Consutruction and assembly works in the underground complex are combined with operation of the units at the Hoa-Binh hydroelectric station

  • Engineering Calculations and Production Efficiency
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    For underground machine halls with a large number of units the areas of the assembly floors should be 1.5–2 times greater than for outdoor hydrosation powerhouses. Zones of the MH adjacent to the vehicular tunnels cannot enter into these areas; these zones should be regarded only as loading areas.

  2. 2.

    The technology of excavating the underground machine hall, including pits for the draft tubes, introduced at the Hoa-binh hydrostation can be recommended for excavating large chambers of considerable length.

  3. 3.

    The use of the given technical solutions when constructing underground hydroelectric station and pumped-storage stations in combination with fulfillment of par. 1 of the “CONCLUSIONS” will make it possible to reduce considerably the total construction time of underground machine halls and to provide start-up of all units.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 1, pp. 29–39, January, 1996.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Sklyarenko, A.V. Consutruction and assembly works in the underground complex are combined with operation of the units at the Hoa-Binh hydroelectric station. Hydrotechnical Construction 30, 22–33 (1996). https://doi.org/10.1007/BF02446380

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02446380

Keywords

Navigation