Skip to main content
Log in

New testing methods and new testing tools for systems utilizing substation communication networks

Neue Prüfmethoden und Werkzeuge für Systeme mit Kommunikationsnetzwerken in Schaltanlagen

  • Originalarbeiten
  • Published:
e & i Elektrotechnik und Informationstechnik Aims and scope Submit manuscript

Abstract

The upcoming standard IEC 61850 prepares the ground for the broad application of data communication networks and systems in substations. With the new systems becoming installed, new testing methods and tools will be required in addition to the established ones. Also the established methods need some adaption to the new situation.

This paper gives an overview about the technology, the possible effects on testing, and outlines test methods and tools to be applied.

Zusammenfassung

Die entstehende Norm IEC 61850 schafft die Voraussetzungen für die breite Anwendung von Kommunikationsnetzwerken und -systemen in Schaltanlagen. Mit der Installation dieser neuen Systeme werden auch neue Prüfmethoden und Prüfwerkzeuge erforderlich sein. Die etablierten Methoden werden ebenfalls eine gewisse Anpassung an die neue Situation benötigen.

Diese Arbeit gibt einen Überblick über die Technologie, die möglichen Auswirkungen auf das Prüfen und umreißt Prüfmethoden und Werkzeuge, die zur Anwendung kommen können.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Abbreviations

Current:

Transformer

EPRI:

Electric Power Research Institute, Palo Alto, California, U.S.A.

GOMSFE:

Generic Object Model for Substation and Feeder Equipment

GOOSE:

Generic Object Oriented Substation Event

GSSE:

Generic Substation Event

IED:

Intelligent Electronic Device

PT:

Potential Transformer

SAV:

Sampled Analog Values

SCADA:

Supervisory, Control, and Data Acquisition

SCL:

Substation Configuration Language

UCA:

Utility Communication Architecture

XML:

Extended Markup Language

References

  • Committee Draft for IEC 61850-8-1. Part 8-1: Specific Communication Service Mapping (SCSM) — Mapping to MMS (ISO/IEC 9506 Part 1 and Part 2) over ISO 8802-3. IEC document number 57/564/CD.

  • Committee Draft for Voting for IEC 61850-6. Part 6: Substation Automation System Configuration Description Language. IEC document number 57/581/CC.

  • Final Draft for International Standard IEC 61850-5. Part 5: Communication Requirements for Functions and Device Models. IEC document number 57/604/RVC.

  • International Standard IEC 61850-3. Part 3: General requirements.

Download references

Author information

Authors and Affiliations

Authors

Corresponding author

Correspondence to F. Steinhauser Dipl.-Ing. Dr. techn..

Rights and permissions

Reprints and permissions

About this article

Cite this article

Steinhauser, F. New testing methods and new testing tools for systems utilizing substation communication networks. Elektrotech. Inftech. 120, 429–432 (2003). https://doi.org/10.1007/BF03053974

Download citation

  • Published:

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF03053974

Keywords

Schlüsselwörter

Navigation