An integrated system for ship construction projects control using risk analysis

  • Floriano C. M. PiresJrEmail author
  • Luiz Felipe Assis
  • Mauro Rezende
  • Claudio L. Baraúna Vieira
  • Silvia S. C. Botelho
  • Nelson Duarte Filho
Article
  • 4 Downloads

Abstract

The Brazilian shipbuilding industry is presently showing significant recovery prospects. However, there are some problems affecting this process. The high level of builder’s risk perceived by the owners and, mainly, by banks, insurance companies and other stakeholders, is likely the most critical.

The main instrument to keep the risk in acceptable levels is a strict control of the construction progress. However, some shipowners have been employing control systems that are excessively complex, detailed and expensive, but, at same time, not sufficiently effective.

This paper presents the main characteristics of a computer system developed to provide a broad control over the construction progress and financial balance as well as a continuous risk assessment.

Keywords

Shipbuilding project management risk analysis 4D-CAD visualization. 

Preview

Unable to display preview. Download preview PDF.

Unable to display preview. Download preview PDF.

References

  1. Jongeling, R. and Olofsson, T. (2007), “A Method for Planning of Work-Flow by Combined use of Location-Based Scheduling and 4D CAD”. Automation in Construction, Vol 16 (2), pp. 189–198.CrossRefGoogle Scholar
  2. Lee, E., Shin, J.G., and Park, Y. (2007), “A Statistical Analysis of Engineering Project Risks in the Korean Shipbuilding Industry”. Journal of Ship Production, Vol. 23 (4); pp. 223–230.Google Scholar
  3. Pires Jr, F. (1999), “An assessment of Brazilian shipbuilding competitive potential”. Journal of Ship Production, Vol 15 (2), pp. 114–125.Google Scholar
  4. Pires Jr, F., Assis, L. F., and Souza, C. M (2005), “An analysis of the Brazilian ship financing system”. Maritime Policy and Management, Vol 32 (3), pp. 209–226.CrossRefGoogle Scholar
  5. Pires Jr, F., Guimaraes, L. F. and Assis, L. F. (2009), “Risk analysis in shipbuilding contracts”. Proceedings of International Maritime Association of Mediterranean.Google Scholar
  6. PMI (2008), A Guide to the Project Management Body of Knowledge. Project Management Institute.Google Scholar

Copyright information

© Sociedade Brasileira de Engenharia Naval 2013

Authors and Affiliations

  • Floriano C. M. PiresJr
    • 1
    Email author
  • Luiz Felipe Assis
    • 1
  • Mauro Rezende
    • 1
  • Claudio L. Baraúna Vieira
    • 1
  • Silvia S. C. Botelho
    • 2
  • Nelson Duarte Filho
    • 2
  1. 1.Rio de Janeiro Federal UniversityBrazil
  2. 2.Rio Grande Federal UniversityBrazil

Personalised recommendations