Concrete work on construction of the arch dam for the Chirkey hydroelectric station

  • Papers
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    The concreting technology work adopted during construction of the Chirkey arch dam, including the delivery of concrete by cableway, intrablock mechanization on concrete and preparatory work, and the stringent sequence of preparing and concreting the blocks, permits performing work with a high quality and labor productivity, providing for raising the dam 7–8 m per month.

  2. 2.

    In order to further improve technology it is necessary to increase the speed of the cableways and their reliability, improve control of the bucket valve, and introduce motorized power buses or power buses on rails.

  3. 3.

    The means of intrablock mechanization developed at the construction site proved its high effectiveness and can be used under any climatic conditions on blocks with a small area and with reinforcement. It is expedient to create a family of such plant-manufactured machines, which will increase their reliability and output.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Literature Cited

  1. V. A. Portnov and A. V. Sklyarenko, “Experience in organizing construction work for the arch dam of the Chirkey hydrodevelopment,” Énergeticheskoe Stroitel'stvo, No. 8 (1974).

  2. A. P. Bechin et al., “Technical and economic effectiveness of the craneless method of concreting,” Gidrotekh. Stroitel'., No. 5 (1974).

  3. L. A. Tolkachev, “Experience in concreting the Toktogul hydroelectric station dam,” Gidrotekh. Stroitel'., No. 12 (1971).

  4. B. K. Frolov, “Construction of the Libby hydrodevelopment,” Énergeticheskoe Stroitel'stvo Za Rubezhom, No. 6 (1970).

  5. B. K. Frolov, Features of concrete work in the construction of two large hydroschemes in the USA,” Gidrotekh. Stroitel'., No. 11 (1971).

  6. E. A. Dolginin and E. E. Liskun, “Concreting operations at the Krasnoyarsk hydroelectric plant,” Gidrotekh. Stroitel'., No. 9 (1972).

Download references

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 10, pp. 9–12, October, 1975.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Danilov, A.S., Portnov, V.A. & Sklyarenko, A.V. Concrete work on construction of the arch dam for the Chirkey hydroelectric station. Hydrotechnical Construction 9, 927–933 (1975). https://doi.org/10.1007/BF02378063

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02378063

Keywords

Navigation