Polymer waterproofing of internal surfaces of headrace conduits at the Dneprogés-II hydroelectric plant

  • Papers
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    Construction and operation experience showed the effectiveness of and good prospects for the use of epoxycoal tar coatings for waterproofing pressure conduits.

  2. 2.

    The effectiveness, operating capacity, and durability of epoxy-coal tar waterproofings depend not only on the correct and well-grounded selection of the type of waterproofing, but also on the observance of all requirements contemplated in the techniques for carrying out waterproofing work.

  3. 3.

    High quality epoxy-coal tar coatings can be guaranteed on carefully prepared concrete surfaces; this should be taken into account in the design of waterproofings and in the preparation of projects for organizing and carrying out construction-erection work.

  4. 4.

    Since the application of waterproofings on intermal surfaces of conduits, which have, as a rule, pronounced slopes, and call for considerable additional expenditure in the erection and dismantling of scaffolds, in those cases in which it is possible to ensure crack resistance of the conduits by using additional reinforcement or increasing the area of the concrete sections, the use of waterproofings should be justified by economic analyses.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Literature Cited

  1. Design Norms “Waterproofing of Power Structures, VSN 37-70” [in Russian], Minénergo of the USSR (1972).

  2. V. I. Sakharov and V. F. Michko, “Paint coal tar epoxy waterproofing of hydraulic structures,” Énergeticheskoe Stroitel’stvo, No. 8 (1972).

  3. V. I. Sakharov and V. F. Michko, “Reinforced epoxy coal tar waterproofing,” Gidrotekh. Stroitel’., No. 3 (1974).

  4. V. I. Sakharov and V. F. Michko, “Reinforced coal-tar epoxy waterproofing of structures of the Karshi main canal,” Énergeticheskoe Stroitel’stvo, No. 2 (1973).

Download references

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel’stvo, No. 3, pp. 11–16, March, 1976.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Verezemskaya, N.A., Karaban, V.M., Milin, A.M. et al. Polymer waterproofing of internal surfaces of headrace conduits at the Dneprogés-II hydroelectric plant. Hydrotechnical Construction 10, 233–240 (1976). https://doi.org/10.1007/BF02407365