Yu. G. Nikolaev and A. G. Yakobson, River Diversion during Construction of Hydraulic Structures [in Russian], Énergiya, Moscow (1978).

    Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to A. I. Il’inskaya.

Additional information

Translated from Gidrotekhnicheskoe Stroitel’svo, No. 3, March 2017, pp. 62 – 69.

Rights and permissions

Reprints and permissions

About this article

Check for updates. Verify currency and authenticity via CrossMark

Cite this article

Il’inskaya, A.I., Bobkov, A.V., Gara, V.S. et al. Closure of the Bureya River in April 2016 and Filling of the Plinth of the Lower Bureya Dam. Power Technol Eng 51, 274–280 (2017). https://doi.org/10.1007/s10749-017-0824-x

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s10749-017-0824-x

Keywords

Navigation