Transport tunnel No. 3 at the Nurek damsite

  • Papers
  • Published:
Hydrotechnical Construction Aims and scope

Conclusions

  1. 1.

    During the construction of the Nurek dam the necessity of building a transport tunnel on a road in the reservoir area, not envisaged in the earlier plan, became evident.

  2. 2.

    On completion of stage I a part of tunnel No. 3 will be rebuilt and used as a permanent structure.

  3. 3.

    In the transport tunnel No. 3 a simplified lining consisting of reinforced-concrete anchors and sprayed-concrete lining of 5-cm average thickness has been used over considerable lengths. Systematic observations are being conducted on the behavior of this lining.

This is a preview of subscription content, log in via an institution to check access.

Access this article

Price excludes VAT (USA)
Tax calculation will be finalised during checkout.

Instant access to the full article PDF.

Similar content being viewed by others

Authors

Additional information

Translated from Gidrotekhnicheskoe Stroitel'stvo, No. 5, pp. 9–11, May, 1970.

Rights and permissions

Reprints and permissions

About this article

Cite this article

Ilyushin, V.F., Perdikis, K.D. Transport tunnel No. 3 at the Nurek damsite. Hydrotechnical Construction 4, 394–398 (1970). https://doi.org/10.1007/BF02376134

Download citation

  • Issue Date:

  • DOI: https://doi.org/10.1007/BF02376134

Keywords

Navigation