Characteristics of the design of the hydropower equipment of the purnari-II hydroelectric station

  • Power Construction Abroad
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    The experience of design works on the hydropower equipment of a hydrostation as large of a large number of suppliers requires a technical coordinator of the works with strict obligations on coordinating the designs of equipment with this coordinator before sending to the customer.

  2. 2.

    At the stage of preparing the tender documents for complete delivery of hydrostation equipment it is necessary to enlist a design organization for a general assessment of the layout of equipment given in the tender drawings, for preparing alternative variants of the layout, and simplifying the process of final coordination of changes in the contract specifications in the case of winning the tender.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel’stvo, No. 3, pp. 52–54, March, 1998.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Linyuchev, V.A. Characteristics of the design of the hydropower equipment of the purnari-II hydroelectric station. Hydrotechnical Construction 32, 171–173 (1998). https://doi.org/10.1007/BF02905900

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02905900

Keywords

Navigation