Minimizing the earliness/tardiness costs on parallel machine with learning effects and deteriorating jobs: a mixed nonlinear integer programming approach

  • ORIGINAL ARTICLE
  • Published:
The International Journal of Advanced Manufacturing Technology Aims and scope Submit manuscript

Abstract

In this study, we introduce a mixed nonlinear integer programming formulation for parallel machine earliness/tardiness (ET) scheduling with simultaneous effects of learning and linear deterioration, sequence-dependent setups, and a common due-date for all jobs. By the effects of learning and linear deterioration, we propose that the processing time of a job is defined by increasing function of its execution start time and position in the sequence. The developed model allows sequence-dependent setups and sequence-dependent early/tardy penalties. The model can easily provide the optimal solution to problems involving about eleven jobs and two machines.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

References

  1. Hino CM, Ronconi DP, Mendes AB (2005) Minimizing earliness and tardiness penalties in a single-machine problem with a common due date. Eur J Oper Res 160:190–201

    Article  MATH  Google Scholar 

  2. Baker KR (1994) Elements of sequencing and scheduling. HN, Hanover

  3. Baker KR, Scudder GD (1990) Sequencing with earliness and tardiness penalties: a review. Oper Res 38(1):22–36

    MATH  MathSciNet  Google Scholar 

  4. Bank J, Werner F (2001) Heuristics algorithms for unrelated parallel machine scheduling with a common due date, release dates and linear earliness tardiness penalties. Math Comput Model 33:363–383

    Article  MATH  MathSciNet  Google Scholar 

  5. Zhu Z, Heady RB (2000) Minimizing the sum of earliness/tardiness in multi-machine scheduling: a mixed integer programming approach. Comput Ind Eng 38:297–305

    Article  Google Scholar 

  6. Sun H, Wang G (2003) Parallel machine earliness and tardiness scheduling with proportional weights. Comput Oper Res 30:801–808

    Article  MATH  Google Scholar 

  7. Arkin EM, Roundy RO (1991) Weighted-tardiness scheduling on parallel machines with proportional weights. Oper Res 39(1):64–81

    MATH  MathSciNet  Google Scholar 

  8. Xiao W-Q, Li C-L (2002) Approximation algorithms for common due date assignment and job scheduling on parallel machines. IIE Transactions 34:467–477

    Article  Google Scholar 

  9. Radhakrishnan S, Ventura JA (2000) Simulated annealing for parallel machine scheduling with earliness-tardiness penalties and sequence-dependent set-up times. Int J Prod Res 38(10):2233–2252

    Article  MATH  Google Scholar 

  10. Yi Y, Wang DW (2003) Soft computing for scheduling with batch setup times and earliness-tardiness penalties on parallel machines. J Intell Manuf 14:311–322

    Article  Google Scholar 

  11. Chang P-C, Chen S-H, Lin K-L (2005) Two-phase sub population genetic algorithm for parallel machine-scheduling problem. Expert Syst Appl 29:705–712

    Article  Google Scholar 

  12. Caoa D, Chena M, Wanb G (2005) Parallel machine selection and job scheduling to minimize machine cost and job tardiness. Comput Oper Res 32:1995–2012

    Article  Google Scholar 

  13. Anghinolfi D, Paolucci M (2007) Parallel machine total tardiness scheduling with a new hybrid metaheuristic approach. Comput Oper Res DOI 10.1016/j.cor.2006.02.009

  14. Sourd F (2005) Earliness/tardiness scheduling with setup considerations. Comput Oper Res 32:1849–1865

    Article  MATH  MathSciNet  Google Scholar 

  15. Lopes MJP, de Carvalho JMV (2007) A branch-and-price algorithm for scheduling parallel machines with sequence dependent setup times. Eur J Oper Res 176(3):1508–1527

    Article  MATH  Google Scholar 

  16. Mosheiov G (2001) Scheduling problems with a learning effect. Eur J Oper Res 132:687–693

    Article  MATH  MathSciNet  Google Scholar 

  17. Biskup D (1999) Single-machine scheduling with learning considerations. Eur J Oper Res 115:173–178

    Article  MATH  Google Scholar 

  18. Mosheiov G, Sidney JB (2003) Scheduling with general job-dependent learning curves. Eur J Oper Res 147:665–670

    Article  MATH  MathSciNet  Google Scholar 

  19. Eren T, Güner E (2007) Minimizing total tardiness in a scheduling problem with a learning effect. Appl Math Model 31(7):1351–1361

    Article  MATH  Google Scholar 

  20. Koulamas C, Kyparisis GJ (2007) Single machine and two machine flowshop scheduling with general learning functions. Eur J Oper Res 178(2):402–407

    Article  MATH  MathSciNet  Google Scholar 

  21. Kuo WH, Yang DL (2006) Minimizing the total completion time in a single machine scheduling problem with a time dependent learning effect. Eur J Oper Res 174(2):1184–1190

    Article  MATH  MathSciNet  Google Scholar 

  22. Kuo WH, Yang DL (2006) Single machine group scheduling with a time dependent learning effect. Eur J Oper Res 33:2099–2112

