Experience in operating the Lenin Karakum Canal headworks

  • Papers
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    Desilting of the water taken in from the Amudarya River in settling basins and removal of the sediment from them is the main operational undertaking at the Karakum Canal Headworks. Dumping of a substantial quantity of sediment removed from these settling basins into the river causes overloading of the stream and silting, which entails a rise of the river bed and of water levels to an extent endangering the regulating structures. The basic solution of the sediment regime regulation at the canal intake is to transport the major part of it into large offstream reservoirs, now being planned, and to accumulate the sediment in them.

  2. 2.

    An effective means of combating channel erosion and shifting of the channels of the canals toward the concave bank are straightening cuts in these areas.

  3. 3.

    In reaches with systematic channel erosion (in connection with the greater than planned slope resulting from the elimination from the project of a partitioning structure at kilometer 50) and on silted oxbow lakes, the stream forms a channel sufficient to pass ever-increasing discharges of the water intake.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Literature Cited

  1. Kh. Sh. Shapiro, “Methodology of calculating total channel silting in the lower pools of low-head hydrocenters on the Amudarya River,” Gidrotikhnicheskoe Stroitel'stvo, No. 3 (1969).

Download references

Authors

Additional information

Translated from Gidrotikhnicheskoe Stroitel'stvo, No. 12, pp. 20–23, December, 1971.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Shapiro, K.S., Sergeev, Y.P., Sorotokin, M.M. et al. Experience in operating the Lenin Karakum Canal headworks. Hydrotechnical Construction 5, 1122–1125 (1971). https://doi.org/10.1007/BF02403548

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02403548

Keywords

Navigation