Conclusions
-
1.
The method of constructing dams by directed blasting is promising in the construction of high and superhigh dams, not only because it reduces construction time and labor costs but also in the case of massive blasts one obtains optimal mixtures of the large-sized rocks which by compaction by the powerful dynamic action of the drop can produce denser and less deformable dams than in the case of construction by the usual methods.
-
2.
The percolating and piping properties and the nonuniformity of the material in dams constructed by blasting for all practical purposes do not differ from dams filled layerwise. To create a dam which is uniform with respect to percolating properties by the blasting method, it is necessary to use special measures for additional crushing of individual zones or plugging of the dam material.
-
3.
For a substantiated design of large dams constructed by blasting, we need further detailed investigations of the processes occurring during blasting and dropping of large masses of rock. The height of experimental dams should be at least 20–30 meters.
Similar content being viewed by others
Literature Cited
G. Deresevich “Mechanics of granular material,” Probl. Mekhan., No. 3 (1961).
V. K. Rubtsov, “Boring and blasting work at borrow pits to obtain rock with a prescribed particle-size distribution,” in: Summaries of Reports of the Joint Conference on Problems of Research, Design, and Construction of Earth Dams [in Russian], VNIIG, October–November (1967).
N. P. Lushnov, “Structure of the particle distribution and angle of repose of stone in rock, fill,” VNII VODGEO, No. 2 (1965).
N. P. Lushnov, Control of the Particle-Size Distribution of Stone in Earth Dams [in Russian], VNII VODGEO (1965).
G. I. Pokrovskii N. S. Fedorov, and M. M. Dokuchaev, Use of Directed Blasting, in Hydraulic Engineering [in Russian], Gosstroiizdat, Moscow (1963).
K. K. Kuz'min, “Catastrophic flash flood of 1973 and the Medeo dam,” Gidrotekh. Stroitel'., No. 3 (1974).
G. N. Petrov and L. S. Reifman, “Investigations of the shoulders of an earth dam constructed in large layers,” Énergeticheskoe Stroitel'stvo, No. 9 (1969).
D. A. Zhigarev, G. N. Petrov, and L. S. Riefman, “Scientific and experimental substantiation of the technology of constructing the Charvak hydroelectric station, dam,” Trudy Gidroproekt, No. 32 (1973).
Additional information
Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 10, pp. 15–19, October, 1975.
Rights and permissions
About this article
Cite this article
Petrov, G.N., Reifman, L.S. & Khusankhodzhaev, F.Z. Dam construction by blasting. Hydrotechnical Construction 9, 938–944 (1975). https://doi.org/10.1007/BF02378065
Issue Date:
DOI: https://doi.org/10.1007/BF02378065