    MATH  MathSciNet  Google Scholar 

  23. Chen P, Wu C-C, Lee W-C (2006) A bi-criteria two-machine flowshop scheduling problem with a learning effect. J Oper Res Soc 57(9):1113–1125

    Article  Google Scholar 

  24. Mosheiov G (1996) ∧-shaped policies to schedule deteriorating jobs. J Oper Res Soc 47:1184–1191

    Article  MATH  Google Scholar 

  25. Gupta JND, Gupta SK (1988) Single facility scheduling with nonlinear processing times. Comput Ind Eng 14:387–393

    Article  Google Scholar 

  26. Kunnatur AS, Gupta SK (1990) Minimizing the makespan with late starts penalties added the processing times in a single facility scheduling problem. Eur J Oper Res 47:56–64

    Article  Google Scholar 

  27. Browne S, Yechiali U (1990) Scheduling deteriorating jobs on a single processor. Oper Res 38:495–498

    MATH  Google Scholar 

  28. Alidaee B, Womer NK (1999) Scheduling with time dependent processing times: review and extensions. J Oper Res Soc 50(7):711–720

    Article  MATH  Google Scholar 

  29. Mosheiov G (1994) Scheduling jobs under simple linear deterioration. Comput Oper 21(6):653–659

    Article  MATH  Google Scholar 

  30. Mosheiov G (1991) V-shaped policies for scheduling deteriorating jobs. Oper Res 39:979–991

    Article  MATH  MathSciNet  Google Scholar 

  31. Hsu YS, Lin BMT (2003) Minimization of maximum lateness under linear deterioration. Omega 31:459–469

    Article  Google Scholar 

  32. Wang JB, Xia ZQ (2006) Flow shop scheduling with deteriorating jobs under dominating machines. Omega 34:327–336

    Article  MathSciNet  Google Scholar 

  33. Wang JB, Ng CTD, Cheng TCE, Liu LL (2006) Minimizing total completion time in a two-machine flow shop with deteriorating jobs. Appl Math Comput 180(1):185–193

    Article  MATH  MathSciNet  Google Scholar 

  34. Wang X, Cheng TCE (2007) Single-machine scheduling with deteriorating jobs and learning effects to minimize the makespan. Eur J Oper Res 178(1):57–70

    Article  MATH  MathSciNet  Google Scholar 

  35. Wang JB (2007) Single-machine scheduling problems with the effects of learning and deterioration. Omega 35(4):397–402

    Article  Google Scholar 

  36. Wang JB (2007) Flow shop scheduling problems with decreasing linear deterioration under dominant machines. Comput Oper Res 34(7):2043–2058

    Article  MATH  Google Scholar 

  37. Wu CC, Lee WC (2006) Two-machine flowshop scheduling to minimize mean flow time under linear deterioration. Int J Prod Econ 103(2):572–584

    Article  Google Scholar 

  38. Kang L, Ng CT (2006) A note on a fully polynomial-time approximation scheme for parallel-machine scheduling with deteriorating jobs. Int J Prod Econ DOI 10.1016/j.ijpe.2006.11.014

  39. Cheng TCE, Kang L, Ng CT (2004) Due-date assignment and single machine scheduling with deteriorating jobs. J Oper Res Soc 55(2):198–203

    Article  MATH  Google Scholar 

  40. Sundararaghavan PS, Kunnathur AS (1994) Single machine scheduling with start time dependent processing time: some solvable cases. Eur J Oper Res 78(3):394–403

    Article  MATH  Google Scholar 

  41. Mosheiov G (1995) Scheduling jobs with step-deterioration: minimizing makespan on a single and multi-machine. Comput Ind Eng 28(4):869–879

    Article  Google Scholar 

  42. Cheng TCE, Ding Q, Kovalyov MY, Bachman A, Janiak A (2003) Scheduling jobs with piecewise linear decreasing processing times. Nav Res Log 50(6):531–554

    Article  MATH  MathSciNet  Google Scholar 

  43. Kunnatur AS, Gupta SK (1990) Minimizing the makespan with late starts penalties added the processing times in a single facility scheduling problem. Eur J Oper Res 47:56–64

    Article  Google Scholar 

  44. Kubiak W, Van de Velde S (1998) Scheduling deteriorating jobs to minimize makespan. Nav Res Log 45:511–523

    Article  MATH  Google Scholar 

  45. Gupta JND, Gupta SK (1988) Single facility scheduling with nonlinear processing times. Comput Ind Eng 14:387–393

    Article  Google Scholar 

  46. Voutsinas GT, Pappis CP (2002) Scheduling jobs with values exponentially deteriorating over time. Int J Prod Econ 79:163–169

    Article  Google Scholar 

  47. Cheng TCE, Ding Q, Lin BMT (2003) A concise survey on the scheduling problems with deteriorating processing times. Eur J Oper Res 152:1–13

    Article  MathSciNet  Google Scholar 

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to M. Duran Toksarı.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Toksarı, M.D., Güner, E. Minimizing the earliness/tardiness costs on parallel machine with learning effects and deteriorating jobs: a mixed nonlinear integer programming approach. Int J Adv Manuf Technol 38, 801–808 (2008). https://doi.org/10.1007/s00170-007-1128-3

Download citation

  • Received:

  • Accepted:

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/s00170-007-1128-3

Keywords

Navigation